202 A.D. 317 | N.Y. App. Div. | 1922
This action was brought to recover a balance claimed to be owing under a contract in writing made between the plaintiff McGovern and the defendant by the Public Service Commission, First District, on the 13th day of February, 1912, for the construction of section 9, route 5, of the Lexington Avenue subway in the borough of Manhattan between a point fifty feet north of the center line of East Sixty-seventh street and a point seventy feet south of the center line of East Seventy-ninth street, and for damages for breaches thereof. The contract was duly assigned to the plaintiffs under the firm name of Patrick McGovern & Co. Proposals were not invited for the construction of the subway for a gross sum, but on a unit basis for the different classes of work and material, and the contract accordingly provided for payment for the work and labor performed and the materials furnished according to the unit basis of prices contained in the proposal of the bidder, and for work not coming within the specified classifications at cost plus ten per cent.
The avenue is seventy-five feet in width and the fee thereto was owned by the city, and the width of the carriageway between the curbs is thirty-seven and one-half feet leaving a sidewalk and areaways on each side of the width of eighteen feet nine inches. The plans provided for an open cut from the surface for the construction of two local tracks and for the construction of two express tracks in tunnels underneath the local, tracks, and for local stations at Sixty-eighth and Seventy-seventh streets; and at those streets the surface of the street was to be excavated for the entire width of the avenue and for some distance beyond in the intersecting streets. The center line of the avenue was made the center line of the subway. From the intersecting streets at which stations were to be constructed the width of the cut became gradually narrower, and between the second and third blocks therefrom it attained the minimum width of thirty-three feet.
One of the units for which the bidders were invited to submit proposals was underpinning, and they were required to specify the amount per lineal front foot of building underpinned for which
There is no evidence or claim that any representation was made to bidders by any one representing the defendant concerning the construction of the contract and specifications with respect to underpinning; and if there had been, at most it might have afforded a basis for a suit in equity to be relieved from the contract, but on no theory would it be binding in an action predicated on the contract as this is. No authority has been cited and we know of none authorizing the receipt of evidence with respect to the construction which a bidder in preparing a proposal placed upon the contract which, if successful, he was to be called upon to execute, or upon the plans or specifications which were to form a part thereof, or which sustains the rulings of the court with respect to such construction by a former bidder or a declaration made to him by a subordinate employee of the Public Service Commission or of the city with respect to the construction of the contract and specifications. On the assumption that there was a question of fact for the determination of the jury on this point, the evidence to which reference has been made was not only incompetent but' was most prejudicial, and the recovery, which was for the full amount claimed on the first cause of action, could not be permitted to stand. We are of opinion, however, that even the expert testimony was improperly received, and that the contract plainly limited the right of recovery for underpinning ■ to the lineal feet front of the main walls of the buildings underpinned; and recently this court so held in construing a contract and specifications which were similar in all material respects to those in the case at bar for the construction of another section of the' same subway. (Daniels Co. v. City of New York, 196 App. Div. 856.) The theory and basis upon which the plaintiffs here make a claim for underpinning the stoops are the same as those upon which a like claim was made in Daniels Co. v. City of New York (supra), but the learned counsel for the respondent has here presented them more elaborately, and he contends that our former decision is not controlling. It is, therefore, proper that we should refer to the evidence with respect to the general nature of the work of underpinning the walls of the building and with respect to the work which it is claimed constituted underpinning the stoops. In the case at bar it is perfectly clear that neither the stoops nor the walls underneath
Section 62 of the specifications, so far as here material, provided that the contractor should at all times, by suitable bridging or other supports, maintain and support “ all surface and sub-surface structures encountered during the prosecution ” of the work in a “ safe condition for the usual service and to the reasonable satisfaction of the owners,” and obligated the contractor to protect from injury “ all surface and sub-surface structures and surfaces of whatever character along the line of the work,” and in the event
The learned counsel for the respondent contends that these provisions of the specifications are inapplicable for the reason that it is elsewhere provided, under the general provisions to which reference has been made, for payment for this underpinning; and he cites in support of his contention the testimony rof experts to the effect that the work was known as underpinning, and also the case of Broadway Realty Co. v. Lawyers Title Ins. & T. Co. (226 N. Y. 335), which related to the marketability of a title and held that it was not marketable for the reason that a stoop appurtenant to the building constituted an encroachment of the building upon a public street. The point now presented for decision is not whether these stoops could be considered for any purpose part of the buildings, but whether by the contract or by any specifications with regard to underpinning the parties intended that the stoops should be deemed parts of the buildings, and whether the contractors are entitled to be paid for the work thus done in supporting them as for underpinning. If so, then the city will be obliged to pay for underpinning two front walls in thirty-eight instances, for it has already paid for the lineal foot frontage of the buildings underpinned with 'respect to the frontage measurement of the walls back of the stoops. That, I think, would be an erroneous construction and would in effect eliminate the word “ front ” from the provisions of the specifications wherein it is provided that the contractor shall receive for underpinning buildings, including all. incidental work and material, $82 per lineal front foot of building underpinned. This, I think, clearly contemplates only one front
