MCI Telecommunications Corp. v. U.S. West CommunicationsMCI Telecommunications Corp. v. U.S. West Communications
INTRODUCTION AND STATUTORY BACKGROUND
This is an appeal by U S West Communications, Inc. (“U S West”) and a cross-appeal by MCI Telecommunications Corporation (“MCI”) from a district court judgment entered after review of a Washington Utilities and Transportation Commission OWUTC”) decision. The WUTC decision approved an agreement between U S West and MCImetro Access Transmission Services, Inc. (“MCImetro”), an MCI affiliate, under the Telecommunications Act of 1996 (“the Act”), codified in part at
The Act calls upon federal courts to hear challenges to interconnection agreements developed and approved through state administrative proceedings. Review in federal court is limited to the determination of whether the agreement “meets the requirements of’ the Act.
This court has recently had occasion to decide several cases under the Telecommunications Act, and we then described the overall operation of the Act at greater length. See Pacific Bell v. Cook Telecom, Inc.,
The Act labels all former local-phone service monopolists Incumbent Local Exchange Carriers (“ILECs”). In this case the ILEC is U S West. The new competitors are called Competing Local Exchange Carriers (“CLECs”). The CLEC in this case is MCImetro.
The FCC by regulation lists certain network elements that must be made available by the ILECs. See
The Act does not, however, attempt to provide all the terms upon which ILECs must transact with CLECs. Rather,
Finally, the Act permits any party “aggrieved” by a determination made by a state agency under
We have jurisdiction of appeals from final judgments in these actions under
HISTORY OF THIS AGREEMENT AND THE EIGHTH CIRCUIT LITIGATION
The FCC promulgated its initial regulations under the Act in 1996. Under the Hobbs Act, the Federal Courts of Appeals have exclusive jurisdiction over challenges to FCC regulations. See
On March 26, 1996, MCImetro requested interconnection negotiations with U S West. On August 30, when the parties could not come to agreement on a number of issues, MCImetro petitioned for arbitration before a WUTC arbitrator.
On October 15, 1996, approximately a month before the WUTC arbitrator was to hold a hearing on the interconnection agreement between MCImetro and U.S. West, the Eighth Circuit stayed the effectiveness of several FCC rules on the ground that the FCC may have not had jurisdiction to issue them. Thus, when the WUTC arbitrator held the hearing in late November and issued his report in December of 1996, some of the rules had been stayed, but no decision on the merits had been issued. On July 18, 1997, after the parties in this case had completed the arbitration and mediation process, the Eighth Circuit issued a decision on the merits. See Iowa Utils. Bd. v. FCC,
Because a state agency has only 30 days to approve an arbitrated agreement, the WUTC entered its order approving the agreement between MCImetro and U S West and modifying the arbitrator’s recommendations in some respects on August 18, 1997. The WUTC said it had not had sufficient time to consider the Eighth Circuit’s decision and therefore did not address its effect on the agreement.
In September 1997, U S West and MCImetro each filed suit in the Western District of Washington seeking review of WUTC’s approval and modification of the agreement. The district court issued its decision on July 22, 1998, while the Eighth Circuit’s decision in Iowa Utilities Board was still in effect. Relying on that decision, the district court struck some provisions from the agreement, reasoning that as a result of the Eighth Circuit’s rulings the provisions no longer met the requirements of the Act.
Both parties promptly appealed the district court’s decision to this court. While this appeal was being briefed, the Supreme Court granted certiorari in Ioiva Utilities Board and handed down its decision. See AT & T v. Iowa Utils. Bd. The Supreme Court reversed the Eighth Circuit in many respects, and reinstated all but one of the previously vacated regulations. We asked for supplemental briefing on the Supreme Court’s decision.
We now turn to the substance of the appeal.
