RICHARD MсCAULLEY, INDIVIDUALLY AND AS PERSONAL REPRESENTATIVE OF THE ESTATE OF MICHELLE McCAULLEY, APPELLANT, V. C L ENTERPRISES, INC., A NEBRASKA CORPORATION, ET AL., APPELLEES.
No. S-20-075
Nebraska Supreme Court
May 7, 2021
309 Neb. 141
Summary Judgment: Appeal and Error. An appellate court will affirm a lower court’s grant of summary judgment if the pleadings and admitted evidence show that there is no genuine issue as to any material facts or as to the ultimate inferences that may be drawn from those facts and that the moving party is entitled to judgment as a matter of law. An appellate court reviews the district court’s grant of summary judgment de novo, viewing the record in the light most favorable to the nonmoving party and drawing all reasonable inferences in that party’s favor. - Pleadings: Judges: Words and Phrases: Appeal and Error. A district court’s denial of a motion for leave to amend a complaint is reviewed for an abuse of discretion. A judicial abuse of discretion exists if the reasons or rulings of a trial judge are clearly untenable, unfairly depriving a litigant of a substantial right and denying just results in matters submitted for disposition.
- Limitations of Actions: Negligence: Breach of Warranty: Contractors and Subcontractors. The limitations period in
Neb. Rev. Stat. § 25-223 (Reissue 2016) applies to defective construction claims brought against contractors and builders, whether such claims are based on negligenсe or breach of warranty. - Limitations of Actions: Contractors and Subcontractors. When the basis of a claim against a builder or contractor is improper workmanship resulting in defective construction, the statute of limitations under
Neb. Rev. Stat. § 25-223 (Reissue 2016) runs from the date of substantial completion of the project, not the date of any specific act which resulted in the defect. - ____: ____. Determining when a construction project is substantially complete for purposes of the limitations period under
Neb. Rev. Stat. § 25-223 (Reissue 2016) requires consideration of the nature and scope of the agreed-upon project. - Pleadings: Rules of the Supreme Court: Appeal and Error. When a party seeks leave to amend a pleading, appellate court rules generally require that leave shall be freely given when justice so requires. Denial of leave to amend pleadings is appropriate only in those limited circumstances in which undue delay, bad faith on the part of the moving party, futility of the amendment, or unfair prejudice to the nonmoving party can be demonstrated.
- Pleadings: Summary Judgment: Evidence. Generally, it is not an abuse of discretion to deny leave to amend when a party seeks to add a new claim or defense after a motion for summary judgment has been heard and submitted, unless evidence or testimony exists in the record indicating the proposed claim or defense was newly discovered or that counsel was previously unaware of the claim.
Appeal from the District Court for Douglas County: W. RUSSELL BOWIE III, Judge. Affirmed.
Andrew M. Hollingsead and Michael J. Matukewicz, of Liakos & Matukewicz, L.L.C., for appellant.
Robert D. Mullin, Jr., of McGrath, North, Mullin & Kratz, P.C., L.L.O., for appellee Able Plumbing, Inc.
Robert M. Schartz and Julie M. Ryan, of Abrahams, Kaslow & Cassman, L.L.P., for appellee Timberland Hardwood Floors, Inc.
Danny C. Leavitt, of Salerno & Leavitt, for appellee Dan Becker.
Daniel J. Welch, Damien J. Wright, and Daniel McDowell, Senior Certified Law Student, of Welch Law Firm, P.C., for appellee Hardscape Contractors, LLC.
HEAVICAN, C.J., CASSEL, STACY, FUNKE, PAPIK, and FREUDENBERG, JJ.
In this construction defect case brought by homeowners against several contractors, the district court found the homeowners’ claims were time barred under
BACKGROUND
In approximately November 2006, Richard McCaulley and Michelle McCaulley began construction on a home in Omaha, Nebraska. The McCaulleys acted as their own general contractor, and in that capacity, they hired a number of different contractors to perform specific work. As relevant to the issues on appeal, the McCaulleys hired Able Plumbing, Inc., to install sewer lines servicing the property; Affordable Exteriors, Inc., to install exterior masonry and brickwork; Stile Construction Services, LLC (Stile), to install the roof; Timberland Hardwood Floors to install hardwood floors; Dan Becker Construction to install the doors and windows; Senegal Specialty Contracting, LLC, to perform waterproofing and to install drain tile and sump pumps; and Hardscape Contractors, LLC, to construct a retaining wall.
