McLaughlin v. Perkins

102 Cal. 502 | Cal. | 1894

Belcher, C.

This is an action to foreclose a lien for materials used and work done by subcontractors in the construction of a building for the defendant, Perkins.

The court below gave judgment for the defendants upon the ground that the claim of lien was not filed in time, and the plaintiff appeals from the judgment on the judgment-roll.

The only question in the case is, was the claim of lien filed within the time required by statute?

The court found the facts to be, in substance, as follows: On August 13, 1889, one E. W. Hyde entered into a written contract with defendant Perkins, to erect for him a certain building according to plans and specifications prepared by R. H. White, architect, and to finish the same within ninety days from said date, for the sum of $4,900, payable in installments — the fifth installment of $687.50 to be paid when the building should be completed and accepted, and the sixth installment of $1,250 to be paid thirty-five days after its completion. This contract was duly recorded, and, under it, Hyde proceeded to erect the building. On September *50416th he contracted with the assignors of the plaintiff to do the tinning and plumbing of the building, which they did, for the agreed price of $720, of which $475 was paid, leaving still due and owing therefor the sum of $245, for which, on March 1, 1890, they duly filed and caused to he recorded their claim of lien.

The building “was completed and finished, according to the plans and specifications, on the twenty-seventh day of January, 1890, but it was accepted by the defendant, William Perkins, on the eighteenth day of January, 1890, and was actually occupied and used by the tenants of defendant William Perkins on the twenty-fifth day of January, 1890, which tenants rented it on the twenty-first and twenty-second days of January, 1890. But plaintiff had no notice of the acceptance of said building by said defendant Perkins, or of its occupation by said defendant’s tenants until the thirty-first day of January, 1890, on which day the architect, R. H. White, issued a certificate in the following words and figures, to wit:

“‘San Francisco, January 31, 1890.
“ ‘ To William Perkins:.
“ ‘ This is to certify that the sum of six hundred and eighty-seven and 50-100 dollars, amount of fifth payment on building located, etc., is due and payable toE. W. Hyde.
“‘[signed] R. H. White, Architect.’”

The contract between Hyde and Perkins contained the following provisions:

“When each payment or installment shall become-due, and at the final completion of the work certificates, in writing shall be obtained from the said architect, stating that the payment or installment is due or work completed, as the case may be, and the amount then, due; and the said architect shall at said times deliver said certificates under his hand to the contractor, or, in lieu of such certificates, shall deliver to the contractor, in writing, under his hand, a just and true reason for not issuing the certificates, including a statement of *505the defects, if any, to be remedied, to entitle the contractor to the certificate or certificates. • And in the event of the failure of the architect to furnish and deliver said certificates, or any of them, or in lieu thereof the writing aforesaid, within three days after the times aforesaid and after demand therefor, made in writing by the contractor, the amount which may be claimed to be due by the contractor and stated in the said demand made by him for the certificate shall at the expiration of said three days become due and payable, and the owner shall be liable, and bound to pay the same on demand. In case the architect delivers the writing aforesaid, in lieu of the certificate, then a compliance by the contractor with the requirements of said writing shall entitle the contractor to the certificates.”

Appellant contends that these provisions of the contract made the certificate of the architect a prerequisite to the payment of any money to the contractor, and that until such certificate was issued the building could not be considered completed nor accepted as completed, and hence, as the lien was filed within thirty days after the certificate above mentioned was issued, it must be held to have been filed in time.

The provisions of the contract were not, in our opinion, as far reaching as claimed, but were intended simply for the protection of the owner by making the approval of the architect a condition precedent to the contractor’s right to demand payment of the money. This condition, however, the owner was at liberty to waive, if he choose to do so, and he might, without any certificate from the architect, have accepted the building, and paid for it as he had agreed to do.

The statute provides that every person, save the original contractor, who claims the benefit of the law in regard to liens, “must within thirty days after the completion of any building, improvement, or structure,” file for record with the county recorder his claim of lien, and that “ the occupation or use of the building, *506improvement, or structure by the owner or bis representative, or the acceptance by said owner, or his agent, of said building, improvement, or structure, shall be deemed conclusive evidence of completion.”

This language is clear and positive, and, as the right to a lien is purely statutory, is -decisive of appellant’s rights here.

It follows that the judgment should be affirmed.

Vanclief, C., and Temple, C., concurred.

For the reasons given in the foregoing opinion the judgment appealed from is affirmed.

Harrison, J., Garoutte, J., Van Fleet, J.

midpage