MD Electrical Contractors, Inc. v. AbramsMD Electrical Contractors, Inc. v. Abrams
Lead Opinion
delivered the judgment of the court, with opinion.
Chiеf Justice Thomas and Justices Fitzgerald, Kilbride, and Karmeier concurred in the judgment and opinion.
Justice Freeman dissented, with opinion, joined by-Justice Burke.
OPINION
Plaintiff, MD Electrical Contractors, Inc., filed suit against defendants Fred and Carol Abrams, under a theory of quantum meruit to recover for services that it rendered as a subcontractor on defendants’ home improvement project. Defendants moved to dismiss the case pursuant to section 2 — 619 of the Code of Civil Procedure (Code) (
This court allowed defendants’ petition for leave to appeal pursuant to Supreme Court Rule 315 (210 Ill. 2d R. 315). Defendants assert on appeal that: (1) the Home Repair and Remodeling Act applies to subcontractors and plaintiff is, therefore, precluded from recovery bеcause it did not comply with the terms of the Act; (2) regardless of the applicability of the Act to subcontractors, plaintiff is prohibited from recovery under quantum meruit because there was no direct relationship between plaintiff and defendants. For the reasons stated below, we affirm the judgment of the appellate court.
BACKGROUND
On November 2, 2005, plaintiff, an Illinois corporation, filed its first amended complaint, which is the subject of this case. Plaintiff alleged that from June 6, 2004, through October 1, 2004, it was a subcontractor that provided labor, electrical equipment, and materials (which we collectively refer to as “services”) toward the remodeling of defendants’ residence in Naperville, Illinois. Plaintiff alleges that it provided services to defendants on a nongratuitous basis; defendants accepted, received, and enjoyed the benefits of these services; and these services had a value of $14,984. Plaintiff has not been compensated for its services. The complaint did not identify a theory of liability, but merely pled the facts above as well as the fact that no contract existed between defendants and plaintiff to govern the method of payment for plaintiffs services.
Defendants filed a motion to dismiss pursuant to
Plaintiff countered that the Act does not apply to subcontractors. The basis for this assertion was the Act’s focus on communications with the homeowner. Plaintiff asserted that because subcontractors generally do not have significant interaction with the homeowner, the Act could not be meant to apply to them. In support of its argument, plaintiff attached a copy of an affidavit of Michael J. O’Brien, MD Electriсal’s president. The affidavit averred that plaintiff was hired by and had a contract with Apex Builders, Inc., a general contractor (Apex is not a party to this litigation), and that prior to commencing work on June 6, 2004, plaintiff conducted a walk-through of the jobsite. During the walk-through, defendants approved the plans, authorized the work to begin, and requested additional services that were not part of the original plan.
The circuit court, after considering the above arguments and ascertaining that plaintiffs theory of liability was quantum meruit, granted defendants’ motion to dismiss. In the process of dismissing the complaint, the trial court asked plaintiff: “[QJuantum meruit is a contract that’s implied, and how can the court imply a contract when the law prohibits one?” At plaintiff’s request, the trial court clarified that its finding was that “to grant the relief that [plaintiff is] saying would be under quantum meruit would be in derogation of statute and a clear legislative pronouncement contrary.” The court concluded by saying that plaintiff could either amend the complaint or the court could issue a finding under Supreme Court Rule 304 (210 Ill. 2d R. 304) so that plaintiff could take an interlocutory appeal. Plaintiff requested the Rule 304 finding and appealed.
Plaintiff presented two issues to the appellate court: first, plaintiff argued that the Home Repair and Remodeling Act does not apply to subcontractors; second, even if the Act does apply to subcontractors, plaintiff was not precluded from recovering in quantum meruit. The appellate court agreed with plaintiffs first contention, finding that the Act does not apply to subcontractors. As such, the court reversed and remanded the cause without reaching the issue of whether recovery is available in quantum meruit even if the Act applies.
