delivered the opinion of the Court.
The Bureau of Highways of the Mayor and City Council of Baltimore issued a notice of letting of a contract for the construction of the Jones Falls Expressway storm water conduits and, in response, DeLuca-Davis Construction Co., Inc., the appellee, submitted a bid that by reason of clerical error was at least $589,880.00 less than it 'intended it to be, and some $700,000.00 less than the engineer’s estimate and the *521 next lowest bid. The sealed bids of all bidders, including that of the appellee, were opened at noon on January 25, 1956, by the Board of Estimates and referred to the Board of Public Works for tabulation and recommendation. As soon as the bids were announced, the appellee realized that it had made a mistake. After several hours of checking, the precise form of the mistake was turned up and the Director of Public Works was notified immediately. Five days after the bids were opened, DeLuca-Davis wrote the Board of Estimates, explaining in detail how the mistake had occurred and that the actual bid should be $2,385,944.25 instead of $1,796,064.25, the bid submitted. The letter requested the Board either to correct the bid accordingly or to return the bid and the certified check for $50,000.00, which had accompanied it pursuant to the applicable charter provisions and the notice of letting. Being advised that the Board proposed to accept the original bid, the appellee filed a bill of complaint in the Circuit Court of Baltimore City, praying a mandatory injunction or decree commanding the Board of Estimates either to correct or reform its mistaken bid and to take no action thereon unless it had been corrected or, in the alternative, that the court permit the appellee to rescind the bid and have both the bid and the certified check returned. A demurrer to the bill by the City was sustained as to the right to rescind and over-ruled as to the right to reform and, after testimony was taken, the chancellor decreed that the contractor be authorized and empowered to reform and correct the bid unit from $6.00 to $16.00 in both Items 2 and 11 of the bid, the bid total of Item 2 from $349,800 to $932,800 and the bid total of Item 11 from $4,128 to $11,008, and the total amount of the bid from $1,796,064.25 to $2,385,944.25. The decree further provided that the Board of Estimates be “directed to receive the complainant’s bid or proposal as so reformed and corrected in lieu of the mistaken bid.” The City appeals from the decree, urging error in it and in the overruling of the demurrer.
The testimony shows that the estimator for DeLuca-Davis, a qualified engineer, prepared the figures for the bid. In calculating the cost of Item 2, the unclassified excavation other *522 than for the post office wall, the estimated number of cubic yards was divided into the estimated dollar cost to obtain a unit cost of $13.34 per cubic yard. The same unit cost was applied to Item 11- — unclassified excavation for post office wall. This unit cost was approved by the president and co-owner of DeLuca-Davis. On the afternoon before the bid was submitted, the estimator prepared a summary sheet showing all costs of the job, and the bid was written up from this summary sheet. In transferring the estimated unit cost for unclassified excavation of $13.34 per cubic yard from the detail work sheet to the summary sheet the estimator by mistake entered the figure of $3.34 for Item 2 and Item 11. There seems little doubt that the mistake came about because the first figure in $13.34 —the figure “1”- — was on a vertical ruled line in the work sheet apparently accentuated by the paper having been folded. The unit cost price of $3.34 was not used in preparing the bid as the bid unit price to multiply the quantity of cubic yards figured on, but instead a figure of $6.00 was used. The difference between $3.34 and $6.00 represented the proportion of overhead and profit allocated to the unclassified excavation item. In its letter to the Board of Estimates and in its bill of complaint, the appellee contends that the bid unit price for Items 2 and 11 should be $16.00 instead of $6.00, which increases the bid total for Item 2 from $349,800 as filed to $932,800 and the bid total of Item 11 from $4,128 as filed to $11,008, or an increase in the total bid of $589,880.00. The testimony of the president of DeLuca-Davis was that if it had been realized before the bid was sent in that the unit price for the unclassified excavation was $13.34 instead of $3.34, the bid unit price would not have been $16.00, as it was sought to be corrected to, but would have been some figure greater than that. He said that the figure of $2,385,944.25 was not the figure he would have estimated and bid if he had realized that $13.34 was the correct unit price. He added that when his counsel asked whether, if the City allowed correction, he wanted to add overhead and profit to the unclassified excavation unit price in an amount greater than was in the original bid, he had answered: “I told him no, I was not interested in that part of it, all I wanted him to do was to correct the mistake *523 of $10.00 that was made * * In response to a question from counsel for the next lowest bidder (who had been permitted to intervene in the case), he said: “* * * I had no way of knowing * * * whether my price would have been below yours or above yours * * *” if the bid had been prepared from the correct figures.
