LANIER AT MCEVER, L.P. v. PLANNERS AND ENGINEERS COLLABORATIVE, INC.
S07G1424
Supreme Court of Georgia
June 30, 2008
Reconsideration Denied July 25, 2008
(663 SE2d 240)
BENHAM, Justice.
ment corruption that the FOIA [and
Jamison S. Prime, A Double-Barrellеd Assault: How Technology and Judicial Interpretations Threaten Public Access to Law Enforcement Records, 48 Fed. Comm. L.J. 341, 345, 368 (1996). Because I would interpret the pending investigation exemption in the Open Records Act in a manner that encourages governmental officials and agencies to remain accountable to the people of Georgia, I respectfully dissent to Division 1 of the majority‘s opinion.
I am authorized to state that Chief Justice Sears and Justice Thompson join this dissent.
DECIDED JUNE 30, 2008 —
RECONSIDERATION DENIED JULY 25, 2008.
Hull, Towill, Norman, Barrett & Salley, David E. Hudson, Davis A. Dunaway, for appellee.
Susan J. Moore, Delong, Caldwell & Bridgers, Michael A. Caldwеll, Charles C. Olson, James F. Grubiak, Kemuel A. Kimbrough, Ted C. Baggett, Arnall, Golden & Gregory, Robert L. Rothman, Christopher K. Withers, amici curiae.
S07G1424. LANIER AT MCEVER, L.P. v. PLANNERS AND ENGINEERS COLLABORATIVE, INC. (663 SE2d 240)
BENHAM, Justice.
In June 2001, Lanier at McEver, L.P. (“Lanier“), a large construction developer, retained Planners and Engineers Collaborative, Inc. (“PEC“), a civil engineering firm, to design a storm-water drainage system for a 220-unit apartment complex Lanier was constructing. In the contract for services, Lanier and PEC agreed to the following clause:
In recognition of the relative risks and benefits of the project both to [Lanier] and [PEC], the risks have been allocated such that [Lanier] agrees, to the fullest extent permitted by law, to limit the liability of [PEC] and its sub-consultants to [Lanier] and to all construction contractors and subcontractors on the project or any third parties for any and all claims, losses, costs, damages of any nature whatsoever[,] or claims expenses from any cause or causes, including attorneys’ fees and costs and expert witness fees and costs, so that the total aggregate liability of PEC and its subconsultants tо all those named shall not exceed PEC‘S total fee for services rendered on this project. It is intended that this limitation apply to any and all liability
or cause of action however alleged or arising, unless otherwise prohibited by law.
After the apartment building was completed, Lanier discovered erosion and other physical damage which an expert attributed to PEC‘s negligent design of the storm-water drainage system. Lanier has spent $250,000 in repairs to the system thus far and expects to spend a total of $500,000 by the time repairs are complete. To recoup its damages, Lanier sued PEC for negligent construction of the drainage system, breach of contractual warranty and litigation expenses. In response, PEC filed a motion for partial summary judgment, seeking to invoke the parties’ agreement and limit its liability for any damages owed to Lanier to $80,514, which was PEC‘s total fee for services. The trial court granted PEC‘s motion for partial summary judgment and the Court of Appeals affirmed. Lanier at McEver, L.P. v. Planners & Engineers Collaborative, 285 Ga. App. 411 (646 SE2d 505) (2007). We granted Lanier‘s petition for certiorari to determine whether the limitation of liability clause in the parties’ construction contract violates Georgia‘s public policy. Because the clause violates Georgia‘s public policy as set forth in
1. “As a general rule a party may contract away liability to the other party for the consequences of his own negligence without contravening public policy, . . . except when such an agreement is prohibited by statute. . . .” Smith v. Seaboard Coast Line R. Co., 639 F.2d 1235, 1239 (5th Cir. 1981). At the time the parties entered into their contract in June 2001,
A сovenant, promise, agreement, or understanding in or in connection with or collateral to a contract or agreement relative to the construction, alteration, repair, or maintenance of a building structure, appurtenances, and appliances, including moving, demolition, and excavating connected therewith, purporting to indemnify or hold harmless the promisee against liability for damages arising out of bodily injury to persons or damage to property caused by or resulting from the sоle negligence of the promisee, his agents or employees, or indemnitee is against public policy and is void and unenforceable, provided that this subsection shall not affect the validity of any insurance contract, workers’ compensation, or agreement issued by an admitted insurer.