PROVISION PROHIBITING U S WEST FROM SEPARATING ALREADY COMBINED NETWORK ELEMENTS
As approved by the WUTC, the agreement contained a provision requiring
COMBINING SEPARATE NETWORK ELEMENTS AT MCIMETRO’S REQUEST
In addition to requiring that U S West refrain from separating already combined network elements, the agreement requires U S West to combine otherwise separate elements upon MCImetro’s request. This provision was mandated by FCC Rules 315(c)-(f) at the time of arbitration. The Eighth Circuit invalidated Rules 315(c)-(f) using the same rationale it employed to invalidate Rule 315(b). That is, the Eighth Circuit concluded that requiring combination was inconsistent with the meaning of the Act because the Act calls for “unbundled” access. See Iowa Utils. Bd.,
Unlike its decision with regard to Rule 315(b), however, the Eighth Circuit’s decision with regard to Rules 315(c)-(f) was not before the Supreme Court. The Court’s holding concerning Rule 315(b), however, confirms that the Eighth Circuit’s interpretation of the Act was incorrect. The Court firmly stated that the Act’s mention of “unbundled access” does not even “remotely imply” that elements must be provided only in uneombined form and never in combined form. Iowa Utils. Bd.,
DARK FIBER
The agreement contains a provision requiring U S West to provide MCImetro with dark fiber on an unbundled basis. Dark fiber is fiber optic cable laid in the ground but not yet activated for use. The FCC’s original “network elements” rule did not mandate unbundled access to dark fiber, but the district court held that an interconnection agreement provision requiring such access did not violate the Act. The district court’s conclusion has since been solidified by the FCC’s new rule, which treats dark fiber as a network element and therefore mandates U S West to provide competitors with access to it. See
CO-LOCATION OF REMOTE SWITCHING UNITS
U S West also challenges a provision of the agreement requiring U S West
U S West argues that we must strike the provision because the WUTC relied on the FCC’s interpretation of the word “necessary,” an interpretation with which the Supreme Court has found fault. See Iowa Utils. Bd.,
We are not reviewing the actions of a federal agency subject to the APA, however. Here, our task is not to examine possible flaws in the WUTC’s decision-making process, but to decide whether a provision resulting from that process-the provision requiring co-location-has resulted in an agreement that fails to “meet the requirements” of the Telecommunications Act.
SHARED TRANSPORT
Shared transport refers to cable that connects facilities owned by different parties. The agreement did not require U S West to provide MCImetro with unbundled access to shared transport, despite an FCC rule mandating such access. Relying on the FCC rule, the district court held that because the agreement failed to include a provision requiring unbundled access to shared transport, the agreement in that respect failed to meet the requirements of the Act.
Subsequent to the district court’s decision, the Supreme Court vacated the rule in question. The Court held that in promulgating the rule, the FCC had construed too permissively the congressional requirement that elements should only be subject to unbundled access if “necessary” and if lack of access to them would “impair” a competing carrier from providing services. See
The FCC has now promulgated a new network elements rule, this time taking into account the Supreme Court’s directives in Iowa Utils. Bd. Once again, the regulations require unbundled access to shared transport, though under limited circumstances. See
Because the present rule is narrower than the rule relied upon by the district court, we reverse the district court’s decision. We remand so that the district court may consider whether to order a new provision or direct the parties to return to the WUTC in light of the special local considerations that may be relevant.
BILL AND KEEP
The Telecommunications Act requires that interconnecting ILECs and CLECs compensate each other for the cost of one party’s transport and termination of traffic originating on the other party’s network. See
U S West argues, however, that it presented sufficient evidence in this case to demonstrate that its cost of transporting and terminating MCImetro calls so exceed MCImetro’s costs so that bill and keep is neither just nor reasonable in these circumstances and therefore violates the Act. U S West assigns error to the arbitrator’s use of a presumption that calls between carriers will be in balance, arguing that the presumption is contained in one of the FCC rules the Eighth Circuit stayed before it ruled on the merits in Iowa Utilities Board and was therefore technically not in effect at the time the arbitrator made his decision. The rule (since reinstated by the Supreme Court) simply provides that “[njothing in this section precludes a state commission from presuming” that traffic is in balance.