The McCaulleys moved into the home sometime in late February or early March 2008. Approximately 4 years later, on February 7, 2012, they filed this construction defect action in the district court for Douglas County, naming as defendants 12 of the contractors involved in the construction of the home, including the 7 contractors referenced above.
The McCaulleys alleged a separate negligence claim against each of the seven contractors. Specifically, they alleged that each such contractor owed a legal duty to install its “respective
While the case was pending, Michelle died. Her claims have been revived by Richard in his capacity as personal representative of her estate. For ease of reference, this opinion will continue to refer to the plaintiffs/appellants as “the McCaulleys.”
At different times during the litigation, each of the seven contractors referenced above filed a motion for summary judgment, arguing the claim against it was barred by the 4-year limitations period under
In March 2014, the district court granted summary judgment in favor of Timberland Hardwood Floors, Senegal Specialty Contracting, and Hardscape Contractors, generally agreeing that the limitations period for the McCaulleys’ claims against these contractors began to run on the dаtes that each contractor substantially completed its work. After determining the
Similar summary judgmеnt motions were filed by Affordable Exteriors and Stile, and those motions were pending when this court decided Adams v. Manchester Park.1 At the summary judgment hearing in November 2015, the McCaulleys made an oral motion for leave to file a fourth amended complaint, relying on language in the concurring opinion in Adams to argue they should be allowed to amend their complaint to allege the breach of an express warranty to repair. Both Affordable Exteriors and Stile objected to the requested amendment, arguing that the McCaulleys had alreаdy filed three complaints and that none had alleged the existence, or breach, of an express warranty to repair material defects. The court took the oral motion to amend under advisement.
In an order entered February 11, 2016, the district court granted summary judgment in favor of Affordable Exteriors and Stile, again reasoning that the 4-year limitations period under
After all remaining claims were resolved, the district court entered final judgment, and the McCaulleys timely appealed. We moved the case to our docket on our own motion.
ASSIGNMENTS OF ERROR
The McCaulleys assign, restated, that the district court erred in (1) finding their claims against the seven contractors were time barred by
STANDARD OF REVIEW
[1] An appellate court will affirm a lower court’s grant of summary judgment if the pleadings and admitted evidence show that there is no genuine issue as to any material facts or as to the ultimate inferences that may be drawn from those facts and that the moving party is entitled to judgment as a matter of law.2 An appellate court reviews the district court’s grant of summary judgment de novo, viewing the record in the light most favorable to the nonmoving party and drawing all reasonable inferences in that party’s favor.3
[2] A district court’s denial of a motion for leave to amend a complaint is reviewed for an abuse of discretion.4 A judicial abuse of discretion exists if the reasons or rulings of a trial judge are clearly untenable, unfairly depriving a litigant of a substantial right and denying just results in matters submitted for disposition.5
ANALYSIS
STATUTE OF LIMITATIONS
The primary issue on appeal is whether the contractors were entitled to summary judgment on statute of limitations grounds. Given the nature of the McCаulleys’ claims against the contractors, all parties agree the applicable statute of limitations is found in
Any action to recover damages based on any alleged breach of warranty on improvements to real property or based on any alleged deficiency in the design, planning, supervision, or observation of construction, or construction of an improvement to real property shall be commenced within four years after any alleged act or omission constituting such breach of warranty or deficiency. If such cause of action is not discovered and could not be reasonably discovered within such four-year period, or within one year preceding the expiration of such four-year period, then the cause of action may be commenced within two years from the date of such discovery or from the date of discovery of facts which would reasonably lead to such discovery, whichever is earlier. In no event may any action be commenced tо recover damages for an alleged breach of warranty on improvements to real property or deficiency in the design, planning, supervision, or observation of construction, or construction of an improvement to real property more than ten years beyond the time of the act giving rise to the cause of action.6
[3] We have long held that the limitations period in
[4] As a general rule, when the basis of a claim against a builder or contractor “is improper workmanship resulting in defective construction, the
The MсCaulleys generally contend the project was the construction of their home; as such, they argue the limitations period did not start to run against any contractor until the entire home was substantially completed in late February or early March 2008. The contractors define the project more narrowly. They contend the McCaulleys contracted for separate construction projects with each of the contractors; as such, they argue the limitations period began to run against each contractor on the date that contractor substantially completed its work.