The purpose of
2. Georgia law defines indemnity as “the obligation or duty resting on one person to make good any loss or damage another has incurred by acting at his request or for his benefit.” (Citation and punctuation omitted.) Holmes v. Clear Channel Outdoor, 284 Ga. App. 474, 477 (644 SE2d 311) (2007).1 Although the clause at issue in this case does
agents or construction subcontractors of Lanier or PEC). This is because the clause applies to “any and all claims” by third parties and shifts all liability above the fee for services to Lanier no matter the origin of the claim or who is at fault. Thus, while a third party is not precluded from suing PEC for any negligent actions in constructing the storm-water drainage system, the clause at issue here allows PEC to recover any judgment amount entered against it from Lanier once the $80,514 threshold has been surpassed, including judgment amounts on third-party claims for which PEC is solely negligent.
In this case, the $80,514 threshold has already been met insofar as Lanier has expended a quarter of a million dollars to repair the drainage system. As a result, PEC will be able to recover from Lanier losses for all future third-party claims. This complete avoidance of liability to third partiеs for sole negligence in a building contract is exactly what
Nevertheless, PEC points to cases from other jurisdictions to support the argument that this clause does not violate public policy; however, decisions from other jurisdictions that uphold the enforcement of certain limitation of liability clauses may be distinguished from the clause in this case. For example, in Valhal Corp. v. Sullivan Assoc., 44 F.3d 195 (3rd Cir. 1995), the developer agreed the architect‘s liability to the devеloper and its project contractors/subcontractors for negligent acts would be limited to $50,000 or the total
fee for services,3 but did not agree that it would limit the liability of the architect regarding “any third parties for any and all claims” or that the limitation would “apply to any and all liability or cause of action however alleged or arising.”4 These two phrases, which appear in the clause at issue, shift PEC‘s liability for third-party negligence claims, which could be brought by any member of the public, to Lanier who would be required to reimburse
3. Assuming without deciding that this case is analogous to Emory Univ. v. Porubiansky, 248 Ga. 391, 393 (282 SE2d 903) (1981) insofar as it involves professional engineers who are statutorily charged with maintaining the safety and welfare of the public,7 we need not address this clause‘s viability under
Judgment reversed. All the Justices concur, except Hines and Melton, JJ., who dissent.
MELTON, Justice, dissenting.
The majority opinion сorrectly states that, as a matter of law, “[the] complete avoidance of liability to third parties for sole negligence in a building contract is exactly what
1.
an “[a]greement or contract in which one party agrees to hold the other without responsibility for damage or other liability arising out of the transaction involved.” Black‘s Law Dictionary 731 (6th ed. 1990). The clause in question here does not hold PEC harmless or without responsibility, it merely limits PEC‘s liability to pay damages. Irrespective of the contract between Lanier and PEC, PEC remains fully responsible and liable to third parties foreseeably injured by any negligent act committed by PEC. Samuelson v. Lord, Aeck & Sergeant, Inc., 205 Ga. App. 568, 572 (2) (a) (423 SE2d 268) (1992) (“Independently of the contract to design a building or premises, an architect or engineer owes a general duty to use reasonable care not to harm third persons who, it is reasonably foreseeable, might be harmed by a nеgligent architectural design.“). Such an injured third party could bring suit against PEC, and PEC would be liable to pay the extent of any damages awarded to that third party. If that payment, however, exceeded the amount of PEC‘s fees, it might then seek to enforce its contract with Lanier. This is the nature of a limitation of liability clause. Valhal Corp. v. Sullivan Assoc., 44 F.3d 195, 202 (II) (B) (3rd Cir. 1995). An indemnity or hold harmless clause, on the other hand, would require Lanier to wholly absolve PEC of responsibility for its actions, necessitating that Lanier would have to defend any claim against PEC as the party to whom any third party would look for recourse. That simply is not the case here. PEC remains liable for its negligence, despite the fact that its damages have been capped. As a result,
As the Court in Valhal Corp., supra at 202 (B) (1) explained:
The law recognizes different methods by which a party can limit his/her exposure to damages resulting from his/her negligent performance of a contractual obligation. An exculpatory clause immunizes a person from the consequences of his/her negligenсe. Similarly, an indemnity clause holds the indemnitee harmless from liability by requiring the indemnitor to bear the cost of any damages
from which the indemnitee is held liable. The instant clause has no such consequence. The clause before us does not bar any cause of action, nor does it require someone other than [PEC] to ultimately pay for any loss caused by [PEC‘s] negligence. [PEC] remains liable for its own negligence and continues to be exposed to liability up to a . . . ceiling. Thus, the amount of liability is capped, but [PEC] still beаrs substantial responsibility for its actions.
