3 La. Ann. 285 | La. | 1848
The judgment of the court was pronounced by
The plaintiffs allege that, on the 13th of January, 1836, they entered into a contract with the defendants for the construction of the West Feliciana Railroad, which contract is annexed to their petition; that the work required, and the materials to be furnished to execute this contract, amounted to the sum of $500,000, including extra charges for changes and alterations; that soon after the date of this contract they entered upon the execution of it, and continued to discharge their obligations under it up to the 1st of August, 1836, when they were under the necessity of suspending operations; but that antecedently they had taken all the steps and measures necessary for the full compliance with the said contract on their part, by engaging laborers and workmen, purchasing the necessary quantity of lumber, providing tools, implements, &c. They further represent that they furnished all the necessary materials to construct, and did actually construct, a large portion of the road, and that the said materials and labor, together with extra allowances for changes of tresslework to embankment, with other extra work and materials and lumber supplied, are worth the sum claimed. The petition further charges that, by another contract with the defendants, they were bound to make a bridge across the bayou Sara, for which they are entitled to recover $30,000. The plaintiffs ask judgment for $530,0015.
They further allege that the defendants failed and refused to comply with the contract on their part, for this: First, that they'did not, after the expiration of the first month, pay the sums due petitioners under it, neither did they thereafter pay them monthly the several sums due them. - Secondly, that they did not furnish the iron plate, rails, cut iron, chains, splicing plates, and a requisite quantity of spikes, and neglected to have an engineer on the premises. Thirdly, that the defendants did not permit their engineer to make true and correct estimates of the amount of work done by the plaintiffs at the expiration of each month, according to his own knowledge of the amount and character of said work, and his own measurement of the same, and the true intent and meaning ,of the contract; b.ut, to the injury of the rights of the plaintiffs, insisted upon said engineer’s making his monthly estimates of the work and labor done by the plaintiffs, at the caprice and pleasure of the president and directors or .agents of said company. Fourthly, that the defendants insisted upon paying the estimates incorrectly made as above charged, in the depreciated notes of the West Feliciana Railroad Bank, and other depreciated bank notes of the State of Mississippi, and wholly refused to pay the same in gold or silver-, or in good bank paper. Fifthly, that the defendants wholly refused to pay petitioners the value of the work and labor done, and materials furnished in carrying out the change from tressle-work to embankment, and refused to furnish engineers to make estimates for the same. Sixthly, that the defendants wholly and altogether refused to pay petitioners the value of materials and lumber furnished by them in the construction of said road, and refused to permit their engineers to make estimates of the same. Seventhly, that the defendants neglected to procure the right of way over the land through which the railroad was to pass, although repeatedly requested to procure the same by petitioners.
Eighthly, that the defendants refused to allow estimates to be made for the
The petitioners further allege that they have sustained much loss on a steam saw-mill built by them at the request of the defendants, and also on horses, carts and other necessary implements purchased by them to be used in the construction and completion of said railroad : That they often requested the defendants to comply with their stipulations, and notified them that they would not waive any of their rights: That the defendants still neglecting to perform, they were duly and legally put in default; That the said defendants, intending to take an unwarrantable advantage of petitioners, instructed their engineer, after they had been put in default, to declare and determine the said contract to be abandoned; and that, in consequence of the premises, the petitioners have sustained damage to the amount of $500,000.
The defendants admit the existence of the contract, but deny every other allegation. They further aver that, the plaintiffs are precluded and estopped from contesting or disputing the correctness of the estimates of the engineers of the company, both by the terms of the contract sued on, and by the allegations and admissions in their original petition ; that the plaintiffs were at all times in delay and in default; that they did not commence working at the time stipulated, por deliver the work within the time stipulated ; nor did they complete and finish the grading of any one mile of the road, nor in any manner comply with their contracts; that said contract was properly terminated; and that the defendants, on their part, did comply with the'contract and were ready and willing to continue to do so-. They further aver that they have made advances to the plaintiffs as appears- by an account annexed to their answer, and pray for judgment in reconvention against them for the amount of those advances and interest; that they advanced the p&intiffs the sum of $9,500, on account of the erection of the bridge mentioned in the petition, but that before the said bridge was completed, it fell down and was destroyed, aDd the materials composing it have been since seized and- sold as the property of the plaintiffs by one of their creditors, whereby the said plaintiffs became bound to refund to the respondents the aforesaid sum. The answer further states that TJsal Hopkins, one of the original members ef the firm of Isaac McCord 8f Co., died on the 20th of September, 1837; that by his death the contract was cancelled, and the subset quest abandonment of it could not have subjected them- to damage, even if the plaintiffs had faithfully executed the contract up to that time.- The defendants' also- claimed damages for the alleged breaches of contract by the plaintiffs, but that claim has been discontinued.