In their petition for leave to appeal to this court, defendants raised, as the sole issue, the application of the Act to subcontractors. However, in their brief to this court, defendants raise a second issue, namely, whether subcontractors are able to recover in quantum meruit or any direct action outside the Mechanics Lien Act (
As to the first issuе, plaintiff maintains that the language is ambiguous. In response to the second issue, plaintiff contends that this question is forfeited because the issue was not raised in the defendants’ statement of points relied upon in the petition for leave to appeal, as required by Supreme Court Rule 315 (210 Ill. 2d R. 315).
ANALYSIS
I
This is a case of first impression and requires this court to examine the meaning of the Home Repair and Remodeling Act with respect to subcontractors. As this case is one of statutory interpretation, the standard of review is de novo. Harshman v. DePhillips,
It should be noted at the outset that the use of general contractors and subcontractors is a common business practice in the home repair and remodeling industry. This relationship usually entails a homeowner contracting with a general contractor to oversee a specific project, such as an addition to a home. The general contractor acts as a project manager and may in turn contract with other individuals or tradesmen to perform certain duties, for instance the plumbing or masonry. The general contractor, in its managerial сapacity, ensures that each task is performed in the proper manner and order. The homeowner pays the general contractor based on the terms of their agreement. The general contractor in turn pays the subcontractors based on the agreements that they formed. Thus, the hallmark of a subcontractor is that he works for the general contractor and not for the homeowner or business owner. This practice alleviates much of the burden on the homeowner of coordinating a construction project. It ensures that the homeowner does not have to know enough about construction to ensure that the plumber roughs in the plumbing before the drywall contractor hangs the sheet rock that obscures the wall cavity where the pipes were to be run. It also allows the homeowner to deal with only one person or company and not to have to contract with or supervise every aspect of the project. This common understanding of the general contractor/subcontractor relationship is critical to the understanding of the Home Repair аnd Remodeling Act.
The process of statutory interpretation is firmly established. The goal is to ascertain and give effect to the intent of the legislature. The simplest and surest means of effectuating this goal is to read the statutory language itself and give the words their plain and ordinary meaning. Illinois Graphics Co. v. Nickum,
In the present case, we are asked to decide whether and to what extent the Home Repair and Remodeling Act applies to subcontractors. We begin with the language of the Act itself. The Act requires that “a person engaged in the business of home repair or remodeling shall furnish to the customer for signature a written contract.”
The next stage of analysis looks to the definitions provided within the Act. “Person” is defined in section 10 of the Act as “any individual, partnership, corporation, business, trust, or other legal entity.”
For the purposes of the case at bar, plaintiff does not dispute that it was engaged in home repair and remodeling work at defendants’ place of residence. Further, the parties do not dispute that the work plaintiff performed, had it been done by a general contractor or in direct relationship to the homeowner, would fall squarely within the Home Repair and Remodeling Act. Finally, plaintiff does not claim that it attempted to comply with the Act. Instead, the question is whether, by nature of plaintiff’s being a subcontractor, the Act applies in a way that prohibits plaintiff from recovering from the homeowners because it did not comply with the Act.
Defendants argue that the Act is unambiguous in its use of the term “any person,” which, they contend, clearly includes subcontractors. Plaintiff contends that the Home Repair and Remodeling Act was designed to regulate the communications between contractors and the cоnsumer/homeowner. Thus, because subcontractors typically do not have significant direct communications with homeowners, the Home Repair and Remodeling Act cannot apply to them.
The text of the Act lends support to plaintiffs position. Section 5 states that the “General Assembly recognizes that improved communications and accurate representations between persons engaged in the business of making home repairs or remodeling and their consumers will increase consumer confidence, reduce the likelihood of disputes, and promote fair and honest practices in that business in this State.”
The text of the consumer rights brochure that must accompany a contract also militates against a reading that includes subcontractors. Under the “contracts” section of the brochure, item 10 states, “Remember, homeowners should know who provides supplies and labor for any work performed on your home. Suppliers and subcontractors have a right to file a lien against your property if the general contractor fails to pay them. To protect your property, request lien waivers from the general contractor.”
