Defendant appeals from a judgment awarding plaintiff $35,841.24 damages for breach of contract.
Questions Presented
1. Do the terms of the contract prohibit recovery of damages incurred by plaintiff solely due to defendant’s failure to obtain rights of way as agreed?
2. Did plaintiff fail to comply with its legal duty to minimize damages?
3. Was interest on the amount of damages from date of completion of contract recoverable ?
General Facts
The case was tried upon an agreed statement of facts. Plaintiff, a general engineering contractor, entered into an agreement with defendant to construct a water supply line froffi. Baden to Colma. The contract required plaintiff to complete the work within 150 calendar days after the first Monday subsequent to the city’s notification to plaintiff to commence work. Specifications for the work were expressly made a part of the contract.
Section 70 provided: “In addition to certain lands which are already owned by the City, the City will acquire the other necessary right of ways or easements for the required construction prior to the time the Contractor commences work in the field.”
1. Terms of the Contract.
Defendant’s main defense is that under the terms of the contract plaintiff’s only remedy for defendant’s delay in obtaining the requisite rights of way was to apply for and obtain an extension of time to complete the work. The portions of the sections of the specifications upon which it bases its contention follow.
Section 44 provided that should the completion of the work be delayed the commission might grant the contractor additional time for completion, and if the commission believed that such delay was unavoidable, as unavoidable was thereinafter defined, the commission would grant such time.
Section 45 defined unavoidable delays as including all delays beyond the control of the contractor which he could not have provided against by exercise of care, diligence, etc. Orders of the commission changing the amount of the work, the manner in which it was to be prosecuted, unforeseen delays on the part of other contractors, and delay in securing materials, equipment, etc., due to action of the War Production Board, would be considered unavoidable delays. Delays due to adverse weather conditions would not be considered unavoidable. °
Avoidable delays (section 46) would include all delays which might have been avoided by the contractor exercising care, diligence, etc. Reasonable loss of time due to submitting plans to the engineer for approval, interruptions on account of reasonable interference of other contractors and other unavoidable delays which did not delay the completion of the whole work beyond the time specified, would not be considered unavoidable delays.
Section 47 provided that whenever the contractor foresaw any delay or when it occurred, he should notify the commis
Section 48 provides that if the contractor requires an extension he shall file an application therefor in the form therein set forth not later than 20 days before the date of the expiration of the time fixed for the completion of the work.
Section 49 provides: ‘Apart from granting the Contractor extensions of time for unavoidable delays, no payment or allowance of any kind shall be made to the Contractor by way of compensation or damages on account of any hindrance or delay from any cause in the progress of the work or any portion thereof, whether such delay be avoidable or unavoidable.”
It will be noted that the definitions of “unavoidable” and “avoidable” delays in the contract refer primarily to delays by, or beyond the control of, the contractor and not of the defendant, except to orders issued by defendant’s commission changing the amount of work to be done, the quality of material to be furnished or the manner in which the work is to be prosecuted, and to delays due to other contractors. Nowhere is there the slightest suggestion that defendant will be absolved from damages caused by its not keeping its agreement to secure rights of way prior to the starting of the work. To construe that language in section 49, which says, “no payment . . . shall be made to the Contractor” for “hindrance or delay from any cause . . . whether such delay be avoidable or unavoidable” to mean that it was thereby intended by the parties that the only remedy for the contractor, when the city broke its solemn agreement to procure rights of way in advance, was for the contractor to obtain an extension of time to do the work, would be to give the clause and the contract as a whole a strained, unreasonable and unfair interpretation. Particularly is this so, when it is remembered that the contract was drawn by defendant’s attorney. Considerable portions of it are devoted to outlining what are avoidable, and unavoidable delays and this type of delay is not included. Nor is there any provision for exten
The cases relied upon by defendant are readily distinguishable from the case at bar. In Hansen v. Covell,
Defendant relies greatly upon the fact that section 49 provides that no payment shall be made “.by way of compensation or damages on account of-any--hindrance-or delay fromany cause . -. .’’ In Hill v. City of Duluth,
While there were two phases of plaintiff’s recovery, one . for the period of standing by while the plaintiff did not have available to it the necessary right of way, and the other for the additional expense caused plaintiff by the winter weather, damages for both of which the court allowed, we can see no reason for denying recovery of damages for the second phase any more than for the first phase. Both were damages suffered by plaintiff because of defendant’s neglect. Nor is it important whether such neglect was not caused by bad faith on the part of defendant.
2. Duty to Minimize Damages.
Approximately 90 days before what should have been the date of completion defendant stopped the work because it did not have the necessary rights of way to enable plaintiff to continue on. Defendant contends that because plaintiff did not then quit the job, declare the' contract breached and sue for its damage, it failed to exercise its legal duty to minimize the damage, citing Restatement, Torts, section 918, and Jegen v. Berger,
3. Interest.
The court allowed interest at 5 per cent on the amounts allowed as damages from April 30, 1949, which was the date of completion of the contract, to date of judgment, amounting to $5,087.77. This allowance of interest was apparently upon the authority of section 3287, Civil Code. However, as said in Department of W. & P. v. Okonite-Callender C. Co.,
We find nothing in Irvine v. Reclamation Dist. No. 108,
As to the $5,087.77 interest, the judgment is reversed. In all other respects the judgment is affirmed. Plaintiff will recover costs.
Peters, P. J., and Wood (Fred B.), J., concurred.
Respondent’s petition for a hearing by the Supreme Court was denied November 20,1952. Schauer, J., was of the opinion that the petition should be granted.
Notes
Unless otherwise stated, emphasis is added by us.
