185 A.D. 609 | N.Y. App. Div. | 1918
Lead Opinion
The ground of the demurrer is that the defense is insufficient in law. The plaintiffs, on allegations contained in six separate counts, on an assignment from Patrick McGovern, seek to recover the sum of $284,920.84, together with interest, on-a contract made by him with the defendant through the Public Service Commission for the First District on the 13th day of February, 1912.
The defense to which the demurrer was interposed is, in substance, that the liability of the city on the contract was limited to the amount for which the board of estimate and apportionment had authorized the issuance of bonds, and that the amount so authorized, with the exception of the sum of $51,400.56, has already been paid. The defense is pleaded as a complete defense, which manifestly it is not; but that point, although referred to, is not taken by the learned counsel for the respondents, and both parties apparently are desirous of having the case decided as if the defense were pleaded as a partial defense. It being a matter of public importance, we deem it proper to express our views on the sufficiency of the defense so regarded.
On the 12th day of May, 1905, the board of rapid transit railroad commissioners of the city of New York, pursuant to authority conferred by chapter 4 of the Laws of 1891 and of the acts amendatory thereof and supplementary thereto, duly adopted a rapid transit route to be constructed, which as modified became known as the Lexington Avenue route, or route No. 5, extending from Battery Park to East One Hundred and Fifty-seventh street, in the city of New York. The Public Service Commission, the successor of said board (Laws of 1907, chap. 429), thereafter caused plans and specifications for the construction of the railroad to be prepared, thereby subdividing the work into sixteen sections, with a
The learned counsel for the city state in their points that the contract was awarded to McGovern “ for $1,961,997,” which is quite inaccurate and -with respect to a very material point, as I view the case. I find no provision of the contract indicating'that it was awarded for a gross sum, and fail to find these figures therein in any form. I infer from the resolution of the board of estimate and apportionment that on the estimated quantities of the different work and the price bid therefor by the plaintiffs’ assignor, if there had been no error in the estimates and no extra work required, the figures specified would have constituted the contract price of the work; but there was no agreement on the part of the city to pay the contractor that precise amount, and no agreement on his part to do the work for that amount. By the terms of the contract payments were to be made on monthly estimates according to the engineer's estimates of the amount and value of the work done, but fifteen per cent of the amount so certified by the engineer was to be deducted as security for performance until the amount so withheld aggregated $225,000, and thereafter ten per cent of the monthly estimates was to be deducted. The contractor was at liberty to make a cash deposit instead of giving a bond as security for performance; and by the terms of the contract it was expressly stated that he was not entitled to the return of the cash deposit or to the percentages so deducted from the monthly estimates until the engineer and Commission certified that all the work to be done had been fully completed. I emphasize this, for to my mind it has a very material bearing on the question of law presented, since' if the contention of the corporation should prevail, the contractor might be obliged to forfeit the amount of the percentages deducted monthly and would be without redress for any work
In the first count plaintiffs allege that from the time the contract was made until the 18th day of August, 1915, they were continuously engaged in the performance of the work and that at the last named date the work was fully completed, with the exception of minor matters; that the engineer of the Commission made forty-two certificates estimating the amount due the contractor for work performed on the unit basis, aggregating $2,277,096.05, the last estimate having been made on the 15th of January, 1916, and also made eight estimates and certificates in writing of work done and materials furnished by plaintiffs which could not be classified according to the unit basis, in the aggregate amounting to $38,943.73; that in order to protect and safeguard buildings adjacent to the subway and the subway itself, it became and was necessary to do a large amount of underpinning of buildings less than seven stories in height, and plaintiffs did the work, “ in many cases having been ordered to do So by the Public Service Commission and its engineers,” and that all of such work done by them was necessary and the major part was required in carrying out the original plans called for by the contract, and the balance was required by changes made in the original plans calling for additional and different work; that the unit price of such work prescribed by the contract was $82 per lineal foot, and that plaintiffs were obliged to underpin 1,824.71 lineal feet, the contract price of which was $149,626.22, and that the engineer wrongfully and unreasonably neglected and refused to make any estimate for this work, and that such refusal was in violation of the contract and owing to an erroneous construction thereof, and the Public Service Commission also declined to allow or to pay or to certify to the board of estimate and apportionment any amounts due plaintiffs for the underpinning; that a detailed statement of the amount claimed for that item was duly delivered to and left with the Public Service Commission and the finance department of the city prior to the commencement of the action; that on the 18th day of August, 1915, plaintiffs had substantially completed the contract and then demanded that defendant obtain a final certificate from the chief engineer
It is unnecessary to consider in detail the allegations of the various counts of the complaint. Suffice it to say that the second count was for 4,751 cubic yards of tunnel excavation, the unit price of which was $8.25 per yard, which was only allowed as for rock excavation at $4.65 per cubic yard, owing to an erroneous classification thereof; the third is to recover $51,831.74, for extra work and material; the fourth is for the other extra work aggregating $7,313.69; the fifth is for $44,514.39, the' extra cost of the work owing to errors in borings made by defendant and exhibited to bidders with respect to the nature of the material, and the sixth is for extra work and material required by the Public Service Commission and its engineers amounting to $64,326.32, but the claim for this item was reduced by the agreement referred to after the alleged substantial completion of the work to $25,000. The defense contains no denial, and, therefore, for the purpose of determining the demurrer, all the facts pleaded in the complaint are deemed admitted. (Douglass v. Phenix Ins. Co., 138 N. Y. 209; Devoe v. Lutz, 133 App. Div. 356.)