However, defendants argue that the statute is unambiguous and applies to plaintiff. They note that plaintiffs complaint states that it is an Illinois corporation with its principal place of business in Illinois. Corporations are specifically listed in the definition of “person.”
Instead of adopting either the defendants’ or plaintiffs argument, this court recognizes that “[sjtatutes should be read as a whole with all relevant parts considered.” In re Marriage of Kates,
The entire focus of the Act is on regulating the direct contact and contracting between the “person” and the homeowner or consumer. Section 5 of the Act sets forth the policy statement of the General Assembly in enacting the Act. It states in relevant part, “[T]he business of home repair and remodeling is a matter affecting the public interest. *** [A]ccurate representations between persons engaged in the business of making home repairs or remodeling and their consumers will increase consumer confidence ***.” (Emphases added.)
The conclusion that the Act applies only to those who contract directly is further supported by section 15 of the Act. Section 15 specifies the contents of the contract that the “person” is to provide to the homeowner. Section 15 states, “Prior to initiating home repair or remodeling work *** a person engaged in the business of home repair and remodeling shall furnish to the customer fоr signature a written contract *** that states the total cost ***.” (Emphases added.)
In addition,
“A person engaged in the business *** that prepares or presents a written offer for home repair and remodeling to a consumer, shall advise the consumer, before the contract or agreement is accepted and executed, of the presence of any contractual provision that requires the consumer to: (i) submit all contract or agreement disputes to binding arbitration *** and (ii) waive his or her right to a trial by jury.”815 ILCS 513/15.1(a) (West 2006).
Further, aside from the point that a subcontractor does not prepare or present a “written offer for home repair and remodeling to a consumer,” there is the negotiations clause that appears in subsection (b).
Finally, section 20 of the Act also supports the exclusion of subcontractors from the Act. Section 20 states that a person engaged in the business must “provide to its customers a copy of the ‘Home Repair: Know Your Consumer Rights’ pamphlеt prior to the execution of any home repair and remodeling contract.” (Emphasis added.)
Defendants maintain that a proper reading of the Act merely requires a subcontractor to comply with the Act if it wants to preserve the right of direct action against the homeowner. Preserving a right of action, however, is not the sole focus of the Act. The Act also regulates liability for failure to comply with its terms. The enforcement provisions use the same “any person” language as the rest of the Act. Thus, the Act implicates not just civil recovery, but civil liability as well.
Section 35 of the Act authorizes the Attorney General or the State’s Attorney to “bring an action *** against any person to restrain and prevent any pattern or practice violation of this Act.” (Emphasis added.)
Our conclusion that the Act does not include subcontractors is also consistent with related statutes. A subcontractor’s recovery against a homeowner is usually governed by the Mechanics Lien Act (
The Mechanics Lien Act is designed to provide, among other things, a remedy for wronged subcontrаctors. If the Home Repair and Remodeling Act applies to subcontractors, portions of the Mechanics Lien Act are rendered superfluous. For instance, section 5 of the Mechanics Lien Act prescribes a notice that each subcontractor must provide to a homeowner in order to preserve its lien claim:
“Each subcontractor who has furnished, or is furnishing, labor, services, material, fixtures, apparatus or machinery, forms or form work in order to preserve his lien, shall notify the occupant either personally or by certified mail, return receipt requested, addressed to the occupant or his agent at the residence within 60 days from his first furnishing labor, services, material, fixtures, apparatus or machinery, forms or form work, of his agreement to do so.
The notice shall contain the name and address of the subcontractor or material man, the date he started to work or to deliver materials, the type of work done and to be done or the type of labor, services, material, fixtures, apparatus or machinery, forms or form work delivered and to be delivered ***.”770 ILCS 60/5(b)(ii) (West 2006).
If the Homе Repair and Remodeling Act required each subcontractor, before work began, to “furnish to the customer for signature a written contract or work order that states the total cost, including parts and materials listed with reasonable particularity and any charge for an estimate” (
The Mechanics Lien Act also requires a subcontractor to give a specific warning to a homeowner when it provides the notice of rendering services. This warning reads:
“The subcontractor providing this notice has performed work for or delivered material to your home improvement contractor. These services or materials are being used in the improvements to your residence and entitle the subcontractor to file a lien against your residence if the services or materials are not paid for by your home improvement contractor. A hen waiver will be provided to your contractor when the subcontractor is paid, and you are urged to request this waiver from your contractor when paying for your home improvements.”770 ILCS 60/21 (West 2006).
