Opinion by
This is an appeal from an order of the Court of Common Pleas, Allegheny County, denying appellant United States Steel’s motions for judgment n.o.v. and for a new trial.
Plaintiff’s decedent was employed by the Langen-felder Co. as a machinery operator. Langenfelder was an independent contractor of U. Í3. Steel at an iron orе processing plant in Saxonburgh, Pennsylvania. Lan-genfelder’s responsibility under the contract involved the stockpiling of iron ore when delivered to the plant, and the recovery of the ore when needed in the plant.
The ore arrived by railroad car and was loaded into giant earth moving machines called “Euclids” which were supplied by Langenfelder and were capable of hauling 40 tons of ore. The Euclids were then driven to an area designated by U. S. Steel where the ore was piled. In order to pile the ore, the operators had to drive onto the pile and release the ore as they traveled along the top of the pile.
Beсause ore was available only on a seasonal basis, stockpiling of considerable amounts of ore was required during the summer months. In depositing ore on the top of the pile, and in order to make maximum use of the area used for piling, the Euclid drivers were required to spread the ore evenly across the top of thе pile so that the pile would not peak and thus limit its height. To do this, the Euclid operators had to drive within iy2 to 2 feet of the edge of the pile while depositing the ore. At times, the piles reached heights of two hundred feet.
During peak periods of ore shipment, the stockpiling operations were conducted on an around-the-clock basis. Euclid operators testified that visibility during the night shifts was very poor, and that the edge of the pile was practically indiscernible. Other than the headlights of the Euclids, which were of the same inten
Appellee’s decedent was employed by Langenfelder as a Euclid operator. On the night of August 28, 1968, decedent was assigned to work the edge of a 40-50 foot high ore pile. At approximately 2:00 a.m., the de
Langenfelder had performed these operations under contract with the appellant since 1958, and worked as scheduled by the appellant. U. S. Steel safety personnel were at the stockpiling operation on a daily basis. The general fоreman of the Saxonburg operation testified that he was familiar with Langenfelder’s operations and knew that the Euclids had to operate close to the edge on an around-the-clock basis. Other Euclid operators testified that their vehicles had run off the edge on several prior occasions during the night shift due to the рoor visibility at the edge of the pile.
After a jury returned a verdict for the appellee, appellant moved for a judgment n.o.v. or for a new trial. Appellant contends, inter alia, that the court erred in refusing these motions because Pennsylvania law does not impose liability on the employer of an independent сontractor under these facts.
Normally, an employer of an independent contractor is not responsible for the negligent acts or omissions of the contractor or its employees. Under v. Coplay Cement Mfg. Co.,
There are, however, exceptions to this general rule of non-liability, and the instant case, falls within one of these exceptions. The exception does not rest upon any personal negligence of the emрloyer, but is a rule of vicarious liability. The rule is stated in Section 416 of the Restatement of Torts, 2d:
“One who employs an independent contractor to do work which the employer should recognize as likely to create during its progress a peculiar risk of physical harm to others unless special precautions are takеn, is subject to liability for physical harm caused to them by the failure of the contractor to exercise reasonable care to take such precautions, even though the employer has provided for such precautions in the contract or otherwise.”4
In the instant case, the appellee contendеd that the decedent was exposed to a peculiar risk (“running the edge” at night) which necessitated special precautions (the provision of adequate lighting to illuminate the pile) that the contractor negligently failed to take. Thus, the appellee argues that appellant was properly found liable for thе contractor’s failure to take said precautions.
Comment (e) further explains “peculiar risk”. “It is not essential that the peculiar risk be one which will necessarily and inevitably arise in the course of the work, no matter how it is done. .It is sufficient that it is a risk whiсh the employer should recognize as likely to arise in the course of the ordinary and usual method of doing the work, or the particular method which the employer knows that the contractor will adopt.”
Section 416 is thus applicable only to situations in which the negligence of the independent contractor consists of thе failure to take the precautions necessary for the safe performance of a task. The risk of harm must arise from the peculiar or inherent nature of the task or the manner of performance, and not the ordinary negligence which might attend the performance of any task. “[Lliability does not ordinarily extend to so called ‘collateral’ or ‘casual’ negligence on the part
The cases cited by appellant are inapposite. In Hader v. Coplay Cement Manufacturing Co., supra, plaintiff’s theory of recovery was the retention of control by the employer over the operations of the independent contractor. The court found a lack of control and, therefore no liability on the employer. See also, Fisher v. United States,
Only two Pennsylvania Supreme Court cases have cоnstrued §416. In Philadelphia Electric Co. v. Julian, supra, n.3, the independent contractor was held liable for its sub-contractor’s negligence in failing to take precautions necessary to guard against damage to underground gas mains in the installation of guard rails. Although the subcontractor should have recognized the danger of excavating near the gas mains, tiie emplоyer was nevertheless held liable under §416 for its failure to further warn. The employer was held liable despite the fact that it may have relied on the independent’s knowledge of the danger. The Pennsylvania case denying recovery on the basis of §416 is Brletich v. United States Steel Corp.,
Appеllant’s contention that the court erred in not instructing the jury that the peculiar risk be “one of abnormally great danger” is without merit. The Court charged almost verbatim the Restatement language which contains no requirement that an abnormally great danger be present, and, in fact, specifically excludes such a requirement. See Comment (b) to §413 explaining peculiar risk as that term is used in §416; Gee also Comment (d) to §416, supra.
Appellant’s argument that there was insufficient evidence to establish proximate cause of the injury is equally without merit. It is clear that a plaintiff need not exclude every conceivable cause of an accident in order to recоver. Jones v. Treegoob,
Judgment and order affirmed.
Notes
There was no error in allowing the testimony of appellee’s safety expert. The witness was a highly qualifiеd engineer with extensive experience in safety engineering whose qualifications were unquestioned by appellant at trial. His qualifications and experience convincingly establish his competency. Griffith v. Clearfield Truck Rentals,
Appellant’s contention that this evidence of other aim liar acсidents was inadmissible is without merit as it was offered to show notice of a dangerous condition and admitted for this limited purpose. Yoffee v. Pennsylvania Power and Light Co.,
Section 416 was adopted in Pennsylvania in Philadelphia Electric Co. v. Julian,
The Section renders irrelevant contract provisions placing the responsibility for all necessary safety precautions on the independent contractor. Appellant’s right of indemnity against cоntractor by virtue of a contract is not involved herein.
There is no contention that the decedent, as an employee of the contractor, was not within the scope of the coverage of §416.
The distinction between “ordinary risks” and “peculiar risks” has been described as “shadowy at best”. The definitions appearing in the Restatement provide general guidelines for making the distinction, and the illustrations give examples contrasting ordinary and peculiar risks. See Illustration 3 to Comment (e) and Comment (d) to §416. The determination is a mixed question of law and fact, and may, in clear cases, be made by the trial judge as a matter of law. West v. Guy F. Atkinson Construction Co.,
Since the inception of its operations in 1958, Langenfelder’s methods did not change. Operations were continually conducted on an around the clock basis during summer months.
We cannot find any reversible error in the testimony of appellee’s actuarial expert. Although the practice of an actuary placing a final figure representing present worth has been condemned as possibly usurping the jury’s function in determining a decedent’s present worth [see Allendorf v. Elgin, J. & E. Ry. Co.,
