142 Ala. 506 | Ala. | 1904
It appears from the cross-bill of the owner, The Mobile Lodge No. 108 Benevolent and Protective Order of Elks, to which the demurrer was interposed by The D. J. McDonald Stone Company, that after the McDonald Company had given the owner notice that it claimed a lien as a sub-contractor for the labor and materials furnished the contractor -as required by § 2731 of the Code, that the owner advanced to the contractor, as a part of the contract price, a sum of money
After this advance was made, other material men and subcontractors gave notice that they claimed liens, but the amount which became due to the contractor, by reason of the advance to him was wholly insufficient to pay all the lienors.
It is not averred in the cross-bill that the contract contained stipulations authorizing the -advance of the money to the contractor. The point made by the demurrer is that The McDonald Stone Company had a lien upon the money paid or advanced to the contractor.
It is first contended by counsel for the Mobile Lodge, the owner, that under the facts alleged, it had the right to make the payment or advancement because there was, at the time of the service of the notice, nothing due the contractor — no such sum was then due to him payable presently or in the future for the reason that he had not then earned it by completing the building. This contention, if we understand it correctly, is predicated upon the proposition that the statutes only give a lien to material men and subcontractors upon any unpaid balance due the contractor by the owner at the time of the service of the notice.
The logic of this contention would lead to the result that if on the day the notice is served there be nothing actually due the contractor, but on the next day or the next week thereafter, there becomes due to him on the contract a sum of money, the material men or subcontractor would have no lien upon it as an unpaid balance and could not subject it.
In the recent case of Alabama & Georgia Lumber Company v. Tisdale, 139 Ala. 250, Ave passed upon this question. In that case Tisdale, the owner, after notice that plaintiff claimed a. lien, made a payment to the contractor. We held that he was liable, and among other things said that “the unpaid balance as used in the statutes means any sum of money which is due Avhen the notice
That what was there said is the correct construction of the statutés we need, it seems to us, only quote that provision of § 2731 of the Code, providing for notice to the owner, which is in this language, viz; “after such notice, any unpaid balance in the hands of the owner or proprietor shall be held subject to such lien.” But it may be said that Greene v. Robinson, 110 Ala. 507, is opposed to this conclusion. Indeed, that case seems to be relied on as supporting the contention here made. It is true the opinion contains the statement that “the law is very clear that it is only the unpaid balance in the hands of the owner or proprietor at the time of notice to him, that can be made subject to plaintiff’s claim and for which a lien can be enforced.”
But the question here presented and the one presented in Alabama & Georgia Lumber Company v. Tisdale, were not involved in that case, as will be readily seen by a reference to the facts and the exception reserved to the ruling of the trial court brought here for review. In that case the plaintiff’s notice was given on the 19th day of November, 1894. On the trial the defendant, owner, offered to prove by the contractor that he owed him nothing on account of the contract after the 16th day of November, 1904. The court refused to permit this to be done. And this was the question that this court was called upon to decide and it was with respect to that question that the language quoted above was employed.
The McDonald Company having a lien, under the statutes, upon any unpaid balance that may become due under the contract to the contractor, could the owner defeat or impair that lien by advancing money upon the
The case of Mobile Street Railway v. Turner, 491 Ala. 213, is relied upon as establishing the right of the owner
In that case, which was a garnishment, the contract contained an express stipulation conferring upon the owner the right to provide, (upon a certain contingency which the uncontradicted answer of the garnishee disclosed had arisen) at the expense of the contractor, all materials and labor necessary to a completion of the building, which expense was to be deducted from the contract price to be paid the contractor. It clearly has no application here.
But it is insisted that the owner was justified in paying this money, although The McDonald Company had a lien upon it, because after its paymnet there would have become due, upon the completion of the building, to the contractor, a sufficient sum to have paid The McDonald Comptny’s claim, had not it been for the intervention of other lienors.
There is no pretense that The McDonald Company did any thing which induced the payment here sought to be justified. Its justification is predicated upon § 2744 of the Code. To see that this section does not support the contention, we need only quote it: It reads as follows : “When the lien is sought, to be ¡enforced by any person other than the contractor, it shall be the duty of the contractor to defend the suit at his own expense; and after notice of an intention to file a statement of the lien, and pending the suit, the owner or proprietor may withhold from the contractor money sufficient to-cover the amount claimed, and the probable cost and expense of suit; and in case of recovery against the owner or proprietor, or his property, he shall be entitled to deduct from the amount owing by him to the contractor the amount of such judgment, costs and expense ; and if he shall have settled with the contractor, he shall be entitled to recover from the contractor the amount recovered of. and paid by him; and such recovery may be had in the same court, on motion', on three days’ notice.”
The demurrer to the cross-bill should have been sustained, instead of being overruled.
The decree overruling the demurrer to the cross-bill will be reversed and one will be here rendered sustaining it.
Reversed and rendered.