By comparison, the brochure required under the Home Repair and Remodeling Act requires the statement, “homeowners should know who provides supplies and labor for any work performed on your home. Suppliers and subcontractors have a right to file a lien against your property if the general contractor fails to pay them. To protect your property, request lien waivers from the general contractor.”
If each subcontractor is required to contract with the homeowner directly, there would be no need for these provisions in the Mechanics Lien Act. All the information required in both the Mechanics Lien Act notice and warning would already have been given as required under sections 15 and 20 of the Home Repair and Remodeling Act.
Forcing subcontractors to comply with the Act would increase the burden on the very homeowners the Act is meant to protect. Such a homeowner would have to read and examine each contract, ensure that the totals in the subcontracts do not exceed the amount allocated to that portion of the project under both the contract with the general contractor and the contract that the general contractor has with the subcontractor. The homeowner would have to ensure the same project deadlines are present. The homeowner may even have to ensure that the deadlines in one contract are sufficiently early to allow other subcontractors to complete their tasks before the total project deadline. The simplicity of providing the homeowner with one written contract enumerating all the costs would be obfuscated under such a reading. Even under the best of circumstances, all a requirement of subcontractor compliance would yield is repetition of the same information already conveyed by the general contractor.
The statute is focused on regulating the communications and business practices of those people who directly solicit and contract with the homeowner.
The statute’s plain language limits its application to only those who contract directly with the homeowner. To allow any other interpretation not only would be contrary to our principles of statutory interpretation, but would also do severe damage to industry practice and other statutes. The Home Repair and Remodeling Act is unambiguous and only applies to those who form direct contracts with the homeowner.
II
Defendants’ petition for leave to appeal raised only the issue of the application of the Home Repair and Remodeling Act to subcontractors. However, in defendants’ brief to this court, they raise the question of plaintiffs ability to recover under quantum meruit where there was no direct contractual relationship between the defendants and plaintiff. In reality, this question is far broader than the application of quantum meruit to the present action. Indeed, the argument is that a subcontractor has no direct right of recovery outside of the Mechanics Lien Act. This question was not properly presented in the defendants’ petition for leave to appeal (PLA). Accordingly, plaintiff argues that the issue is forfeited. For the reasons that follow, we agree.
Defendants argue that this question is not forfeited because it was “(i) directly and properly raised before the Appellate Court, (ii) directly raised in the initial brief filed in this cause, and (iii) [plaintiff] has had ample opportunity to respond to the argument.” This statement is incorrect on all three counts.
The defendants’ contention that the issue was properly raised before the appellate court is a “red herring.” As this court stated in Marshall v. Burger King Corp., “[i]t is well settled that where the appellate court reverses the judgment of the circuit court, and the appellee in that court brings the case before this court as an appellant, that party may raise any issues properly presented by the record to sustain the judgment of the circuit court.” Marshall v. Burger King Corp.,
At the outset, we note that the issue before this court is a different issue than was addressed by the circuit court. Defendants, in their motion to dismiss plaintiff’s first amended complaint, argued that the trial court could not allow plaintiffs action to go forward because to do so would be in derogation of a statute which prohibited the enforcement of this agreement. To support this argument, defendants cited TLC The Laser Center, Inc. v. Midwest Eye Institute II, Ltd.,
In the present case, the trial court, in granting the motion to dismiss asked plaintiffs counsel, “[H]ow can the court imply a contract where the law prohibits one?” Thus, the question before the trial court was not the availability of the quantum meruit theory of recovery itself, but whether the court’s enforcement of an implied contract would be lawful where the Home Repair and Remodeling Act (if it applied to subcontractors) would prohibit the contract from existing in the first place.