The fourth defense sets forth the provision of section 37 of
The learned counsel for the city strenuously argues that the liability of the city is limited by the limit prescribed by the board of estimate and apportionment with respect to the bonds. I think not, for there is no question of power here involved. It is not claimed that the constitutional
Section 149 of the charter (as amd. by Laws of 1910, chap. 545)
It follows, therefore, that the order should be affirmed, with ten dollars costs and disbursements.
Clarke, P. J., Smith, Page and Shearn, JJ., concurred.
Since amd. by Laws of 1912, chap. 226.— [Rep.
Since amd. by Laws of 1913, chap. 540; Laws of 1915, chap. 544, and Laws of 1917, chap. 625.— [Rep.
Since amd. by Laws of 1912, chap. 398, and Laws of 1917, chap. 401. — [Rep.
Concurrence Opinion
As to the items involving extra work in the first, third, fourth and sixth causes of action, whether performed on the order of the Public Service Commission, or made necessary by its changes of plan, it is quite clear .that the city cannot avoid payment merely upon the ground that it has not expressly authorized an issue of bonds or corporate stock in advance of the doing of the work, out of which to pay for such extra work. I base this conclusion mainly upon the ground that, when the board of estimate and apportionment gave its consent to the original McGovern contract, it consented to a contract which contemplated and provided for the doing of extra work upon the order of the Public Service Commission and as deemed necessary by the Commission without any limitation upon the amount of such extra work. It would have been entirely competent for the board of estimate to have refused to consent to any construction contract containing an extra work clause, on the ground that the amount of extra work was not limited, but when the board of estimate chose to rely upon the judgment and good faith of the Public Service Commission as to ordering extra work and gave its consent to a contract providing for extra work, it is plain that, whether judged by purely legal principles or by good faith, the city cannot successfully avoid payment for extra work, done on such order of the Public Service Commission, upon the mere ground that the board of estimate has failed to make the necessary appropriation. I considered these provisions of the Rapid Transit Act with care in People ex rel.
“ Acting under the provisions of the Rapid Transit Act and after taking the necessary preliminary steps, such as obtaining the constitutional consents, the preparation of the detailed plans and specifications and the holding of a public hearing upon the form of the contract, the commission adopted a form of contract for the construction of section 3. This form of contract was duly advertised for proposals in accordance with the provisions of section 36 of the Rapid Transit Act,
“ Subdivision 2 of section 37 of the Rapid Transit Act,
“ For answer to the legal question involved we must look to the Rapid Transit Act and see where the responsibility for the form of the construction contracts is lodged. It is difficult to see how any one who is familiar with the history of the Rapid Transit Act and its development can fail to see that the Public Service Commission is the body intended to be charged with responsibility for and authority over the form of the construction contracts. The Rapid Transit Act of 1891, as amended by the Legislature of 1894, contemplated the creation of a board composed of members named in the act to exercise the powers and duties prescribed therein and provided that such board, after obtaining the necessary constitutional consents, should be independent of municipal control, except in one instance, namely, that any contract for construction at municipal expense must, before execution, be approved as to form by the corporation counsel. The act contained a limitation upon expenditures for rapid transit construction, the limitation being, as embodied in chapter 752 of the Laws of 1894, amended by chapter 519 of the Laws of 1895, in substance as follows: ‘ The amount of bonds authorized to be issued and sold by this section shall not exceed $50,000,000 par value without the consent of the Legislature first had and obtained; provided, however, that
“ Of course, if the board of estimate chose to refuse to consent to a construction contract because of the presence of an extra work clause, or because the amount of extra work was not limited, it would have the right to do so, because to it belongs the power of authorizing expenditures. But that is not this case. It has consented to all the extra work that the commission deems necessary and without limit, and is merely seeking to control the discretion of the commission in determining which is the more advantageous way of arranging to have it done.
“ Moreover, the contention that the board of estimate and apportionment has the authority to alter the terms of the construction contract renders section 38 of the act
With reference, however, to .the causes of action involving strictly contract work, which on the basis of unit prices have resulted in exceeding the bond Emit prescribed when the board of estimate consented to the original McGovern contract and its amendment, the matter is not so clear. It seems, at first blush, as though holding the city hable for any excess over the appropriation tended to nullify the absolute control over expenditure for rapid transit purposes which the Rapid Transit Act, the charter and the sound principle of “ home
Smith, J., concurred.
Order affirmed, with ten dollars costs and disbursements.
See Laws of 1891, chap. 4, § 36, added by Laws of 1894, chap. 752, as amd. by Laws of 1909, chap. 498. Since amd. by Laws of 1913, chap. 540, and Laws of 1917, chap. 625.— [Rep.
Amd by Laws of 1909, chap. 498, and Laws of 1911, chap. 888. Since amd. by Laws of 1913, chap. 540, and Laws of 1917, chap. 625.— [Rep.
Sic. Statute reads “ local.”— [Rep.
Amd. by Laws of 1909, chap. 498, and Laws of 1910, chap. 205.— [Rep,
Renumbered from § 34, added by Laws of 1894, chap. 752, and amd. by Laws of 1909, chap. 498. Amd. by Laws of 1912, chap. 226, and Laws of 1917, chap. 625.— [Rep.
Amd. by Laws of 1909, chap. 498.— [Rep.
Amd. by Laws of 1909, chap. 498. Since amd. by Laws of 1912, chap. 226. — [Rep.
Amd. by Laws of 1909, chap. 498.— [Rep.