167 F. 460 | 9th Cir. | 1909
(after stating the. facts as above). The time for the completion of the contract, which was originally 16 months from the date of the contract, was, without the consent of the sureties,-extended, for a further period of 1 year. We may premise the discussion of the question whether the sureties were thereby released from their obligation by adverting to some of the well-settled principles applicable to the obligation of a surety for the performance of his principal’s contract: (1) The contract of a surety is to be construed as any other contract — that is to say, according to the intent of the parties — and the rules for its construction are not to be confused with' the rule that sureties are favorites of the law and have the right to stand upon the strict terms of their obligation. Brandt on Suretyship and Guaranty (2d Ed.) §§ 92 and 94; Lee v. Dick, 10 Pet. 480, 493, 9 L. Ed. 503. (2) It being determined what is the meaning of the contract, the sureties are entitled to stand upon the very terms of their undertaking. Said Justice Story:
“Nothing can be clearer, both upon principle and authority, than the doctrine that the liability of a surety is not to be extended by implication beyond the terms of his contract. To the extent and in the manner and under the circumstances pointed out in his obligation, he is bound, and no further. It is hot sufficient that he may sustain no injury by change in the contract, or that it may even be for his benefit. He has a right to stand upon the very terms of his contract, and if he does not assent to any variation of it, and variation, is made, it is fatal.”
The decisions cited and relied upon by the defendant in error are all cases in which the power to make the alterations was expressly reserved, and in which it was stipulated that the contract should not thereby be invalidated. Thus in Wehr et al. v. Germ. Evan. St. Matthews Con., Balto., the court said:
“But if, by tbe terms of tbe original contract, additions to or alterations in tbe work are provided for, or left to tbe judgment and discretion of tbe other contracting party, either without limit or within certain limits, then the variation, if within the limits prescribed, is allowed by the contract itself, and the surety cannot complain of the variation which he has agreed to by the original contract.”
,.t In Hayden v. Cook, in a building contract, it was provided that the owner at any time during the progress of the work should have the right to. make any alterations, changes, or additions to the building, and that the same should not invalidate the contract. It was held that the changes and additions disclosed by the evidence were provided for in the contract, and that the making of the same did not discharge or release the surety. In Village of Chester v. Leonard et al. the original contract provided that the engineer of the village could make such changes in the forms, dimensions, and alignment of the work as might, in his opinion, and that of the board of water commissioners, be necessary for its proper fulfillment. The court said:
“Sureties for the performance of a contract so framed must be presumed to contemplate the making of such changes, and, as the defendants did not stipulate for any right to participate in determining whether they should be made, there was no occasion to notify any one but the principal contractor of the fact that they had been ordered.”
In People’s Lumber Company v. Gillard, it was held that, where the contract to which the bond was appended provided for certain changes by the board of trustees, the sureties on the bond must be presumed to have known of such provision, and to have agreed that
The judgment is reversed, and the cause is remanded to the Circuit Court, with instructions to enter judgment for the defendants in the action upon the pleadings and the agreed statement of facts.