4 Colo. 285 | Colo. | 1878
The appellant and J. Y. Sybrant, in the spring of 1875, entered into a contract wherein it was agreed that the said Sybrant should build a house, furnishing all the material according to certain plans and specifications, on a certain lot in the town of Colorado Springs, and would complete the same on or before June 15, 1875. The total consideration to be paid was $3,100, of which sum $300 were to be paid'when the walls were completed; $300 on completion of building, and $2,500 in real estate, consisting of two lots, one of the value of $1,500, the other of the value of $1,000. The original agreement was lost. After the building was completed, upon application of Mclntire,' Sybrant furnished him with a certificate setting forth, substantially, the terms of the contract as he understood them. While the building was in progress of construction it is fairly inferable from the evidence, that in lieu of conveying to Sybrant the lot valued at $1,000, Mclntire agreed to pay the like amount in money, to enable Sybrant to complete the building. Mot only is the testimony of Sybrant to this effect, but Mclntire’s course in making cash payments, largely in excess of the amount due, if the terms of payment had not been 'subsequently altered, tends to corroborate Sybrant’s statement, that the original contract was subsequently modified by parol, so far as to convert the $1,000 payment in real estate into a money payment.
The lien claimants are Gerrit S. Barnes, the firm of McGovney & Capehart and Albert S. Millard. Barnes furnished to Sybrant, the contractor, hardware and materials for use, and that were used in the construction of Mclntire’s building, of the value of $530.27. McGovney & Capehart furnished materials of the value of $636.09 which were used in the building, and Millard furnished materials which were used in the building of the value of $225.50. Mo dispute arises as to the amount due the several lien claimants from Sybrant, but the controversy presented by the pleadings and proofs relates to the validity of the several claims as liens on the building and premises of Mclntire, under the
The statute just cited, when its provisions are observed, gives a lien to. the sub-contractor and persons furnishing labor and materials, for the value thereof, but not exceeding the amount due or to become due from the owner to the principal contractor at the date of the notice to the owner of the building, of the lien claimed. Jensen et al. v. Brown, 2 Col. 694. The lien of the sub-contractor and material-men is always in strict subordination to the terms of the original contract between the owner and his immediate contractor. Phillips on Mechanics’ Liens, § 62. A material inquiry therefore is, what amount was due at, or became due after, the filing of the lien.
Appellant urges that the building was not finished as the contract of Sybrant. It is true that as he was making but slow progress in the construction of the building, Mclntire directed Sybrant’s foreman to complete the work more speedily so that it might be ready for occupancy by D. J. Martin, his prospective tenant. The building was completed by the foreman with the consent, and to a certain extent, under the direction of Sybrant. Mclntire treated the contract as entire and as completed by Sybrant. In the account rendered by Mclntire to Sybrant, the amount paid the foreman by Mclntire was charged up to Sybrant. We do not think the court erred in finding that the building was completed by Sybrant. The account rendered demonstrates, that, as understood by the parties, Sybrant was accountable to Mclntire for whatever amount was advanced to the foreman toward the completion of the building.
' Although the contract called for the best lumber, it is not necessarily to be construed to mean lumber of rare or extraordinary quality. Within the reasonable, intent of the contract, “the best lumber” means the best of the kind that is ordinarily used in the construction of like buildings. In view of the fact that the evidence discloses that there was none other than Colorado lumber in the Colorado Springs
The testimony as to the character of the Colorado lumber used in the building is widely conflicting. If there was any departure from the terms of the contract in this respect, what damages, if any, were sustained, does not appear. In view of all the evidence, we think the court might have found, as it must, in fact, have found, that any claim for damages on that ground had been waived by the acts and conduct of the appellant.
A very different question relates to the appellant’s claim to recoup, on the ground that the building was not completed within the agreed time. According to the terms of the contract, the building was to have been finished June 15, 1875; but Mclntire, by permitting Sybrant to continue to work on his contract after the expiration of the. time, waived his right to rescind the contract on that ground. But, by consenting to the extension, he did not thereby waive such damages as he may have sustained by reason of the delay. Waterman on Set-off, § 515; Sedgwick on Meas, of Dam., p. 215 (n); Sinclair v. Tallmadge, 35 Barb. 602; Abbott v. Gatch, 13 Md. 314.
The evidence shows that the appellant caused the building to be erected, not for his own use, but with the intention of renting it to others. If it should appear that the building could have been rented June 15th, had it then been completed, or at any time thereafter prior to September 1st, when it was finished, ordinarily, the owner would be
Prom the testimony of Mclntire and Martin, it appears that had the building been completed in time, it would have been occupied by a tenant, two and half months before it was finally finished. The rental value for that period might be recouped, unless, by a subsequent settlement intended by the parties to be final, such damages were expressly, or by implication, waived.
About a month after the completion of the building, subcontractors and material-men having applied to Mclntire for the amount they claimed to be due, he sought a settlement with Sybrant, so that he (Mclntire) might be enabled to pay off the lien claimants pro rata. Sybrant testifies, that before the settlement was had, ‘ ‘Mclntire claimed he wanted to know how much money was going to parties who had .claims against the building.” Accordingly, he rendered the following account to Sybrant:
“H. A. Mclntire, real estate, loan and insurance agent, Colorado Springs, Colorado.
This statement of account between H. A. Mclntire and J. V. Sybrant, made this 27th day of September, 1875, shows that the contract price of building erected on lot 19, block 92, Colorado Springs,
was..............................-...........$3,100 00
There was paid June 10, 1875.......... $650 00
There was paid July 6,1875...........1,450 00
There was paid July 29, 1875......... 105 00
On August 26, 1875, it being impossible to get the building completed by the contractor, another party was called and completed it, to whom was paid, 248 38
--2,453 38
Balance due contractor $646 62”
By this account it was agreed that (exclusive of extra work to the payment of which Mclntire did not then bind himself), the balance then due contractor was $646.62.
With a full knowledge of all the circumstances attending the carrying out of the contract, this settlement is had. And although it is true that an account rendered is not necessarily conclusive, it is always admissible in evidence to be weighed by the court or jury as other evidence. That the court treated it in the light of a final settlement between the parties, made for the evident purpose of enabling Mclntire to adjust the lien claims against the building, is apparent from the decree. Having in view the concomitant circumstances we cannot say that, all the testimony being considered, the finding of the court is unsupported by the weight of evidence. We will not disturb it. As no one who can be prejudiced complains of the disallowance by the court of the item for extra work, it need not be considered.
The decree of the court below is
Affirmed.