The second cause of action is to recover six thousand six hundred and thirty-four dollars and eighty cents, being the difference between eight dollars and twenty-five cents per cubic yard on 1,843 cubic yards of excavation for emergency exits and a ventilating chamber, and four dollars and sixty-five cents per cubic yard which was allowed to the contractors therefor. On this cause of action a verdict was directed in favor of the plaintiffs for practically the amount claimed. The engineer classified this work under the classification made by the specifications for “ rock excavations (except excavations for sewers and pipes),” the contract price of which was four dollars and sixty-five cents per cubic yard. The learned counsel for the city contends that under the general provisions of the contract with respect to the conclusiveness of the determination and certificate of the engineer, which are the same as those set forth in our opinion in Daniels Co. v. City of New York (supra) and need not be restated here, the determination of the engineer is binding and conclusive on the contractors in the absence of fraud or bad faith, of which there is no evidence. The learned counsel for the respondents claim that this work was incidental to the construction of the tunnel for the express tracks, and that the refusal of the engineer to classify it under the item in the specifications for “ tunnel excavation (except tunnelling for sewers),” for which the contract price was eight dollars and twenty-five cents per cubic yard, was arbitrary and not merely an error in classifying the work, but constituted an erroneous construction of the contract and specifications, which is reviewable by the court under our former decision to which reference has been made. The plans required the construction of an exit for passengers on each side of the avenue from each of the express tracks to the local stations at Sixty-eighth street and Seventy-seventh street, and also a large ventilating chamber over and in connection with the express tracks. When the plans and specifications were prepared, it was expected that the entire excavation for the express tracks covered by this contract would be tunnelled through solid rock. The learned counsel for the respondents contends that since the construction of the exits and of the ventilating chamber were required only in connection with and for the express tracks, the excavation therefor constituted tunnel excava
The third cause of action was for extra work performed and materials furnished by the contractors under the contract in constructing, removing, relocating, and restoring certain ducts containing electrical wires, and in supplying, furnishing and drawing cables into and through them. On that cause of action, a verdict was directed in favor of the plaintiffs for $43,796.20. The city conceded that the contractors performed this work and furnished these materials and that the amount claimed was the reasonable value thereof, but it denied liability therefor. There were several duct lines under Lexington avenue within the area which the contractors were required to excavate by open cut. The Empire City Subway Company had one on each side of the street extending from one end of the section to the other. The Consolidated Telegraph and Electrical Subway Company had another duct line extending the entire length of the section. It was on the easterly side from Sixty-seventh to Sixty-ninth streets and there crossed to the westerly side. Each of the ducts carries many cables. The Empire ducts carry the telephone and the police and fire department wires, and the Consolidated ducts carry the Edison Company’s high and low tension wires. The ducts were of tile encased in concrete, and within them there were individual channels for the cables. At each street intersection, the continuity of the ducts was broken by a manhole, and the cables, which were of the length between the manholes, with some allowance for slack, were drawn through the ducts and hung upon racks along the wall and spliced together at the manholes. The contract plans, upon which the bids were received, showed the duct lines as they then existed in
“ Detailed Drawings.
“ Section No. 39. The Engineer will prepare and furnish to the Contractor, from time to time as required, drawings and plans amplifying such details of the contract drawings as may be necessary, and drawings and plans necessary to show the adjustment and reconstruction of all surface and sub-surface structures wherever the reconstruction of the same is necessitated by the construction of the- railroad. These plans must be strictly followed, unless local conditions should develop, during construction, suggesting changes, when, with the approval of the Engineer, such changes may be permitted.”
Section 58 of the specifications required the contractors to give one week’s notice in advance to the proper city officials and to all companies owning or having charge of surface or sub-surface structures along any part of the work, of their intention to commence operations along that part of the route and to co-operate with those in charge of said structures and furnish them reasonable facilities for inspecting “ the methods of caring for their property.” Section 59 provided that the engineer would prepare a tentative plan to be submitted to the parties interested with respect to the rearrangement of “ sub-surface structures requiring removal and relaying or reconstruction, due to interference with the railroad structure ” and required him to make any reasonable changes requested by interested parties and approved by him, and provided that a further plan should be made then, which, on the approval of the engineer, would be final. Section 60 provided that whenever it- became “ necessary to cut, move, change, or reconstruct any surface or sub-surface structures, or connections therewith, such work shall be done according to the reasonable satisfaction of the owners of such pipes or other structures.” Section 61 required that" all work of reconstruction or alteration should be done with reasonable dispatch, and that facilities should be provided to the end that the work would “ interfere as little as possible with the practical working and use of such structures.” Section 62 required the contractor by suitable bridging or other supports to maintain and support in a safe condition for the usual service and reasonable satisfaction of the owners “ all surface and sub-surface structures encountered during the prosecution of the work; ” and to protect such structures from injury, and in the event of injury, to restore
The plaintiffs showed by testimony of experts that all of these duct lines might have been retained in place with certain changes of manholes and “ flattening out ” of the ducts, where the roofs of the subway stations came close to the surface of the street, and that if they had been so retained in place, with these changes, there would have been very little additional excavation required, and that no substantial amount of new cable would have been required. The Commission estimated that 155,300 feet of duct would be required to be relaid as provided in section 64 of the specifications, and this estimate was inserted in the form of proposals for the use of bidders with, however, a note to the effect that it was understood that the quantities of the various items specified were given as a basis for the uniform comparison of bids, and were not in any way guaranteed or represented as correct or intended to be relied on, and that they should not be taken as final and should form no basis for any claim in case they did not correspond with the final measurements or quantities, and that the Commission reserved the right to increase or diminish or omit entirely any of the quantities or items. The contractors at first proceeded on the assumption that the ducts were to be supported and retained in place; and there is evidence tending to show that
The fourth cause of action is for two items, (1) for $4,428.85 for gas pipes relaid owing to physical interference with the subway
“ Work not Susceptible oe Classification.