Upon these pleadings the ease was submitted to-a jury, who returned a nominal verdict in favor of the plaintiffs. The plaintiffs have appealed from the judgment rendered on this verdict; but their counsel have informed us that, unless this court can amend it in their favor, it is their wish that it be affirmed-, rather than the should case be sent back for a new trial.
Our attention- is first called to several bills of exception taken by the plaintiffs-’’ counsel, some of which require to be noticed.
Two of these bills were taken to the opinion of the-court rejecting the d;epo" sitionsof A. JBr Hamilton and Charles A. Snyder, on the ground of interestin' the result of the' suit. These witnesses were absent, and their testimony was taken on-behalf of the plaintiffs, under a- commission. On its being offered, the defendants objected to it, on the ground stated. These two witnesses are shown to have represented themselves as partners of the plaintiffs. In a nota
The other bills of exception were taken to the charge of the court to the jury, and to the refusal of the court to charge the jury as prayed for by the plantiffs’ counsel. As the ease is before us in a situation that will enable us to pass finally upon the rights of the parties, an examination of those bills of exception becomes unnessary. .
Each of the parties charges the other with many grievous breaches of contract, and the evidence goes far to show that their complaints in that respect are equally well founded, and that both were in default from the beginning. But with a view to simplify the inquiry, we will first consider the case on the¡ hypothesis most favorable to the plaintiffs, that they had faithfully executed the contract until the 25th of September, 1837, and that the notice given them on that day by the engineer of the company that it was abandoned, was an active breach of it. The question will then be what is the rule of damages which should govern, and what evidence is required to establish them. That question was lately before us in a case not unlike the present—that of Seaton v. The Second Municipality, ante p. 44. We then held that where a contract is broken before the time of full performance and the party elects to consider it. in that light, and sues for damages also before the time of full performance, the market value at the time of the breach, when there is a market value, i» the measure of damages. In that case there was no market value, and we considered that the question involved a minute inquiry into the cost of the materials, the expense of their transportation to. the place where they were to be used, the quantity of labor required and the value of that labor, the whole to be assessed at the time of the breach. The .present case differs from this only in the circumstance that it was commenced after the time for full performance, and that as the state of the market in respect to prices was susceptible of explicit and intelligible proof at the time of the trial in the court below, no conjectural estimate was required to ascertain what would have been the expense of a complete execution of tho contract.
The defendants have received and kept labor and materials of the plaintiffs, and have made to them various payments, and the only question left open for our decision involves the settlement of their accounts, to be made in conformity with the foregoing dispositions of law. Two separate surveys and estimates of the work done, and of the materials furnished, by the plaintiffs, have been made by two competent engineers, proportionably to the prices agreed on in the contract. The difference between them is not material, and the defendants are willing that the highest should be taken as true. It amounts to §44,423 63. The plaintiffs’ counsel alleges that this estimate is too low; that it only allows them the price of common excavation for the excavation of many thousand yards of hard pan; that it makes no allowance for the transport of a large quantity of spoil bank beyond the distance of 120 feet, for other extra work, and for losses sustained on implements and machinery. The survey made, ex parte, for the plaintiffs by Baggerly, and the testimony of their clerk, Joseph A. Brown, cannot be taken for true, in opposition to the surveys and estimates of the engineers Banks and Petrie, and the testimony of the witnesses who attended them. The surveys and estimates of Banks, which the defendants admit to be true, were made monthly under the contract; the plaintiffs in whose presence they were made, received partial payments under them. We have no doubt of their correctness, as far as they go. The witnesses swear that there is no hard pan, properly so called, on the line of the railroad, but that
The transportation of- the spoil bank-beyond the distance of 120 feet, is shown to have been made with the approbation of the engineer of the company, and the plaintiffs were entitled to compensation for it under the contract.
The engineers of the company testify that other extra work was done by the plaintiffs, which inured to the benefit of the defendants; and it is a serious question, whether, after- the termination of the contract by the net of God, the plaintiffs are not in good- conscience entitled to some indemnity for the loss they are shown to have sustained on- their machinery, and particularly on the steam saw mill erected-by them for the sole purpose of preparing the timber necessary for the road.- The defendants have paid the plaintiffs on account of the railroad $34,078 92; and on account of the bridge, which was destroyed, as alleged in the answer, $9,500. They have discounted for them a note of hand, on which there is a balance-due of 21,581 33 ; and finally they have advanced to them in money $3,100.
The evidence in the record is not sufficient to enable us to ascertain the real amount duo the plaintiffs over and above the estimate of' Banks ; but we are satisfied that the whole- amount of their claim would not exceed that of the defendants; and as the defendants have asked that the judgment be affirmed rather than the case should be sent back for a new trial, in order to ascertain the amount due them, the decree of the court will conform to that request.
Judgment affirmed.