137 F. 731 | 9th Cir. | 1905
after making the foregoing statement, delivered the opinion of the court.
Appellants claim that “the finding that plaintiffs performed the work is wholly unsustained by the evidence.” It will be observed that under the contract the three holes were to be sunk to bedrock. Counsel for appellants admit that the testimony in relation to holes 1 and 2 is clear, positive, direct, and certain. They were sunk “to bedrock.” The controversy between the parties is confined solely to hole 3. Was it sunk to bedrock ?
O. A. Nelson, one of the plaintiffs in the court below, testified, among other things, as follows: “Q. Did you do anything under that arrangement in the way of carrying out the agreement? A. I fulfilled the contract.”
It is argued that this answer was a mere conclusion of law, not constituting any legal evidence which this court should consider as tending to show the fact that the hole was sunk to bedrock. The record shows that no objection was made. by defendants to this answer as being a mere conclusion. No motion was made to strike the testimony
Again, in the further course of his examination the following question and answer appear: “Q. Will you state the depth to bedrock? A. The first hole was a strong 16
We are unable to accept the statement of the learned counsel for appellants “that this answer asserts nothing more positively than that the first hole went down a foot into bedrock, that the second hole went to bedrock, and that the third hole was 22 feet deep.” The answer must be considered with reference to the question asked as to the depth of the three holes to bedrock. To answer the question the statement of the witness as to the first hole being “one foot down in the bedrock,” and the second hole “to bedrock,” was mere surplusage, and it was unnecessary for the witness to repeat the words “to bedrock” in respect to the third hole in order to complete the answer to the question as asked. Suppose the question had been asked, “What was the depth of the third hole to bedrock? and the answer given, “22 feet or about that.” Would not that have been a complete, direct, and positive answer to the question ? The question was a leading one, but no objection was taken to it, and the answer must be accepted as evidence.
This is the only positive and direct evidence on this point. In this connection it is deemed proper to state that the evidence in the record shows clearly that the defendants, having been informed by the plaintiffs that they had fulfilled the contract, took no steps to visit or examine the holes with the view of satisfying themselves that the contract had or had not been completed until about five months after such information was given, and then the banks of the holes were caved in, and the facts could not be ascertained by an investigation of the holes. In the meantime, according to the testimony of the defendants, “property constantly increased in value on Fairbanks Creek from the time these shafts were sunk.” It was some time in November, 1903, when defendants “felt pretty certain that the contract was not fulfilled”; they heard reports “that there was something that was not what it ought to be.” So defendants concluded to sink shafts near the' holes sunk by plaintiffs, and went down to bedrock to run drifts under the holes sunk by plaintiffs, in order to ascertain whether
Gibbs, speaking of the variation, said: “At the back end of the hole it must have varied at least three feet. We obtained the direction of that hole. * * * I placed the stick in the bottom of the hole, looking right at the center of the drift on the back, and left the candle there, and when I got on top there was the stick pointing off to the left, and there was Nelson’s hole to the right of the stick.”
Crabbe testified: “We went to hole No. 3, and measured that from the top — put the same stick across to get the center location of the hole. It was 22 feet and 8 inches deep. The length of the drift was 10 feet 4 inches as it ran in, and, as near as we could come to telling from our pole on the top, it was bearing off to the left. Q. How much? A. About 4 or 5 feet anyway — at the least; I could not ex
To illustrate the character of the testimony upon the part of the defendants as to the work done by them, we take the witness Boss, who had taken a lay from defendants on a part of the ground. He testified that the drift in shaft 2 bore a little to the left of hole 2: “In a distance of 12 feet I should judge it was about 15 or 18 inches. Q. Where did it strike the old shaft? A. Under the up-hill end of the shaft. Q. How much of the old shaft did it expose? A. I don’t know.”
With reference to shaft 3, sunk by defendants, he said: “The hole was sunk 23 feet and 3 inches, and the drift was driven 11 feet and 6 inches. * * * Q. How did this drift compare with reference to the old shaft? A. As near as I could judge, exactly to the center. * * * Q. What was the result'of the exposure made at any part of this drift with reference to the old shaft? A. Well, we didn’t see anything that looked like an old shaft there. It was what I supposed to be solid gravel.”
In his cross-examination he said that they ran a drift 11 feet “to be sure we had got over far enough” to reach the hole sunk by Nelson and Hensley. The drift which was run was larger at the starting point than it was at the end.
“Q. Did you enlarge that hole and widen it so there would be no chance of your missing it? A. No, sir.”
Zeimer, a witness for the defendants, testified that he went into shaft 3, and measured the drift back about 11 feet and a half. “We went there to find out whether this drift ran under the other shaft, and we lined it up with the other shaft. * * * We put a pole down the bottom, and lined it up on top the same way. * * * Found out that they were in line. Q. Did you make any examination of the drift with reference to that shaft, to see what that ¿howed as to bedrock? A. I could not say whether that goes to bedrock or not. I didn’t have no pick.”
After the conclusion of the testimony the court desired “more accurate information in relation to the location of the shafts sunk by Nelson and Hensley on the upper end
It is apparent from the decree rendered by the court that it did not consider the report of the surveyor established the fact, as claimed by the appellees, that hole No. 3, sunk by Nelson and Hensley, did not go to bedrock. The bedrock at the bottom of the holes was not level. The contract did not require that the entire bottom of the holes should disclose bedrock. If any part of the hole went to bedrock the contract was complied with. The fact that a tunnel run from the new shaft Number Three would tap the Nelson shaft, as stated in the report, does not prove that the Nelson shaft or hole Number Three was not sunk “22 feet or about that” to bedrock.
In equity causes the rule is well settled ¿hat the findings of the court below upon the facts are to be taken as presumptively correct, and unless an obvious error has intervened in the application of the law, or some serious or important mistake has been made in the consideration of 'the evidence, the decree should not be disturbed. Warren v. Burt, 58 F. 101, 106, 7 C.C.A. 105; Stuart v. Hayden, 72 F. 402,
After a careful examination of all the evidence, we are unwilling to say that the court below committed any mistake in the consideration of the evidence applicable to the points under discussion, or the conclusion which it deduced therefrom. The court had the witnesses before it, and had knowledge of the conditions existing in the vicinage where the holes were sunk, and was, in the very nature of things, better able to understand and apply the testimony of witnesses than we are.
It is true that specific performance, as claimed by appellants, is not a matter of absolute right, but rests entirely in judicial discretion, to be exercised according to the settled principles of equity so as to reach the ends of justice. Snow v. Nelson (C.C.) 113 F. 353, 356; Willard v. Tayloe, 8 Wall. 557, 19 L.Ed. 501; Story, Eq.Jur. § 742.
As is said in 26 Am. & Eng.Ency.Law (2d Ed.) 67: “It must appear that the contract is fair, just, and equitable in all its parts. If, therefore, a decree of specific performance would work hardship or injustice upon the defendant, or operate oppressively upon him, a court of equity will decline to interfere.”
The contract was fair and just between the parties, and the record herein does not show that its enforcement would work any hardship or injustice upon the defendants. The fact that it was shown by the complaint that one McMahon had an interest in the premises did not deprive defendants from establishing their rights, if any they had, as against the plaintiffs herein, and the record shows that in the answer of McMahon he asks that his interest in the premises “be not determined in this action.”
The decree of the District Court is affirmed, with costs.