69 Mo. App. 524 | Mo. Ct. App. | 1897
The plaintiff is a builder and the defendant is a contractor of excavation work. On the fourteenth day of June, 1895, the plaintiff was awarded the contract for the construction of a building on the west side of Talmage avenue, where it intersects the
“ C. B. McCormack,
“Dear Sir: — I will grade the lot and excavate the trenches and pier holes for foundry on Talmage avenue for the sum of three hundred and twelve dollars.
“Respectfully, John A. Lynch.”
When plaintiff was notified that the contract had been awarded to him, he immediately notified the defendant that his bid was accepted, and requested the latter to begin work immediately. On the next day they met on the ground for the purpose of locating definitely the work, when the defendant declined to do the work on the ground that in making his estimate of the cost of the grading and excavation he supposed that the building was to be erected on the lot on the east side of Talmage avenue, which required much less grading than the lot on the west side, and that on account of this alleged mistake he was not bound by his proposal. The plaintiff let the work to another contractor for $825. The plaintiff brought this action against the defendant, claiming as damages the difference between defendant’s bid and the amount he had to pay to have the work done, and also damages for a delay of two days, making a total of $527. The answer is a general denial. The cause was submitted to the court without the intervention of a jury, and judgment was entered for $533. The defendant has appealed and complains of the instructions and also that the judgment is excessive.
The evidence for the plaintiff tended to prove the
Against the objections of plaintiff the circuit court permitted the defendant to introduce evidence tending to prove that preparatory to making the bid he examined the plans and was unable to determine from them the exact location of the proposed building; that he went to Talmage avenue where it intersects the track of the Missouri Pacific Railroad, and that from the best information he had he located the building site on a lot on the east side of the avenue; that the surface of that lot corresponded with the floor level of the proposed building above the railroad track as shown by the plans, and that believing that lot to be the true location he made his estimate on it instead of the lot on the west side of the avenue. His evidence also tended to prove that the lot on the west side of the avenue was much above the required grade; that the excavated dirt would have to be hauled a long distance, and that the amount bid by him was much less than the actual cost of the work.
In rebuttal of his evidence the plaintiff testified that he did nothing to mislead the defendant as to the location of the building; that at the time he accepted the bid he was not aware that the defendant was laboring under the alleged mistake; that he saw the site of the building for the first time when he and defendant went there together for the purpose of locating it; that previous thereto he knew nothing about the lot, and that it was not necessary that he should know, as in making his bid for the entire work he based his estimate of the cost of the excavation on the defendant’s bid.
The theory of the plaintiff’s instructions which were given, is that if the defendant made the bid and it was accepted by plaintiff before it was withdrawn
A party who enters into a contract under a mistake as to a material matter may, under certain conditions, be relieved in equity from his obligation. In the case at bar the defendant could have avoided a recovery if his alleged mistake had been induced by some concealment or misrepresentation on the part of the plantiff. Some authorities hold that he would be released even if the plaintiff was conscious of the fact that he was laboring under the mistake. But such a defense is equitable in its character and must be pleaded, which the defendant failed to do. In justice to the plaintiff, however, it must be said, that there is no evidence to show that he by word or act contributed to defendant’s mistake, or even had reason to believe or suspect that the defendant was in error as to the true location of the building.
It follows that the judgment of the circuit court must be affirmed.