(Citations and footnote omitted.)
To reach its conclusion, the majority both prognosticates the result of a future trial in this case and relies on case law which fails to support its conclusion. In order to find that the contract clause in question could not possibly expose PEC to any liability from third parties, the majority states: “In this case, the $80,514 threshold has already been met insofar as Lanier has expended a quarter of a million dollars to repair the drainage
With regard to the case law cited by the majority, none of those cases supports the majority‘s ultimate conclusion. Each and every case deals with a situation in which one party wholly indemnifies and holds harmless the other party. Smith v. Seaboard Coast Line R. Co., 639 F.2d 1235 (5th Cir. 1981) (railroad indemnified and held harmless for all liability and damages); Frazer v. City of Albany, 245 Ga. 399 (265 SE2d 581) (1980) (agreement to indemnify and hold harmless from any and all losses); Hartline-Thomas, Inc. v. Arthur Pew Constr. Co., 151 Ga. App. 598 (260 SE2d 744) (1979); Borg-Warner Ins. Finance Corp. v. Executive Park Ventures, 198 Ga. App. 70 (400 SE2d 340) (1990) (agreement holding parties harmless from any and all liability and damages); Federated Dept. Stores v. Superior Drywall & Acoustical, 264 Ga. App. 857 (592 SE2d 485) (2003) (agreement indemnifying and holding party harmless from entire responsibility and liability). Nonе of the cases involves a situation like the one at hand, where liability has been capped. Instead of supporting the majority opinion, they make it clear that
clauses which purport to wholly indemnify or hold harmless a party. Again, no such clause is involved here.
Smith v. Seaboard Coast Line R. Co., supra, actually supports the conclusion in this dissent. In Smith, the district court determined that
[A]s a general rule, a party can protect himself by contract from liability for the consequences of his own negligent acts. As to contracts relating to the construction or maintenance of buildings, however, this statute changes this common law rule and, thus, should be strictly construed.
Strictly construed,
In reaching the opposite result, the majority overlooks the differences between indemnity and hold harmless provisions on the one hand and limitation of liability clauses on the other hand. Those very real differences
preclude [the majority‘s] assumption that a statute expressing a prohibition against indemnity and hold harmless provisions [such as
OCGA § 13-8-2 (b) ] announces a public policy against something as distinct and accepted as limitation of liability clauses. Indeed, . . . such an assumption has the practical effect of amending this statute.
Valhal Corp., supra, 44 F.3d at 205 (2). Without inherent authority or authorizing precedent, the majority so amends
Nonetheless, in some cases, damages may be capped at such a nominal level that a party may, in effect, be immunized from almost all liability for its negligent acts. In this instance, the clause in question might violate
censure by the appropriate review board. Therefore, under these circumstances, PEC‘s limitation of liability to the full extent of its fees is “not so drastic as to remove the incentive to perform with due care.” Valhal Corp., supra, 44 F.3d at 204. The majority‘s analysis, on the other hand, would seem to operate as a blanket prohibition precluding any limitation of liability between the parties whatsoever.
2. The contract clause in question in this case is also in compliance with the public policy underlying
A contract cannot be said to be contrary to public policy unless the General Assembly has declared it to be so, or unless the consideration of the contract is contrary to good morals and contrary to law, or unless the contract is entered into for the purpose of effecting an illegal or immoral agreement or doing something which is in violation of law.
