105 N.E. 653 | NY | 1914
Lead Opinion
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *348 The trial justice held that the contract in question was to be wholly performed in the state of Pennsylvania, and the law of that state holding the contract valid and enforceable governed its operation and effect, consequently the plaintiff could not succeed in this action for the reason that submission to arbitration was a valid condition precedent which had not been complied with.
The clause of the contract, quoted in the statement of facts, confers upon the engineer, the arbitrator, power to determine the effect of any stipulation of the contract and whether or not there has been a performance of the same by either party, and to decide "all matters in dispute arising or growing out of thecontract." It further provides not only that the decision of the engineer as arbitrator shall be final and conclusive between the parties, but each party "waives all right of action, suit orsuits or other remedy in law or otherwise under this contract orarising out of the same to enforce any claim except as the sameshall have been determined by said arbitrator."
Numerous cases involving contracts containing clauses relating to arbitration have been before this court for consideration. InPrest., etc., Delaware Hudson Canal Co. v. Pennsylvania CoalCompany (
In Guaranty Trust S.D. Co. v. Green Cove S. M.R.R. Co. (
"It is hereby stipulated and agreed, by and between this association and the member named herein and his beneficiary, that the issues in any action brought against it under this certificate shall, on the demand of this association or its attorney, be referred for trial to a referee to be appointed by the court in which such action is brought."
An order of reference made against the objection of plaintiff was reversed by the General Term, and the latter order was affirmed by this court, which held that the clause of the contract above quoted was contrary to public policy and not binding on the parties thereto.
Tested by the principles of the cases cited, we conclude that the language employed in the contract in question is susceptible of but one construction, namely, an attempt on the part of the parties to the same to enter into an independent covenant or agreement to provide for an adjustment of all questions of difference arising between the parties by arbitration to the exclusion of jurisdiction by the courts.
Notwithstanding the decisions of the courts of Pennsylvania that the contract as to arbitration was valid and enforceable in that state, judicial comity does not require us to hold that such provision of a contract which is contrary *352
to a declared policy of our courts (White v. Howard,
As a new trial must be ordered in this case, we conclude that the engineer mentioned in the contract in controversy between the parties had reference to the engineer at the time that the several acts were to be performed by such officer, and that the decease of the first engineer did not prevent his successor from performing all of the obligations of the contract to be performed by him.
The judgment should be reversed and a new trial ordered, costs to abide the event.
Concurrence Opinion
An agreement that all differences arising under a contract shall be submitted to arbitration relates to the law of remedies, and the law that governs remedies is the law of the forum. In applying this rule, regard must be had not so much to the form of the agreement as to its substance. If an agreement that a foreign court shall have exclusive jurisdiction is to be condemned (Benson v. Eastern B. L. Assn.,
A very similar question was involved in Benson v. EasternBldg. L. Assn. (
"We think this argument proves too much. It is difficult *354
to see why it would not uphold an agreement that all claims against the parties should be determined by arbitrators and not by the courts. It might be said with as much force in such a case as in the one now before us that the cause of action could, under the agreement, accrue only on the decision of the arbitrators. Yet nothing is better settled than that agreements of the character mentioned are void. (Greason v. Keteltas,
Building contracts are made in New York to be performed all over the United States. If the judgment of the court below is to stand, jurisdiction over controversies arising under such contracts may be withdrawn from our courts and the litigation remitted to arbitrators in distant states. The presence of the parties here, the ownership of property in this jurisdiction, these and other circumstances may make resort to our courts essential to the attainment of justice. If jurisdiction is to be ousted by contract, we must submit to the failure of justice that may result from these and like causes. It is true that some judges have expressed the belief that parties ought to be free to contract about such matters as they please. In this state the law has long been settled to the contrary. (Sanford v. CommercialTravelers' Mut. Acc. Assn., 86 Hun, 380;
I concur with Judge HOGAN and vote for reversal.
HISCOCK, CHASE and CUDDEBACK, JJ., concur; WILLARD BARTLETT, Ch. J., dissents; MILLER, J., not sitting.
Judgment reversed, etc. *355