*486 OPINION
Appellant, MBP Corp., sued two governmental entities for breach of a lease agreement and inverse condemnation. The trial court dismissed the suit, ruling that the defendants were immune from suit. Appellant challenges the dismissal, raising two issues. First, MBP contends governmental immunity does not bar its constitutional-takings claim against the appellees, the Board of Trustees of the Galveston Wharves and the Galveston Port Facilities Corporation (collectively, the “Wharves”). Second, appellant contends the Wharves waived immunity through egregious conduct. We affirm the dismissal.
I.
BackgRound
In 1990, the Wharves agreed to lease the rooftop and aerial rights of the Mallory Building, more commonly known as the Galveston Cruise Ship Tei’minal (the “Terminal”), to MBP’s predecessor-in-interest, Woodlands Corp. In 1994, Woodlands transferred its leasehold rights to MBP.
Over the next ten years, MBP and the Wharves agreed to several amendments of the original lease agreement. In 1999, the parties executed an amendment that permitted the Wharves to construct several improvements on the Terminal rooftop, including an enclosed pedestrian walkway. Through another amendment signed in 2003, the Wharves expanded several rooftop improvements and modified the pedestrian walkway.
This case arises from the Wharves’ decision, allegedly in breach of the lease agreement, to further expand the pedestrian walkway in 2007. As a result of Hurricane Katrina, which caused damage to ports throughout the Gulf Coast, several significant cruise lines altered their routes to make use of the port of Galveston. To accommodate a corresponding increase in passenger traffic, the Wharves opted to build additional air conditioning units in the Terminal and expand the rooftop’s pedestrian walkway into a larger disembarkation ramp. They approached MBP with a proposal to amend the lease to expressly provide for the additional construction, but the parties could not reach agreement on the terms of the amendment. 1 Nevertheless, the Wharves built the desired improvements anyway, contending that Section 1.02 of the lease agreement, as amended in 1999, already gave them permission to “construct and maintain air conditioning equipment ... and an enclosed pedestrian walkway.”
MBP disagreed with the Wharves’ contract interpretation and sued them for breach of contract, requesting the following relief: (1) an injunction requiring the Wharves to remove the latest installations and restore the rooftop to its previous condition; (2) an injunction preventing the Wharves from further altering the rooftop; and (3) attorneys’ fees. 2 The Wharves asserted immunity and moved to dismiss the suit for lack of subject-matter jurisdiction. In response, MBP filed a supplemental petition alleging a constitutional-takings claim:
*487 Article 1[ ] § 17 of the Texas Constitution prohibits the taking or damaging of a person’s property by a governmental entity for public use without adequate compensation to the owner of the property. Plaintiff is the owner of a leasehold interest in the rooftop of the Mallory Building and the aerial space above it. Defendants have taken or damaged such property without initiating a condemnation proceeding and without adequate compensation to Plaintiff. Plaintiff is entitled to injunctive relief to prohibit such activity and to restore the rooftop to its state prior to the unauthorized actions of Defendants.
Notably, MBP did not seek “adequate compensation” for the alleged taking, but instead continued to pursue only injunctive relief and attorneys’ fees.
The trial court ruled that the Wharves were immune from suit, and dismissed MBP’s claims for lack of subject-matter jurisdiction. MBP has appealed the dismissal, raising two issues. First, MBP contends its pleadings raise a constitutional-takings claim against which the Wharves have no immunity. Second, MBP argues the Wharves’ behavior is sufficiently egregious to justify the application of the “waiver by conduct” exception theorized in
Federal Sign v. Texas Southern University,
II.
Analysis
Under the doctrine of governmental immunity,
3
political subdivisions of the State are protected from lawsuits for damages, absent a waiver of immunity or legislative consent to sue.
See Lake Charles Harbor & Terminal Dist. v. Bd. of Trs. of the Galveston Wharves,
A governmental entity’s immunity encompasses both immunity from liability and immunity from suit.
See Tooke v. City of Mexia,
A. Standard of Review
If a political subdivision of the State is entitled to immunity from the
*488
plaintiffs claims, the trial court lacks subject-matter jurisdiction to consider the suit.
See Clear Lake City Water Auth. v. Friendswood Dev. Co.,
The plaintiff bears the burden of alleging facts that affirmatively demonstrate the trial court’s subject-matter jurisdiction over a case.
See Tex. Ass’n of Bus. v. Tex. Air Control Bd.,
When, as here, the defendant’s plea challenges the existence of jurisdictional facts, 5 we consider the relevant evidence submitted by the parties to the extent necessary to resolve the jurisdictional questions raised. See Miranda, 133 S.W.3d at 227. In this scenario, we will assume as true all evidence that favors the nonmovant. See id. at 228. A trial court properly grants a plea to the jurisdiction when the relevant evidence is undisputed or fails to raise a fact question as to jurisdiction. See id. However, if the evidence reveals a fact question on the jurisdictional issue, we will remand the dispute to be resolved by the fact-finder. See id. at 227-28.