Before this court, the issue presented by defendants is decidedly different. Defendants present the issue by stating that a “subcontractor has no claim against a homeowner in quantum meruit under long-settled Illinois law.” Thus, the issue changes from one that was intertwined with the application of the Home Repair and Remodeling Act to a question that is an independent basis for dismissal of the case. It is also worth noting that the first time the cases of Redd v. Woodford County Swine Breeders, Inc.,
Further, Supreme Court Rule 315(c)(3) requires that petitions for leave to appeal contain a “statement of the points relied upon for reversal of the judgment of the Appellate Court.” 210 Ill. 2d R. 315(c)(3). If a party fails to raise an issue in its petition for leave to appeal, it may be deemed a forfeiture of that issue. Central Illinois Light Co. v. Home Insurance Co.,
Contrary to defendants’ assertions, the issue was not directly raised in the PLA. The first time thе quantum meruit issue is even mentioned in the PLA is in footnote 2 on page 12 of the PLA, where the defendants note that the appellate court declined to address the “related issue” of whether a subcontractor can recover from a homeowner with whom there is no direct contractual relationship. The issue is alluded to a second time in the last paragraph of the conclusion, where the defendants state that the plaintiff has no right to proceed directly against the defendants “under any theory except a properly perfected mechanic’s lien.” These passing references do not constitute a statement sufficient to meet the requirements of Rule 315.
Finally, there is no legal support to claim that a court should reach an issue simply because plaintiff has had an “ample opportunity to respond.” Beyond the defendants’ implication that plaintiff had “ample opportunity to respond,” plaintiffs only response to this argument was to assert that the issue was forfeited. This case is illustrative of why the court must have forfeiture rules. By raising the question at this juncture, this court is effectivеly deprived of the benefit of having the issue squarely addressed by the parties. Therefore, this issue is forfeited for the purpose of the present appeal before this court.
CONCLUSION
For the reasons stated, the Home Repair and Remodeling Act does not apply to subcontractors. We affirm the judgment of the appellate court, which remanded this cause to the trial court for further consideration.
Affirmed.
Notes
before this court, neither party has claimed that plaintiff was anything other than a subcontractor. Accordingly, we do not review and make no determination of the truth or falsity of this statement. It is worth noting that to the extent that plaintiff has contracted directly with defendants for services which were not included under the contract between plaintiff and the general contractor, plaintiff may have ceased to act as a subcontractor. However, such a determination is a factual question and beyond the scope of this opinion.
Dissenting Opinion
dissenting:
The court’s decision today rests on the assumption that the Home Repair and Remodeling Act is an affirmative defense to the cause of action аsserted in this case. The court’s opinion, however, never addresses if this assumption is correct. The court’s analysis is therefore incomplete. Additionally, the court’s decision rests upon its discussion of the relationship of a “subcontractor” to a “general contractor.” This is problematic for a number of reasons, not the least of which is the fact that the court’s understanding of that relationship comes from “facts” not found in the record. In fact, operation of the Home Repair and Remodeling Act in this case has nothing to do with notions regarding the relationship between general and subcontractors at all — the Act does not even use the terms, a fact all but ignored by the court. Instead, the Act concerns only the nature of work done and whether the work has been done pursuant to the Act’s requirements concerning accuracy of communications about that work to the consumer. Facts about these things are entirely underdeveloped in this record, a fault of plaintiffs complaint to be sure, but a fault that the court condones. In utterly failing to allege any specifics about the contract in this case and the work undertaken, the complaint hardly offers a proper foundation for this court’s first opportunity to address the Home Repair and Remodeling Act.
The court is not bothered by any of this, or the niceties of proper procedure for that matter. The result is an opinion of near-advisory nature and a confusing one at that. Readers of the court’s opinion may try, as I have, to determine exactly what the court’s ruling is. As far as I can perceive, it is this: the Home Repair and Remodeling Act applies only to entities that contract directly with consumers and, to the extent that plaintiff claims that it was not such an entity, the Act does not apply to it. This perhaps would be an acceptable ruling, if there were any basis in the record for it. The record, however is far too underdeveloped to allow for that conclusion, and I therefore respectfully dissent.
