58 Ark. 7 | Ark. | 1893
This action is based on the act of the General Assembly of this State, entitled ‘ ‘ An act for the better protection of mechanics, artisans, material-men and other sub-contractors,” approved March 17th, 1885, and was brought on the 8th of December, 1890, to enforce a lien for labor performed and materials furnished in the construction of a building on certain lots owned by the defendants, Stark and Moore. The complaint in the action, as amended by interlineation, is as follows :
“ R. H. McPadden, Plaintiff,
vs.
“T. J. Moore, N. H. Stark, Chris Johnson, Defendants.
The plaintiff, R. H. McPadden, states that the defendants are justly indebted to him in the sum of nine hundred and eight dollars and seventy-nine cents for labor performed and materials used in the construction of a building owned by defendants, T. J. Moore and N. H. Stark, and known as the Stark and Moore building, and situated on parts of lots 14, 15, 16 and 17 of the old court house square in the city of Camden, county of Ouachita, and State of Arkansas, and more definitely described as follows, to-wit:
“ ‘A lot of land situated on the corner of Adams and Jefferson streets, fronting on Adams street 59 feet and 95 inches, and running back the width of the front with Jefferson street 110 feet to Ouachita alley. Said parcel of land being the southwest corner of the old court house square.’
1 ‘ That said labor was performed and material furnished at the request of the defendant, Chris Johnson, who had contracted with his co-defendants to construct said building, and by him used in the construction of said building. That he presented an itemized account of said labor and material to said defendant and contractor, Chris Johnson, who certified to the correctness of the items amounting to eight hundred and forty-eight dollars and seventy-nine cents, but refused to certify to the items amounting to sixty dollars. That thereupon plaintiff made affidavit to the correctness of the last named items, and also said refusal, and within ten days after the completion of the contract for said building by said Chris Johnson, on November 24, 1890, plaintiff, on 29th day of November, 1890, presented said itemized account, amounting to nine hundred and eight dollars and seventy-nine cents to defendants, T. J. Moore and N. H. Stark, certified and sworn to as above, and demanded payment of the same from them, which was by each of them refused, and at the same time (they) refused to endorse on the same the time of presentation or to hold back the whole or pro rata part thereof. That thereupon, and within ten days after the completion of the contract for said building by defendant Johnson, to-wit: on the 2nd day of December, 1890, plaintiff filed in the office of the circuit clerk of Ouachita county, in which said building is situated, said itemized account so certified and sworn to, with an affidavit attached thereto, showing the presentation of said account to said contractor, Johnson, and his action thereon and the action of plaintiff in making affidavit to said disputed items, amounting to sixty dollars, and his subsequent presentation, within ten days after completion of said contract by contractor Johnson, of said account to defendants, T. J. Moore and N. H. Stark, and his demand of payment of the same by them, and their refusal, as well ás their refusal to endorse on the same the time of presentation, and to hold out the full or jbro rata share of said account. Said affidavit also contained a correct description of the building in the construction of which said labor and materials in said account mentioned were used and the ground on which the same is situated. A copy of said account sworn to as above is filed herewith and asked to be made a part of this complaint. Plaintiff says that he has a lien upon said building and the ground on which the same is situated for said labor and materials. Wherefore he prays judgment for the sum of nine hundred and eight dollars and seventy-nine cents and costs against defendant, Chris Johnson ; that a lien be declared upon said building and land for the payment of the same, and for other relief.” On the margin of the complaint is the following amendment: “And at the time of furnishing the material to contractor, Johnson, he notified said Stark and Moore of his intention of furnishing said material and performing said labor on said building and the value thereof.”
The defendants, Stark and Moore, moved to strike out.the marginal amendment and demurred to the complaint, both of which the court.sustained, and rendered .judgment against plaintiff in favor of Stark and Moore; and plaintiff appealed.
The defendant, Chris Johnson, made no defense ; and judgment was rendered against him in favor of plaintiff for the amount of the account sued on.
The contract of the owner with the contractor is the authority by which the right is given to the contractor to erect or construct a building or other improvement on the ground of the owner, and is a limit of such right, and a measure of the liability of the owner for labor performed and material furnished in the making- and construction of the building or improvement. It is the foundation of the sub-contractor’s lien-. By it the owner consents to the services of the laborers and material-men employed by the contractor. In view of this fact, the law gives to the sub-contractor a lien on the improvement and the ground on which it is erected, on the performance of specified conditions, for the labor performed and materials furqished by him in the construction of. the improvement. But as the owner has only consented to pay, for the entire labor and materials necessary to complete the improvement, the sum he has stipulated to pay the contractor, the sub-contractor is necessarily limited in all cases in the amount of his lien to the contract price, unless the owner expressly or impliedly consents to a lien for an additional or further sum. As a compensation for the charge against his property, the owner is entitled to a credit on the contract price for the amount he is compelled to pay to relieve his land. In this way the owner is not forced to pay anything in addition to the stipulated price for services and materials, and the contractor is required to comply with his contract with laborers and material-men, and reasonable protection is provided for the sub-contractor, and the owner is secured. In protecting the sub-contractor the law places it without the power of the owner to defeat his lien by payments in disregard of his claim. Mansfield’s Digest, secs. 4405, 4421, 4424; Acts of 1885, p. 76, sec. 3; Shellabarger v. Thayer, 15 Kas. 619 ; Clough v. McDonald, 18 Kas. 114 ; Laird v. Moonan, 32 Minn. 358 ; Hunter v. Truckee Lodge, 14 Nev. 24 ; Lonkey v. Cook, 15 Nev. 58; McAlpin v. Duncan, 16 Cal. 126 ; 2 Jones on Biens, sec. 1290.
It is evident, therefore, that a plaintiff in an action to enforce a mechanic’s lien should set forth in his complaint so much of the contract of the owner with the builder as is necessary to show his lien and the amount thereof.
The only allusion to a contract of the owner in the complaint in question is contained in these words: “ who had contracted with his co-defendants to construct said building.” It is obvious that the complaint in this respect is indefinite and uncertain. This is a defect which cannot be reached by a demurrer, but must be taken advantage of, if at all, by a motion to make more definite and certain. Mansfield’s Digest, section 5082.
While the complaint in question is by no means a model of pleading, yet enough is stated in it to show that appellant was entitled to a lien for some undisclosed amount, under the act of March, 17, 1885. In view of this fact we have refrained from deciding whether a sub-contractor can be entitled to a lien for an amount exceeding his share of the reserved fund, under the act of 1885, as it is not shown that such share is not equal to the amount of his claim, and that it is necessary for us to decide the question in this case.
The judgment of the circuit court in favor of appellees is, therefore, reversed, and the cause is remanded with instructions to the court to deny the motion and overrule the demurrer, and for other proceedings.