B. Alleged Takings Claim
In its first issue, MBP contends the Wharves’ governmental immunity does not extend to MBP’s constitutional-takings claim. The Wharves respond that their immunity remains intact because they lacked the requisite intent to take property using sovereign powers, and instead expanded the disembarkation ramp solely under a “color of right” pursuant to the lease agreement.
See Gen. Servs. Comm’n v. Little-Tex Insulation Co.,
The Texas Constitution provides a limited waiver of the government’s immunity when property is taken, damaged, or destroyed for public use without adequate compensation.
See
Tex. Const. art. I, § 17;
Steele v. City of Houston,
[T]he State does not have the requisite intent under constitutional-takings jurisprudence when it withholds property or money from an entity in a contract dispute. Rather the State is acting within a color of right under the contract and not under its eminent domain powers ....
Texas courts have long recognized that the State wears two hats: the State as a party to the contract and the State as sovereign. The State, in acting within a color of right to take or withhold property in a contractual situation, is acting akin to a private citizen and not under any sovereign powers. In this situation, the State does not have the intent to take under its eminent domain powers; the State only has an intent to act within the scope of the contract.
Id. (citations omitted); see Holland, 221 5.W.3d at 643 (“When the government acts pursuant to colorable contract rights, it lacks the necessary intent to take under its eminent-domain powers and thus retains its immunity from suit.”).
Here, the parties disagree about the application of these principles to the Wharves’ conduct. The Wharves contend their intent was merely to act pursuant to the lease agreement because their duty to perform arose
solely
from contract.
See Tex. Parks & Wildlife Dep’t v. Callaway,
In resolving this dispute, we note that the phrase “color of right under the contract” has not received a comprehensive definition in this immunity context. However, case law may provide guidance as to some of the boundaries of this doctrine. For example, the mere existence of a contract between the government and a private party does not necessarily confer immunity on the entity for all interactions between those parties: “The existence of a contract is not talismanic, but merely leaves the state’s immunity from suit intact; it does not build an impenetrable wall nullifying the possibility of other waivers of and exceptions to that immunity.”
Id.; see also Little-Tex,
On the opposite end of the spectrum, the government may lack the requisite intent to take under its sovereign powers even if no contract exists or the government’s interpretation of the contract is wrong.
See Holland,
This court, in an alleged “color of right” case decided last year, examined whether the government acted akin to a private party or, conversely, whether its actions necessitated the use of sovereign powers:
The easement language gave Harris County the right to take actions that “do not unreasonably impair [SWBT’s] use of the easement.” Under the auspices of this language, Harris County required SWBT to relocate a manhole vault, conduits, cables, and telecommunications facilities within the easement, relocate some facilities entirely outside the easement, and lower remaining lines that are located in the new right-of-way several feet, thereby causing SWBT to incur at least $200,000 in damages. Although Harris County asserts that their actions do not constitute a taking, a private landowner would not be able to force SWBT to relocate its equipment, give up a portion of its easement to public right-of-way, and incur up to $200,000 in damages based on the “unreasonably impair” language in the easement. Only a government entity with condemning powers could force a private utility company to relocate equipment and relinquish part of its easement to public right-of-way, and under Texas case law, these actions constitute a taking.
Sw. Bell Tel., L.P. v. Harris County,
Applying these principles here, we hold that MBP has failed to establish the Wharves’ requisite intent to take property using its sovereign powers. We note that this case presents an unusual factual backdrop, at least in the context of immunity cases, because the governmental entity already
owns
the property it is alleged to have taken. There is no question that, in the absence of the lease agreement with MBP, the Wharves could have built a disembarkation ramp on their own property without needing sovereign powers.
7
Cf. Sw. Bell Tel.,
In fact, MBP’s ability to limit the Wharves’ property improvements, and the Wharves’ duties to consider MBP’s objections to any construction, are strictly limited to whatever rights may be conferred by the parties’ voluntary contract.
See Callaway,
Our determination that this is a contract dispute, and not a valid takings claim, is also supported by the relief MBP seeks: (1) an injunction requiring the dismantling of the recent improvements, (2) an injunction preventing further alterations to the rooftop, and (3) attorneys’ fees under the lease agreement. These remedies may be available in a breach-of-contract suit but cannot be recovered in a constitutional-takings claim.
See Scott v. Huntsville Indep. Sch. Dist.,
In addition, although we do not decide the merits of MBP’s breach-of-contract claims here, 8 the Wharves have presented a colorable argument that the lease agreement, as amended in 1999, actually permitted the 2007 enlargement of the pedestrian walkway. In 1999, the parties specifically amended Article I of the lease agreement to include broad language in Section 1.02 authorizing the Wharves “to use a portion of the roof of the Mallory Building upon which to locate, construct and maintain air conditioning equipment, elevator equipment, and an enclosed pedestrian walkway.” 9 MBP does not disagree with the Wharves’ contention that the disembarkation ramp is a “pedestrian walkway.” Thus, under the Wharves’ interpretation of the contract, its decision to enlarge the pedestrian walkway complied with Section 1.02.