It was shown further that the net worth of DeLuca-Davis was $82,000.00, that if it were compelled to perform the contract at the original bid, it would suffer a loss of over $400,000.00 and that it could not obtain a bond if the job were to be done at the original estimate. There was testimony that there was a general perceptible reaction in the room when the appellee’s bid was opened and announced — a realization that something was wrong, that there was an error in the bid. It was shown that the mistake was a bona fide, clerical and mechanical error. The estimator demonstrated how the mistake had occurred and the two co-owners of DeLuca-Davis both testified that they neither knew of, nor suspected, the mistake until the bid was opened. They testified also that they had not known of the engineer’s estimate— which was $700,000 more than their bid — before preparing their own bid. The chancellor made the following findings of fact, which the appellants do not seriously challenge and which are supported by the record: 1, there was an error in the bid of the appellee which was entirely clerical and mechanical; 2, the error was material and substantial; 3, the error was palpable and the City, as soon as the bids were opened, either knew or should have known that there was a substantial error in the bid; 4, the error was made in absolute good faith.
The Baltimore City Charter, Flack (1949), Sec. 38, provides that the Board of Estimates shall award a contract required to be let by sealed competitive bids * * * “to the lowest responsible bidder * * * or shall reject all bids.” It provides further that “Bids when filed shall be irrevocable.” The successful bidder must execute a formal contract and a bond in the amount of the contract price. All bids must be accompanied by a certified check for an amount specified in each case and a bidder to whom the contract is awarded, who fails to execute the required contract and bond, forfeits the
*524
deposit check as liquidated damages. The notice of letting incorporated all the requirements of the Charter. The City contends that the Charter provisions are peremptory and leave no discretion to either party. It argues that the bidder knows exactly his liability and its extent if he receives the award and refuses to accept the contract. He has agreed that his bid once made is irrevocable and has further agreed that he has damaged the City to the extent of the amount of the certified 'check filed with the bid, and so, in legal contemplation, cannot ever be said to have made a mistake in the amount of the bid because he has guaranteed in advance that any error he makes shall be at his own expense and not at the cost of the City. The City goes on to urge that for these reasons there can be neither reformation of the bid nor cancellation of it and return of the deposit, and that its contentions were established by the decision of this Court in
M. & C. C. of Baltimore v. Robinson Con. Co.,
It is manifest to us that the City is correct in saying that there cannot be reformation, for at least two reasons. In the first place, to warrant the equitable remedy of reformation the mistake must have been mutual.
Phelps, Juridical Equity,
Sec. 227;
Dulany v. Rogers, 50
Md. 524, 533;
Stiles v. Willis,
DeLuca-Davis did not seek merely to make a mechanical correction, such as correctly multiplying the number of cubic yards by the real unit price but, in effect, made a new bid after the mistake was discovered. To determine the amount of this bid judgment had to be exercised. Its president, in the exercise of this unilateral judgment, decided that it would not do what it would have done if the true facts had been known when the original bid was made, but rather, that the revised bid would be figured by the use of the original unit price without any increase attributable to overhead and profit— merely to add back the $10 omitted from the unit cost of excavation and not add overhead and profit as he would normally have done. To permit to be done what the appellee seeks to do, would not only run entirely counter to the underlying principle of reformation, which is merely to correct a mistake in the expression of what had been mutually agreed upon, but would also completely nullify the purpose and the safeguards of the competitive bidding system established by the City Charter. We have found no authority that has permitted reformation in a situation such as the one before us. Sometimes it has been suggested, as the appellee suggests in this case, that
Moffett, Hodgkins & Clarke Co. v. Rochester,
Turning to the question of cancellation of the bid, it is plain to us that had the parties here been two individuals there is no doubt that a court of equity would have had the power, and on the facts of the case the duty, to decree rescission of the bid and the return of the deposit. Our concern has been whether the same standard applies where one of the parties is a public body controlled, as are the bidders who seek to do its building, by statutory provisions for the elimination, in the public interest, of unfairness or favoritism, or whether the relief in such cases has been foreclosed by M. & C. C. of Baltimore v. Robinson Con. Co., supra. We have concluded that the sound weight of authority is that recission may be decreed as against a municipal or other public body by a court of equity, and that the Robinson case is distinguishable and not controlling.
