132 Ga. 849 | Ga. | 1909
The Potomac Engineering and Construction Company brought suit against the Mayor and Council of Washington, Georgia, alleging that the defendant was indebted to the petitioner for work and labor done and material furnished in constructing a waterworks system for the municipality, under the terms of a certain contract entered into by the plaintiff and the defendant. In the petition it is alleged that the plaintiff had fully completed the work required by the contract, and that the amount sued for was then due. The defendant admitted in his answer that it owed the plaintiff a part of the sum sued for, but insisted that the claim of the plaintiff should be reduced, because of its failure to complete the work which under the contract it was bound to perform by a certain date fixed in the contract; and that under the terms of the contract the plaintiff became bound “to pay to the City of Washington the sum of $20.00 for each additional day over and above the allotted time that is required to finish the work.” The quotation immediately preceding is from the contract itself; and it is also stipulated in the contract that “Strict 'compliance .with the above clause will be insisted on.” The defendant contended that the portion of the contract just referred to is one for liquidated damages, while the plaintiff insisted that the provision in the contract imposed a penalty and that it was non-enforeeable in the absence of proof showing damages to the city on account of the delay in completing the work.
Judgment reversed.