76 N.Y.S. 412 | N.Y. App. Div. | 1902
Lead Opinion
This is an action to foreclose a mechanic’s lien on premises Hos. 226 and 228 West Seventy-eighth street, owned by the defendant Horgan, who was erecting thereon a double six-story and basement apartment house. On the 15th day of August, 1899, the plaintiff contracted in writing with the owner to do the plumbing and gas-fitting work and furnish the materials therefor for the gross sum of $4,200, payable in five installments as follows: Fvrst, when all cast iron sewer, soil and vent lines are in and brown mortar, $850; second, when gasfitting and water supply lines are in and white mortar, $800; third, when all lead roughing is done and job tested and water test passed and standing trim, $700; fourth, when half of fixtures are set and doors hung, $900; fifth, when all fixtures are set and job completed, $950 ; making total amount of contract $4,200. The time for the completion of the work was left blank. The contract, however, provided that if the contractor refused or neglected to supply sufficient material or workmen the owner might, on three days’ notice, declare the work abandoned, and complete it at the cost of the contractor. On the 7th day of April, 1900, the plaintiff abandoned the work upon the theory that the owner was in default in refusing to make the fourth payment. The plaintiff claims that he had performed all work and furnished all materials required by the contract as a condition precedent to the fourth payment, and that he thereafter demanded such payment, and upon the owner’s default abandoned the work.
The owner claims that the plaintiff had not earned such payment at the time he abandoned the work, and the trial court has so found. The plaintiff gave evidence tending to show that he made a demand and that the owner was unable to pay but did not deny the plaintiff’s right to payment. The owner testified that no demand was made, and gave evidence tending to show that with reference to some of the items of work upon which it is now claimed that the plaintiff was in default, he had previously drawn the attention of the plaintiff thereto, who promised to complete or remedy the same. The trial court has either expressly or by necessary implication found these facts also in favor of the owner.
The trial court has found on sufficient evidence that it cost the owner the sum of $1,433.54 to complete the contract, and that this
There was evidence tending to show, and I -think it. fairly preponderates in that direction, that the plaintiff failed to perform .many items of work and to furnish many items of material required by the contract before he was entitled to the fourth payment. He failed to complete the work of furnishing and connecting fourteen lines of vent pipes to extend beyond the roof, work required before he was entitled to the first payment, and it cost the owner seventy-six dollars to complete this work. The contract required the plaintiff to furnish and set eighty-nine fixtures. • Forty-seven of these were upon the premises on the seventh of April, but according to the evidence adduced by respondent those on the third floor were not set, and it appears that many items in connection with the fixtures that were set had not been either supplied or. attached, viz., the rubber aprons and shampoo connections were wanting ; the gas logs were not connected ; pipes were not painted; covers to tubs ■were not screwed on ; waste pipes and strainers were not supplied, ■and other similar items of work and materials were not performed or furnished, and there were other items for defective work and damages done, and not remedied, by plaintiff’s workmen.
The plaintiff contends that the items of material and work omitted 'were of such a character that they could have been furnished as well at the completion of the contract, but, conceding this; the plaintiff was required to put the defendant in default before he was at liberty to abandon the contract, and this, he could not do with 'respect to the fourth payment without showing that he had discharged one-half of his obligation in respect to- furnishing and setting fixtures. In this we think he failed. It appears that-it cost $166 to complete the work which the plaintiff claimed to have done and $191.12 in addition thereto to remedy defects therein. The plaintiff should have remedied these defects, supplied these omissions, and then, if the owner refused to make the payment, he might with propriety have abandoned the work.
Where a contractor, acting in good faith, removes his men and tools believing that he has fully completed his contract* but in fact slight omissions are found which, may be readily supplied or reme
The owner, however, having in accordance with the terms of the agreement completed the contract work, the plaintiff would ordi
For these reasons that part of the judgment appealed from should be reversed and a new trial granted, with costs to appellant to abide the event.
Yah Brunt, P. J., and McLaughlin, J., concurred; Patterson, J., concurred in result; O’Brien, J., dissented.
Dissenting Opinion
I think that not only part but all of the judgment should be reversed, and for the following reasons : The action is to enforce a mechanic’s lien for $900, the fourth payment under a written contract for plumbing and gasfitting, which it is alleged became due on April 6, 1900, at which time, because of its non-payment, the plaintiff discontinued work. The answer admits that the first three payments were made, but denies that the fourth was due, and avers that the third was prematurely paid on condition that plaintiff should forthwith deliver all materials and fixtures, which he never did, abandoning the work before the fourth installment was payable, wherefore defendant procured ■ the remainder of the work to be done at an expense of $1,790.66, and lost in rents by reason of delay incurred through plaintiff’s breach the sum of $1,000, leaving a balance due from the plaintiff.