Procedural Background & Controlling Principles
The first indication that the court’s opinion is offtrack appears early on in its “Background” section. In a footnote, the court explains that because neither party has “claimed that plaintiff was anything other than a subcontractor,” it need not address the fact that the record reflects that plaintiff may have “ceased to act as a subcontractor.”
I am not entirely sure what the court means by “beyond the scope of this opinion.” This case is before us on the dismissal of plaintiffs complaint pursuant to
It could be said that all of the problems in today’s opinion stem from the court’s inability to properly frame the central issue before it. As I have noted, the question raised in this appeal is whether the circuit court properly dismissed plaintiffs complaint. The court, however, sees the issue differently, stating that, in this appeal, it is asked “to decide whether and to what extent the *** Act applies to subcontractors.”
Defendant’s motion to dismiss was presumably brought pursuant to subsection (a)(9) of
What, then, did plaintiff allege in its complaint? The complaint alleged in conclusory fashion that, over the course of a five-month period in 2004, plaintiff “furnished sub-contractor services, which consisted of providing electrical materials, equipment, labor and services” at defendants’ residence. The complaint, all of a page and a half, alleged that “no contract existed between plaintiff and defendants to govern the method by which plaintiff would be compensated for its services.” Plaintiff sought the reasonable value of its services. The complaint otherwise failed to specifically allege what “subcontractor services” were actually performed or even the scope of its subcontract in relation to the rest of the general contract.
2I find it ironic that the court gives the parties a pass on the shoddy pretrial practice that took place in the circuit court, but then seizes, in its typical arbitrary fashion (see, e.g., People v. McCarty,
All of the other facts in this case come by way of affidavits submitted for consideration upon the motion to dismiss. The affidavits defendants attached to their motion stated that they did not enter into any written contract with plaintiff and did not receive any pamphlet required by the Home Repair and Remodeling Act. The affidavit of Michael J. O’Brien, which was attached to plaintiff’s response, stated that plaintiff contracted with Apex Builders, Inc., the general contractor, “for electrical material and services to be installed and/or performed” at defendant’s residence. O’Brien’s affidavit stated that Apex had a “contractual relationship” with defendants. The affidavit stated further that, “during an initial walk-through,” defendants “approved the preliminary plans and authorized said work to begin.” Plaintiff “performed services including but not limited to installation of conduit, brackets, electrical boxes, recessed lighting and bathroom fans.”
That affidavit also stated, however, that other work, outside of Apex’s contract, was performed by plaintiff. O’Brien’s affidavit stated that “during the same initial walk-through, [defendants] requested that [plaintiff] provide additional material and services not included in the original plan including but not limited to under-cabinet lighting; television and data wiring; and full electrical services to an additional family room and an additional bathroom.” (Emphasis added.)
Importantly, O’Brien’s affidavit says nothing about the central concern for this case: whether the recovery sought by plaintiff represented costs for work “not included in the original plan” as opposed to costs for work that plaintiff performed under Apex’s contract with the defendants.
Finally, defendants supported their reply with affidavits which stated that neither Apex nor plaintiff provided them “with a written agreement or change order for additional work claimed by plaintiff, namely under-cabinet lighting, television and data wiring, and full electrical services to an additional family room and an additional bathroom.” Defendants also stated that they were never “provided with an updated estimate of the cost for any such ‘additional work.’ ”
What are the consequences of these alleged facts? A
“upon the affidavits and evidence offered by the parties, or may deny the motion without prejudice to the right to raise the subject matter of the motion by answer and shall so deny it if the action is one in which a pаrty is entitled to a trial by jury and a jury demand has been filed by the opposite party in apt time.”735 ILCS 5/2 — 619(c) (West 2004).