MBP advances a different interpretation, arguing that, because the Wharves’ construction easement expired in 2000, the 1999 amendment cannot reasonably be read as authorizing further construction in 2007. 10 However, the Wharves respond that (1) Section 1.02, which confers their construction and maintenance rights, neither mentions the construction easement nor suggests that the Wharves’ rights are limited in time; (2) the construction easement does not expressly limit the duration of the rights granted in Section 1.02; and (3) the contract is silent as to the interaction between Section 1.02, which seems to grant perpetual access rights to the Wharves, and the construction easement, which may limit the Wharves’ access to the rooftop.
We need not decide which party’s interpretation is correct to assess the trial court’s subject-matter jurisdiction over the suit.
See Miranda,
Here, MBP has not shown the Wharves’ requisite intent to take property using sovereign powers. Therefore, the Wharves are not subject to liability under article I, section 17 of the Texas Constitution.
See Holland,
Accordingly, we overrule appellant’s first issue.
C. Egregious-Conduct Exception
In its second issue, MBP contends the Wharves have waived their entitlement to governmental immunity through egregious conduct including the Wharves’ (1) receiving benefits from the lease agreement, (2) affirming “they would honor the leasehold” by seeking MBP’s permission to construct improvements, and then (3) breaching the contract. Appellant’s argument presumes the existence of a waiver-by-conduct exception, a question that is far from settled.
Both this court and the First Court of Appeals have discussed, at length, the history of the waiver-by-conduct exception.
See Seureau v. ExxonMobil Corp.,
Over the next few years, several appellate courts interpreted the footnote in
Federal Sign
as creating a new judicially-created “waiver by conduct” exception to immunity.
Seureau,
Even assuming such an exception exists, the facts presented here do not warrant its extension to this ordinary contract dispute.
See Seureau,
To the contrary, the record implies that, from 1990 until 2007, MBP and its predecessor enjoyed an amicable, mutually beneficial relationship with the Wharves. During that time, the Wharves received the benefit of lease payments from MBP, and MBP enjoyed the privilege of using and occupying the leased premises. Unfortunately, after the parties were unable to agree to the terms of an amended lease,
*494
that relationship deteriorated and MBP sued the Wharves for breach of contract. Even if those contract claims have merit, Texas law is clear that a governmental entity does not necessarily waive immunity from suit merely by accepting benefits under, and then breaching, a contract.
See Tex. A & M Univ. Sys. v. Koseoglu,
Therefore, because this case does not present the sort of “extraordinary factual circumstances” present in State Street, we decline to find a waiver of the Wharves’ governmental immunity here. We overrule appellant’s second issue.
CONCLUSION
Finding no merit in the issues presented, we affirm the judgment of the trial court.
Notes
. To secure its approval of the proposed construction, MBP demanded, among other things, a forty-two year extension of the lease, free use of some of the port facilities, the reallocation of some port revenues from the Wharves to MBP, and annual rent payments to MBP that were to start at $60,000 and then increase by 4% every year. The Wharves apparently rejected these demands.
. Initially, MBP also brought a trespass claim and a request for exemplary damages. Both claims were later dropped.
. In this opinion, we will use the term "governmental immunity,” which extends to political subdivisions of the State including cities, as opposed to "sovereign immunity,” which refers to the State’s immunity from suit and liability.
See Seureau v. ExxonMobil Corp.,
. The City of Galveston has authorized the Board of Trustees of the Galveston Wharves to exercise management and control of the city’s wharf and terminal facilities.
See Lake Charles,
. Initially, the Wharves' plea focused solely on the sufficiency of MBP's pleadings. However, after MBP added a takings claim, the Wharves amended the plea to challenge the existence of jurisdictional facts under the evidence submitted to the trial court.
. Although this case involves an allegation that the Wharves exercised
eminent-domain
powers, a constitutional-takings claim may also encompass the government’s use of
police power. See City of Dallas v.
VSC,
LLC,
. In fact, in one of their filings in the trial court, the Wharves contended they could not have intended to use sovereign powers because "they have no legal authority to condemn property.” However, that argument is not well-developed in the record and has not been advanced on appeal; therefore, we do not consider it. See Tex.R.App. P. 38.1 (i).
.
See Miranda,
. Emphases added.
. MBP also contends a remand is necessary to resolve a fact issue as to whether the Wharves exceeded the scope of the rights conferred by Section 1.02, citing this court's opinion in
Ahmed v. Metropolitan Transit Authority,