The defense of a new agreement, whereby the plaintiff was to “ deliver forthwith ” ail the fixtures, is based upon a letter signed by the plaintiff when he received the third payment that he would “ proceed with all possible dispatch to complete the plumbing work * * * according to my original contract * * * provided that payments are made as the work progresses according to the contract.” This certainly is not an agreement to furnish forthwith all the fixtures, nor anything more than a ratification of the original contract and may be disregarded. It throws a flood of light upon the situation, however, and is, therefore, most helpful in discovering the true relations of the parties.
As testified, its purpose was to enable the defendant to procure more money or advance loans in order to complete the erection of the building and it appears that the entire work hinged upon the
The plaintiff testified that he had difficulty in obtaining the third payment from the defendant because the latter was out of funds, and he insisted that the payments should be in accordance with the terms of the contract and this was embodied in the letter he signed; that on the 28th of March, 1900, he sent word to the defendant that half of the fixtures as called for in the fourth payment would be set on April sixth, and that on April seventh, in conversation with defendant’s superintendent, the latter admitted that half of the fixtures were set and promised that payment would be made the fol-owing Monday morning, April ninth. Plaintiff’s workman corroborates this testimony and the superintendent himself says that plaintiff came to see about his payment and he told him if he was-right he would get his money. And by letter dated April seventh, plaintiff- notified defendant that the fourth payment was due. Not having been paid, he discontinued work and he téstifies that the defendant in conversation about April twelfth said he did not have the money to give him and suggested that he put in more fixtures' so a new loan could be had, which he refused to do, although he did write a memorandum to the effect' that “ 90% of the balance of the fixtures . * * * can be delivered in three days after order for same is given .by me.” The payment, however, was never made.
It -thus appears that the real difficulty, which was the one recognized by the parties, was the inability of the -defendant, to get funds with which,to meet, the'demands made upon him in the -erection Of'
It is urged that the rule to be applied in determining the merits of. this contention is not whether the plaintiff had substantially performed the work required to entitle him to the fourth payment, but whether he had performed his obligations “with-'out any omission so substantial in its character as to call for an allowance of damages,” inasmuch as in this case the plaintiff left the work before the entire contract was- completed and brought suit to recover the installment earned and not paid. The words, which we have quoted form a part of what was said • in the case of Van Clief v. Van Vechten (130 N. Y. 571), which contains an admirable statement of the law on the subject. As therein said: “ The question of substantial performance depends somewhat on the good faith of the contractor. If he has intended and tried to comply with the contract and has succeeded, except as to some slight things omitted by inadvertence, he will be allowed to recover the contract price, less the amount necessary to fully compensate the owner for the damages sustained' by the omission. * * * But when, as in this case, there is a willful refusal by the contractor to perform his contract, and he wholly abandons it, and,, after due notice refuses- to have anything more to do with it, his right to recover depends upon performance of his contract, without any omission so substantial in its character as to call for an allowance of damages if he had acted in good faith” The crucial question, therefore^ which determines which rule shall be applied is whether or not the contractor has acted in good faith and not whether or not he is suing to recover an installment rather than the entire 'or final payment. Here the evidence is that the contractor did act in- good faith and intended and tried to comply with the terms of the contract, whereby he was to receive the fourth installment; and I think, therefore, that the general principle of substantial performance should govern.in determining his rights.
Furthermore, we should give tó the contract under consideration a fair interpretation from the standpoint of those who made it and not according to its literal.phraseology. It was-intended to provide a measure of the work and thus set the time for the partial pay
It is admitted that the “ doors hung payment ” had been received by the defendant and that there were more than half, or forty-seven of eighty-nine fixtures set, and at least half of each kind, which are the two requisites stated for the fourth payment. Because, however, of the failure of the plaintiff to actually set the vent pipes mentioned, to put in place detachable rubber' aprons and shampoo connections in the bath rooms, to paint the pipes, to screw on covers furnished for tubs, to replace some broken slate, to connect a waste pipe, to supply certain strainers, to rectify a leak in a valve and in a gas pipe, to repatch some plastering necessarily removed to adjust pipe, it is claimed that he forfeited his right to the fourth installment. The deficiencies specified were covered, I think, by the final and not the fourth payment, and, therefore, constituted no reason for the defendant’s failure to pay the sum demanded; but even if they were, matters which should have all been attended to prior to the fourth installment, none of them were of such a character as to preclude plaintiff from payment for. what he had in good faith performed, provided he had substantially completed his work up to that time.
I think the plaintiff’s evidence abundantly shows that he has fairly and justly earned the sum for which he sués to recover, and that the judgment, accordingly, should be reversed and a new trial ordered, with costs to the appellant to abide the event.
Judgment so far as appealed from reversed and new trial ordered, with costs to appellant to abide event.