101 Wis. 468 | Wis. | 1899
This appeal comes up without a bill of exceptions and presents only the question of whether the trial court applied the law correctly to the facts found.
The decision below is challenged on various grounds, one of which is that defendants were not entitled to the offsets, allowed for defective plastering and defective heating apparatus. As appears from the statement of facts, the building contract provided that the final certificate of the supervising architect should be conclusive between the parties as to material and quality of work, and he approved the work and certified to its full completion according to the-contract more than five days before the commencement of the action. That was the sole requisite to final payment mentioned in the building contract. True, the finding also states that the building was accepted subject to deductions for imperfect work, but it clearly appears that the conditional acceptance mentioned was a mere conclusion of the trial court from the defects not having been discovered till after the final certificate was given, and not because of any stipulation or understanding between the parties as to a conditional acceptance. It is expressly found that the defects in the heating apparatus were unknown when the building-was accepted, and the same is fairly inferable from the finding as to the defective plastering; and in connection with the allegations of the answer stating that such was the fact,, the findings, on the whole, are very clear to the effect that the final certificate covered the completed building without reservation, and was conclusive on the subject of the quality of the' work and material, leaving nothing open for future adjustment between the parties. That the decision of the supervising architect under such circumstances, unless impeached for mistake or want of good faith on his part in accepting the work, is absolutely binding in law upon the parties, does not admit of question. The rule in that regard is inflexible and without exception. Tetz v. Butterfield, 54
It is further contended by the learned counsel for appellant, that the allowance to defendant trustees on account of salvage on the old building of $1,826.85, and interest, xnak-ing in all $2,218.09, was without warrant in the facts found. A careful study of the case fails to show any foundation for that decision. It discloses only that after the destruction of the first building the wreck remaining was of value in subsequent operations, and that plaintiff went on with his •contract, as he was legally bound to do, and completed it without change, except as to some modification of the'plans, for which it was agreed the price should be reduced $900. There was no counterclaim or offset for salvage pleaded, nor was any agreement claimed in the pleadings or found by •the court to the effect that salvage should be allowed to the trustees. That demand should not have entered into the final result in the court’s legal conclusions.
The next and most important assignment of error is that the court erred in not awarding plaintiff damages for breach
Ve have studied the case in vain to discover what principle of law moved the trial court to dispose of the subject ■of plaintiff’s claim for damages as was done. There was pleaded a good cause of action for damages for breach of contract. That cause of action appears to have been established by evidence, as the facts are all found calling for recovery on the legal claim substantially as pleaded, the damages to be measured by the loss which resulted to plaintiff directly and naturally by the breach of the insurance clause of the contract. The insurance taken out .by the •defendant trustees cuts no figure in the case whatever, as appears to us, except as mere evidence of the amount of insurance which might and ought to have been taken out in the names of both parties, loss payable, if any, according to their respective interests. There was a plain breach of that portion of the building contract, and no circumstance appears constituting the defendant trustees trustee for plaintiff of the insurance judgments. It was agreed before the insurance policies were taken out that the trustees should procure so much insurance on the building to protect both parties to the contract, as reliable insurance companies would carry. That amount, as demonstrated by what afterwards occurred, was $15,000. So plaintiff’s damages were such part of $15,000 as his interest in the building bore to the whole amount invested therein when the policies of insurance were obtained.
The relative rights of the parties to participate in any loss
True, one of the policies was settled at a discount, and
The case then is reduced to this: Defendant trustees were entitled'to & complete building for the contract price of $83,377.40, less $900 agreed upon on account of a change in the plans after the fire, and $316 agreed upon for omissions. They were also liable to plaintiff for $12,613.30 damages for breach of the insurance clause of the building contract and interest thereon, as before indicated, and were entitled to credit for all payments made. The account should be stated, in order to divide the lien able from the nonlienable ■claims, thus:
One building. .$33,377 40
Paid before the fire.,...... $9,500 00
Paid after the fire, including deductions. 18,263 12
Paid out of insurance money. 775 47
- 28,538 59
Balance due without interest. $4,838 81
Interest to date of finding. 1,036 50
Total due on the contract at date of findings. $5,875 31
Damages... $12,613 30
Interest thereon from April 17,1894. 3,045 64
Total damage claim. $15,658 94
Total due on both causes of action. $21,534 25
That increases the amount awarded by the trial court to plaintiff on account of his claim for damages $9,966.74, and decreases the amount found due on the lienable claim $9,432.17,
We are conscious that the conclusion we have reached enables the trustees to profit somewhat out of the insurance policies, but the legal principles applicable to the facts are-not vaided thereby. No particular significance is attached to the tabulations of figures made by the learned counsel for appellant, showing that the decision of the trial court gave the defendants a substantial profit from the insurance, or that the decision here results the same way but in a less degree. If that comes from charging the trustees with one building at the contract price, and full damages for their breach of the contract to insure the structure during the' progress of the work for plaintiff’s benefit, and crediting
By the Court.— The judgment of the circuit court is reversed, and the cause remanded with directions to render judgment in accordance with this opinion, adding interest to the sums plaintiff was entitled to, down to the date of such judgment.