Although reformation requires that the mistake be mutual, rescission may be granted whether the mistake be that of one or of both of the parties.
Phelps, Juridical Equity,
Sec. 227. Williston, leader of the objective theory of contracts, is critical of the rule that rescission may be had for a unilateral mistake, as was noted by Judge Henderson for the Court in
Kappelman v. Bowie,
There are numerous cases in many states that have granted contractors cancellation of bids based on clerical, material, palpable, bona fide mistakes. Where, as in the case at bar, the mistake has been brought to the attention of the contracting authority before the acceptance of the bid, the courts have been almost unanimous in granting relief. Some of the decisions are collected in the annotations in 80
A. L. R.
586, and 107
A. L. R.
1451. See, too,
Corbin on Contracts,
Vol. 3. Sec. 609;
Lubell, Unilateral Palpable and Impalpable Mistake in Construction Contracts,
1931, 16 Minn. L. Rev. 137; and 100 U. of Pa. L. R. 753. In the comparatively early case of
Geremia v. Boyarsky
(Conn.),
There are well reasoned cases in which, despite statutes similar to Sec. 38 of the Baltimore City Charter, the Courts have held that rescission would be granted against the public body. A leading case is
Moffett, Hodgkins & Clarke Co. v. Rochester,
In
M. F. Kemper Const. Co. v. Los Angeles,
W. F. Martens & Co. v. Syracuse, 171 N. Y. S. 87, is a case in which essential facts were similar to those of the instant case. The Court said: “Plaintiff’s error was entirely inadvertent, and the trial court, we think, with entire propriety held that, so far as a rescission of its bid was concerned, the facts presented a case for granting the relief sought. Any other disposition would have been inequitable. * * * Respondents invoke the provisions of section 121 of the Second Class Cities Law as preventing a withdrawal of plaintiff’s bid until the awarding and execution of the contract. We do not think, in view of the mistake which plaintiff made, that it was precluded from withdrawing its erroneous bid. In reality, it never submitted its real bid, but an erroneous one, not at all expressing its intent.”
In
Donaldson v. Abraham
(Wash.),
Conduit & Foundation Corp. v. Atlantic City (N. J.), 64 A. 2d 382, dealt with a low bid from which an item of $50,250.00 had been inadvertently omitted. The City was notified before it accepted the bid, but awarded the bid to the mistaken bidder. He could not secure a bond because of his error and the City forfeited the deposit. The Court decreed rescission of the bid and return of the deposit be *532 cause the City’s acceptance of the bid, in the face of a material, excusable error, was unconscionable. It held: 1, that a competitive bid submitted under statutory privilege and regulation is in the nature of an option to the municipality, based upon a valuable consideration; 2, an offer for which a consideration has been given is both an offer and a unilateral contract — in effect, an irrevocable offer or option; 3, for a unilateral mistake in a unilateral contract, the remedy in a court of equity is rescission.
In
Connecticut v. F. H. McGraw & Co., Inc.