“ Article XII. In case any work or materials shall be required to be done or furnished in or about the Works — whether specified herein or indicated on the plans or not — which are not susceptible of classification under the Schedule of Unit Prices, the Contractor shall and will if ordered by the Engineer do and perform such work and furnish such materials at and for the actual and necessary net cost in money to the Contractor for labor and for material, where new material is used and in addition thereto ten per centum (10%) of such net cost for the use of tools and plan, superintendence and all other expenses incidental to the performance of such work and the furnishing of such material, and the Contractor shall have no further claim in excess of the above; but this method of payment shall not apply to the performance of any work or the furnishing*334 of any material which in part or in whole is susceptible of classification under such schedule, which work or material shall be paid for in part or in whole, as the case may be, at the unit price giv.en in such schedule, except as herein otherwise expressly provided.”
If these provisions of the contract are to have any scope, it seems to me that they fairly cover this claim, for concededly this work was unforeseen and the actual cost of constructing the tunnel between these points was increased by this unforeseen condition, for the amount of which the recovery was had. I am, therefore, of opinion that the court was also right in directing a verdict on this cause of action.
The sixth cause of action was to recover a balance of $25,000, alleged to be owing on account of extra work, labor and services performed and material furnished at the special instance and request of the defendant, but the plaintiffs on the trial abandoned all of that cause of action with the exception of nine items for which they claimed the aggregate amount of $9,200.40. The court directed a verdict in their favor with respect to seven of the items, and left the other two to the jury, and the verdict was rendered in favor of the plaintiffs thereon. The first item for $1,875.60 and the second for $1,719.30 were for laying concrete under the side walls of the tunnel and for excavating therefor. This work was all beyond the “ ordered line of excavation,” which was a line one foot, two inches, below the base of the rails. The contractors were required by an order of the engineer to change the outside line of the structure which required excavation beyond the “ ordered line of excavation.” It appears that the contractors had been paid for like work on other parts of the contract. The facts were uncontroverted and the right of the plaintiffs to recover for these items depended upon the construction of the contract work. I am of opinion that the plaintiffs were entitled to recover therefor and that the verdict thereon was proper and right.
Item 3 for $648 is for extra concrete in the side walls, and item 4 for $2,508 is for extra tunnel excavation therefor. This work was required by the engineer and the city paid the contractor for other similar work. These claims were predicated upon a change in the plan. The only point presented by the evidence with respect to these two items which the defendant claimed required submission to the jury was as to whether this work was done in a.medium rock section or in a hard rock section, and the jury on conflicting evidence found in favor of the plaintiffs.
The 5th item for $327, and the 6th item for $292.50, and the 7th item for $440, and the 8th for $560, were for gravel placed in soft ground and the excavation therefor under the floor of the
Item 9 for $830 relates to extra rock excavation consisting of triangular pieces of rock at points where the sewer trenches and the subway excavation met, the removal of which became necessary for the safety of the subway and to expedite the construction thereof.
I am of opinion, therefore, that the plaintiffs were entitled to recover on the sixth cause of action in so far as they have recovered thereon.
Finally the appellant contends that these claims in behalf of the contractor were not presented to the chief engineer on or before the fifteenth day of the month following the accrual thereof, as required by article 43 of the contract, and that by virtue thereof the claims were forfeited. These claims were asserted in behalf of the contractors from time to time as they were required to perform the work, and they were thoroughly understood by the chief engineer, and he understood perfectly well that the contractors did not intend to waive them. If said article 43 applies to such claims, I am of opinion that the defendant should be deemed to have waived the formal presentation thereof. (See Foundation Company v. State of New York, supra.)
The other points have been examined and we find no merit therein.
It follows that the judgment should be modified, without costs to appellant, by eliminating therefrom the amount represented by the recovery on the first cause of action as already stated, and as so modified, affirmed.
Clarke, P. J., Dowling, Page, and Merrell, JJ., concur.
Judgment modified as directed in opinion and as so modified affirmed, without costs. Settle order on notice.