As the arbitrator explained, the WUTC has a general policy favoring bill and keep arrangements. Because we are dealing with a new competitive relationship, the evidence on actual costs contained in the record consists only of speculation on the part of U S West and the statement from a WUTC official, reasonable at least on its face, that costs will be equal even if traffic volume is out of balance as long as individual customers make about as many calls as they receive. Given the impossibility of more concrete data, and Congress’s generally permissive attitude toward bill and keep arrangements as expressed in the Act, the arbitrator’s decision to impose the system does not violate the Act as a mat
UP FRONT CONSTRUCTION CHARGES
The agreement requires U S West to undertake construction if necessary to meet MCImetro’s interconnection requests. U S West does not contest the substance of this provision, but argues that the fact that the agreement does not require MCImetro to pay its construction charges up front rather than after construction is completed violates the Act. The district court rejected this argument and upheld this provision of the agreement.
U S West’s sole argument rests on the Eighth Circuit’s decision to vacate an FCC rule requiring an ILEC to provide CLECs with interconnection at levels of quality superior to those at which the ILEC provides the same services to itself. See Iowa Utils. Bd.,
OBJECTIVE PERFORMANCE STANDARDS
The agreement currently requires U S West to provide services to MCImetro as quickly as U S West provides them to itself. MCI wants the agreement to contain “objective performance standards,” or, in other words, hard numbers on these time limits. MCI wants the agreement to state in exactly how many days U S West must provide a particular service. MCI suggests that the WUTC was required to include objective performance standards by an FCC rule to that effect.
MCI actually is referring to language in the FCC’s First Report and Order, which is not itself an FCC “rule.” The Order explains why the FCC chose to promulgate the rules it did, and why it accepted the arguments of some commenters and rejected those of others. With regard to the issue of nondiscriminatory access to unbundled network elements and just, reasonable and nondiscriminatory terms and conditions for the provision of unbundled network elements, the Order focused on two questions: (1) should the FCC promulgate any national rules at all, and (2) if so, what should those rules be?
In a section titled “Comments,” the FCC put forth the positions of the various com-menters on these two issues. Regarding the second issue, the Order mentions that during the notice and comment period MCI argued that the FCC “should adopt specific standards, including time limits, for implementation of requests for unbundled elements.” In the Matter of Implementation of the Local Competition Provisions of the Telecommunications Act of 1996, First Report and Order, FCC 96-325 (Aug. 8, 1996) at ¶ 300. (“First Report and Order”). The Order goes on to state that a “number of incumbents, including Bell Atlantic, SBC, GVNW, and NYNEX, contend that we should not set specific rules, including time limits, for installation, service, maintenance and repair because incumbent LECs have different operational and administrative systems, and are subject to different state standards.” Id. at ¶ 301.
In a section titled “Discussion,” the FCC explained that it had decided to reject the suggestion to promulgate no national rules at all. Instead, the FCC adopted “general, national rules defining ‘nondiscriminatory access’ to unbundled network elements, and ‘just, reasonable, and nondiscriminatory’ terms and conditions for the provision of such elements.” First Report and Order at ¶ 308. The FCC indicated that the general rules would “rely” on the states to develop more specific ones “in arbitrations
This language in the Order demonstrates that the FCC hoped (or “expected”) that the states would adopt specific rules. Neither the Act nor any FCC rule affirmatively requires states to do so, however. The FCC might have wanted the WUTC to impose more specific requirements, such as objective performance standards, on an incumbent like U S West, but again, our review seeks to determine solely whether the lack of those requirements violates the Act. In the absence of an FCC rule, the law does not require them.
CONCLUSION
We affirm the district court’s decision with respect to the following: (1) the validity of the provision requiring unbundled access to dark fiber, (2) the validity of the provision requiring co-location of RSUs, (3) the validity of the provision imposing the bill and keep method of reciprocal compensation, (4) the refusal to add to the agreement a provision requiring MCIme-tro to pay its construction charges up front, and (5) the validity of the agreement’s failure to include “objective” performance standards.
We reverse the district court’s decision with respect to the following: (1) the validity of the provision prohibiting U S West from separating already-combined network elements, (2) the validity of the provision requiring U S West to combine network elements at MCImetro’s request, and (3) the addition of a provision requiring unbundled access to shared transport.
The overall result is that the original agreement between U S West and MCImetro has been restored in all respects with the possible exception of shared transport. We remand the issue of shared transport for further consideration.
AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
Each party should bear its own costs.