See also Castro v. Chicago, Rock Island & Pacific R.R. Co.,
Application of the Law
Whether the circuit court correctly dismissed plaintiffs complaint turns upon whether the Act has any application to this case in light of the facts actually alleged, and not on generalizations about the relationship between subcontractors and contractors. As an initial matter, I note that both this court and the appellate court have accepted the underlying premise of defendants’
“may accept an assurance of voluntary compliance from anyone engaged in any conduct, act, or practice deemed in violation of this Act. Failure to perform the terms of any such assurance constitutes prima facie еvidence of a violation of this Act.”815 ILCS 513/35 (West 2004).
Rather than provide that analysis, the court chooses to confine the focus of this case to the issue of whether the terms of the Act apply to subcontractors such as plaintiff. In this regard, the court again accepts, without question, the assertions of the litigant — this time plaintiffs assertion that it is a subcontractor. The court’s analysis proceeds then on the assumption that plaintiff is a subcontractor even though an examinаtion of the record shows that plaintiffs subcontractor status is far from clear. The pleadings and affidavits show that the dispute between the parties lies in whether the work identified in plaintiffs complaint was part of the project that was the subject of defendants’ original remodeling contract with Apex. In other words, was the work performed by plaintiff for defendants specified in a written contract signed by them in accordance with section 30 of the Act? If the services identified in plaintiff’s complaint were performed pursuant to a written general contract that was signed by the homeowner, section 30 of the Act has no application to this case because the work was performed pursuant to the requisite written contract. However, if the services identified in the complaint were not part of the written general contract signed by the homeowner, as both plaintiffs and defendants’ affidavits suggest, then it would appear that plaintiff has run afoul of the Act in that it “remodel [ed] or ma[d]e repairs or charge[d] for remodeling or repair work before obtaining a signed contract or work order over $1,000.”
None of these concerns, however, can be answered from the record in front of us. What the case needs for proper disposition is development of evidence, as the complaint failed to allege the relevant facts and the affidavits merely hinted at them. The relevant questions are: What was the scope of the work defined in the contract between defendants and Apex? What portion of that work did plaintiff agree with Apex to perform? What was the extent of the additional work ordered by defendants and agreed to by plaintiff? Was there a written contract signed by the homeowner with respect to this additional work? Without answers to these factual questions, it is impossible to discern the Act’s applicability in this case.
Given the existence of these factual questions, the circuit court’s dismissal of plaintiffs complaint was, at best, premature and, at worst, incorrect. The record before us does not indicate that plaintiff filed a jury demand at the commencement of the proceedings as required by section 2 — 1105 of the Code of Civil Procedure. See
Rather than construe the actual terms of the Act and apply them to the facts — such as they are — the court’s analysis is dependent on its discussion about contractors and subcontractors. Worse yet, the court relies on its own notions regarding these terms. Indeed, after setting forth the standard of review — which the court gets right, but for the wrong reason — it prefaces its analysis by noting that “the use of general contractors аnd subcontractors is a common business practice in the home repair and remodeling industry.”
Unfortunately, the court’s discussion leads to an analysis based on little more than conjecture. Specifically, the court states that “ [subcontractors do not directly contract with a homeowner/customer” so the Act cannot apply to them.
The court’s treatment of this case is unfortunate because the Act is a relatively new piece of legislation that has been the subject of few published decisions. In fact, in addition to the appellate court’s opinion in this case, only two other decisions have addressed questions of the Act’s interpretation. See Smith v. Bogard,
JUSTICE BURKE joins in this dissent.
I note that section 30 makes only the failure to obtain the signed written contract required in section 15 “unlawful.”
The court’s opinion provides little guidance to either the parties or the trial judge with respect to the remand. Based on the conclusory allegations in the complaint and the few additional facts offered in the affidavits, the record here is simply too thin for the court to say with certainty that the circuit court’s dismissal was wrong. That is why I would remand for further proceedings on the
I express no opinion as to (i) whether the Act provides consumers with a private right of action to enforce violations of the Act in this manner and (ii) whether, in enacting the Act, the legislature intended to abolish the common law remedy of quantum meruit. I submit that these are the important questions under the Act. See K.A.L.M. Construction, Inc. v. Stiefbold, No. 2 — 07—1131 (December 4, 2007) (unpublished order under Supreme Court Rule 23),