Camp v. Aetna Ins. Co., 170 Ga. 46, 50-51 (152 SE 41) (1930).
Although professional engineering is a licensed profession controlled by the State and in which the State holds a strong interest,10 the contractual limitation of liability at issue in this case does not violate public policy for several reasons. First and foremost, the contract does not actually relieve PEC from acting with the appropriate standard of care for professional engineers. The contract states:
PEC shall perform services for [Lanier] in a professional manner, using the degree of care and skill ordinarily exercised by and consistent with the standard of competent consultants practicing in the same or similar locality of the site. This warranty is in lieu of all other warranties, either express or implied.
Therefore, even with regard to Lanier, PEC is required to act with the requisite standard of care imposed by law upon all professional engineers. Second, the contract neither eliminates nor reduces PEC‘s exposure to сlaims by members of the general public. Irrespective of any limitations in its contract with Lanier, PEC‘s duty of
reasonable care towards third parties who might foreseeably be harmed by its design, if negligent, remains viable and actionable if breached. See, e.g., Samuelson, supra. Therefore, even though PEC‘s exposure to damages may ultimately be capped, PEC still has a substantial incentive to act with the appropriate standard of care to avoid potential exposure to members of the public other than Lanier.11 Third, both parties to this contract, one a professional construction firm and the other a professional engineering firm, were sophisticated business associations with extensive experience and knowledge about the services which were the subject of the agreement. As a result, the contract in question is the result of informed bargaining by savvy parties of equal footing. Finally, the contract in question was not a standardized adhesion contract in either the terms it contained or in the way that it was negotiated between the parties. The agreement was voluntarily entered into without being forced upon either party in any way. For all of these reasons, it cannot be said, clear from all doubt, that the contract clause in question violates public policy, and this situation is not one in which this Court should exercise the delicate and undefined power to declare otherwise. See, e.g., Orkin Exterminating Co. v. Stevens, 130 Ga. App. 363 (203 SE2d 587) (1973); Piedmont Arbors, supra. See also Valhal Corp., supra.
Although Lanier contends that this matter is controlled by Emory Univ. v. Porubiansky, 248 Ga. 391 (282 SE2d 903) (1981), that case is distinguishable. Porubiansky dealt
I am authorized to state that Justice Hines joins in this dissent.
DECIDED JUNE 30, 2008 —
RECONSIDERATION DENIED JULY 25, 2008.
James C. Morton, for appellant.
Greenfield, Bost & Kliros, William L. Bost III, Michael W. Lord, for appellees.
Shapiro, Fussell, Wedge & Smotherman, H. Fielder Martin, Stephen L. Wright, Freеman, Mathis & Gary, T. Bart Gary, Katie W. Barber, Webb, Tanner, Powell, Mertz & Wilson, Anthony O. L. Powell, Bondurant, Mixson & Elmore, H. Lamar Mixson, Lisa R. Strauss, Deborah J. LaFetra, Elizabeth A. Yi, amici curiae.
Notes
An indemnity contract is defined by Black‘s Dictionary of Law as “[a]n agreement between two parties, whereby the one party, the indemnitor, either agrees to indemnify and save harmless the other party, the indemnitee, from loss or damage, or binds himself to do some particular act or thing, or to protect the indemnitee against liability to, or the claim of, a third party.” [Cit.] “Indemnity” means “reimbursement, restitution, or compensation.” [Cit.] “In a contract of indemnity the indemnitor, for a consideration, promises to indemnify and save harmless the indemnitee against liability of the indemnitee to a third person, or against loss resulting from such liability. The contract of the indemnitor is an original undertaking.” [Cit.] As stated in the written opinion of the trial court, “[a]n indemnity contract differs from a guaranty in that the former is an original rather than a collateral undertaking and generally undertakes to make good the promisee‘s loss resulting from his liability to another rather than from another‘s liability to him.” [Cit.]
The OWNER agrees to limit the Design Professional‘s liability to the OWNER and to all construction Contractors and Subcontractors on the project, due to the Design Professional‘s professionаl negligent acts, errors or omissions, such that the total aggregate liability of each Design Professional shall not exceed $50,000 or the Design Professional‘s total fee for services rendered on this project.