(Conn.),
As has been emphasized, the City relies on
M. & C. C. of Baltimore v. Robinson Con. Co.,
There are a number of differences between the
Robinson
case and the present case. The Robinson Company was a responsible bidder and the lowest bidder. The City, in entire good faith, could have made an award knowing that the bidder had the capacity to perform. Thus, when the City did accept the bid, the Robinson Company was faced with its contractual obligation — delineated by the Charter provisions —either to perform or to forfeit $500.00. When it sought at law to recover the forfeit, it was faced with the fact that ownership of the $500.00 had at law passed to and remained in the City. Law could only act in the situation as it found it. It could not change the contract. It could not reform or rescind it as could equity, so there was no basis in law on which to ground recovery. The opinion of this Court in
Boyce v. Wilson,
In the case before us, DeLuca-Davis sought the aid of equity before its bid had been accepted, and demonstrated to the chancellor that it had made a material, honest and palpable mistake. It produced evidence that clearly would permit, if it did not compel, a finding that it was not a responsible bidder as to the original bid, since it could not obtain a bond for the performance of the contract at the bid price, and performance would cause a loss of over $400,000.00 to a corporation with a capital of only $82,000.00. If, with this knowledge, the City accepted the bid of DeLuca-Davis, it scarcely could be with the bona fide expectation that performance would follow but only with the intention of bringing about a refusal to perform and the consequent forfeiture of the $50,000.00 — conduct which equity must view as unconscionable.
The .Court in the Robinson opinion gave definite indication that if equitable relief had been sought, the rules of decision might well have been different. It said: “If the contract were made by the bid and acceptance the bidder then would be compelled to carry it out or be responsible for it, unless a Court of Equity, for sufficient cause, should relieve him, by rescinding the contract.” (Emphasis supplied.) 2 In distinguishing the Moffett case, it said that there the matter came up on “* * * a bill in equity for a reformation of the proposal. and therefore is not authority for the form of action in this case. In fact, all of the cases, cited by the appellee, are cases in equity and in the most of them there was no statute involved." (Emphasis supplied). Corbin’s comment on the Robinson case is: “the deposit small and ‘equitable’ relief not asked.”
For cases by the same Court, where relief against a mistaken bid was granted in equity and denied at law, see
St.
*535
Nicholas Church v. Kropp
(Minn.),
If it be conceded that in the posture of the case as it came to the Court, the Robinson decision was sound in holding that a bidder could not withdraw his bid at will and was bound by his obligation as long as it was legally unrevoked, we agree with the views of the Court in the McGraw case, from which we have quoted above, that the proper effects of the charter requirements are to assure the municipality that a bidder will be relieved of his obligation only when it is legally justifiable, and that it is legally justifiable when a court of equity is satisfied by clear, cogent and convincing proof that an honest, clerical or mechanical error, not the result of gross or culpable negligence, made the bid that of the bidder in form only but not in actual intent or substance, and the gain of the other party would be unconscionable if advantage were taken of the mistake and the loss would only be that of the bargain if the mistake were nullified. In such circumstances, the blundering bidder may be relieved in equity of his obligation created at law by his bid and deposit, and this is true even though the bid was submitted to a public body under a statute declaring the bid to be irrevocable and providing for the forfeiture of the deposit.
The City argues that the Board of Estimates has taken no action on any of the bids and it cannot be told how it will act so that a decision in the case is premature. The City formally denied in its answer the allegations in the complaint of De-Luca-Davis that the Board of Estimates proposed to accept the erroneous bid, but no proof to that effect was offered and neither in its brief nor at the argument did the City give any indication of intent other than to hold DeEuca-Davis “* * * as in a grasp of steel”, under the authority of the Robinson case, and to forfeit the deposit when the bidder failed to execute the contract.
If the Board had in mind that at the appropriate time, it would declare DeLuca-Davis not a responsible bidder, it could have disposed of this branch of the controversy by merely announcing that intent, and its failure to do so serves as a basis for the assumption that its intent is otherwise. The
*536
Charter gives the Board the power and duty of determining the lowest responsible bidder. In that determination it has a wide discretion and the courts will not control it or interfere except for arbitrary or capricious exercise or where there is collusion or fraud.
Fuller Co. v. Elderkin,
*537 We find that DeLuca-Davis is entitled to cancellation of its bid and the return of its deposit.
Decree reversed, with costs; case remanded for passage of a decree in conformity with this opinion.
Notes
.
State of Oregon v. State Construction Co.
(Ore.),
. It should be noted that in
American Lighting Co. v. McCuen,