The question presented in this case is one we have not directly considered before: When a homeowner has not contracted with a builder or general contractor to construct the entire home, and instead has entered into separate agreements with individual contractors to construct portions of the home, when does the limitations period under
Before addressing that question, we note the MсCaulleys do not contend the district court made any error in determining the dates on which each contractor substantially completed its own work, nor do they make any arguments related to the discovery rule, or the statute of repose, under
The plain language of
More recently, in Fuelberth v. Heartland Heating & Air Conditioning,11 we addressed the application of
Fuelberth recited the general rule that “where the basis of a claim is improper workmanship resulting in defective construction, the statute of limitations period under
Whether the [owner] could institute and maintain suit as soon as one system was substantially complete or [was] required to wait until the substantial completion of the work as a whole depends on whether the agreement [between the owner and the contractor] was divisible or indivisible. If a contract is divisible, breaches of its severable parts give rise to separate causes of action, [and] the statute of limitations will generally begin to run at the time of each breach. . . . If, however, a contract is indivisible, an action can be maintained on it only when a breach occurs or the contract is in some way terminated,
[5] Our opinions illustrate that when applying the general rule that the limitations period under
Here, the evidence was undisputed that the McCaulleys acted as their own general contractor when constructing their home, and they entered into separate agreements with each of the seven contractors to perform a specific project. There was no homebuilder or general contractor responsible for erecting the entire home. And we have been directed to no evidence in the record suggesting that the completion of any contractor’s project was necessarily tied to or contingent upon the completion of another contractor’s work. Nor is there any genuine dispute over the dates on which any contractor substantially completed its agreed-upon work.
On this record, we conclude the district court correctly found that under
AMENDMENT OF COMPLAINT
In their second assignment of error, the McCaulleys argue the district court abused its discretion in denying their oral
[6] Generally, when a party seeks leave to amend a pleading, our rules require that “‘leave shall be freely given when justice so requires.’”18 In applying this rule, we have explained that the denial of leave to amend pleadings is appropriate only in those limited circumstances in which undue delay, bad faith on the part of the moving party, futility of the amendment, or unfair prejudice to the nonmoving party can be demonstrated.19
Here, the district court denied leave to amend after finding the proposed amendment would be futile and would cause unfair prejudice to the nonmoving parties. Because the proposed fourth amended complaint considered by the court in its ruling is not in our record, we express no opinion on the futility of the proposed amendment. Instead, we focus on whether the record supports denying leave to amend on grounds of undue delay or unfair prejudice,20 and we conclude it does.
The McCaulleys filed their original complaint in February 2012. They amended their complaint in April 2012 and again in June 2015. All threе complaints alleged the seven contractors failed to complete their project in a good and workmanlike manner and were therefore negligent. The third amended complaint added breach of implied warranty claims against
By October 2015, the district court had granted the motions for summary judgment filed by five of the seven contractors, and only the motions filed by Affordable Exteriors and Stile remained pending. Those defendants appeared at the November 2, 2015, evidentiary hearing on their motions and offered evidence showing why the claims in the operative third amended complaint were time barred. At that hearing, the McCaulleys, for the first time, asked for leave to amend their complaint to add a new claim that the contractors breached an express warranty to repair. While the McCaulleys arguе on appeal that they were seeking amendment only with respect to the claims against Affordable Exteriors and Stiles, and not with respect to the five contractors already dismissed, their oral motion was unclear on that issue.
[7] Generally, it is not an abuse of discretion to deny leave to amend when a party seeks leave to amend to add a new claim or defense after a motion for summary judgment has been heard and submitted, unless evidence or testimony exists in the record indicating the proposed claim or defense was newly discovered or that counsel was previously unaware of the claim.21 Absent such evidence, a request to amend an operative pleading while summary judgment is pending is often just a belated effort to inject issues of material fact into a proceeding where previously the pleadings revealed none.22
The record does, however, support the conclusion that the McCaulleys’ request for leave to add a new claim was the result of undue delay and would unfairly prejudice the defendant contractors. By the time the McCaulleys sought leave to amend their complaint a fourth time, the litigation had been pending for several years, and five of the contractors had already been granted summary judgment on statute of limitations grounds. Affordable Exteriors and Stile had moved for summary judgment on the same basis and objected to the McCаulleys’ request to add a new warranty claim. Further, Affordable Exteriors and Stile were present in court and prepared to offer evidence showing they were entitled to summary judgment based on the allegations in the McCaulleys’ operative complaint. This record supports a finding of both undue
CONCLUSION
For the foregoing reasons, the district court did not err in finding the McCaulleys’ claims against the seven contractors involved in this appeal were time barred as a matter of law under
AFFIRMED.
MILLER-LERMAN, J., not participating.
