142 Mo. App. 656 | Mo. Ct. App. | 1909

REYNOLDS, P. J.

(after stating the facts). — I. It is conceded in the argument and briefs of counsel that the lien accounts which were filed by plaintiff, state the date of the first commencement of the work and furnishing of material by this plaintiff as October 27th on one account, November 7th on another, and November 28th on the third, all in the year 1906. The lien notices themselves are not set out in the abstract, as they should be, but there is no sug-gestion in the record that any date prior to the dates here mentiond is set out in the lien notices as filed, or that any right was set up to carry the lien back of those dates to the date of commencement of the building. We must, therefore, assume that these dates mentioned in the lien notices filed as the dates when the materials were first furnished and work first done by this plaintiff and his assignor for the construction of the building, are the earliest dates given for the inception of the lien claim. *664It appears by the agreed statement of facts that these are all subsequent to the date of execution of the mortgage or deed of trust, which, according to the stipulation, was executed’ and delivered to defendant Fisher, as trustee for defendant Robinson, on May 22, 1906, and duly recorded the 29th day of the same month. That being so, this case falls within the decision of our Supreme Court in Coe v. Ritter, 86 Mo. 277, as interpreted by that court in the case of Landau v. Cottrill, 159 Mo. 308. In this latter case, the court, commenting on the case of Coe v. Ritter, says: “It is true, that in that case the lien was sought to be extended beyond the face of the record by showing, by parol evidence, that the materials were furnished at an earlier date than the earliest date given in the lien, while in this case a like extension of the lien is sought, by showing by parol evidence, that the buildings were commenced at an earlier date than the earliest date given in the lien. But the same object is sought to be accomplished, and by the same means; and it would seem, that the legal principles announced in that case are just as applicable to the case in hand.” It is not meant by the use of the word “parol,” that the objection goes to the testimony because it was by parol; the ground of the objection is, that the lien account or notice did not, in itself, furnish or set up any fact which would let in evidence to carry the lien back of the date given in the lien account, the only date given being that on which the first item of work was done or material furnished.

In Bruns v. Braun, 35 Mo. App. 337, Coe v. Ritter, supra, is referred to, and Judge Biggs, who delivered the opinion of this court, after referring to the ruling as announced in Coe v. Ritter, that the dates as specified in the lien account cannot be changed by matters in pais, says (1. c. 345) : “The reason of this rule is that when a party seeks to fasten a lien „or incumbrance on real property, the precise nature of the lien or in*665cumbrance should be stated and made a matter of record, so that the owner or other parties interested might be definitely advised of the true facts touching the title to the property.”

Counsel for appellants in this case invoked this rule, asserting that there is no mention made in the lien notice filed of the date of the commencement of the construction of the building, and hence no fact stated in the lien notice on which the lien can be carried back of the - date given in that notice as the date on which the first material was furnished, and as that date is subsequent to the date of the deed of trust, the lien of the plaintiff; on the land is subordinate in right to the lien of the holders of' the notes secured by that deed of trust. We might dispose of the case on this point, as decisive, for we hold it Avell taken, but as that is not the main question counsel on either side have so ably argued and elaborately briefed, we have concluded not to dispose of the case on this point but on the main question.

II. Our Mechanic’s Lien Law (sec. 4203, E. S. 1889), after enacting that every mechanic and material-man, etc., doing work and labor or furnishing materials, etc., for the erection of buildings and improvements on lands, etc., shall have a lien upon the buildings, etc., and the land belonging to the OAvner, upon which they are situated, to secure the payment for such work and labor done or materials furnished, by section 4215, provides that this lien for the work, labor and materials “shall attach to the buildings, erections or improvements for which they were furnished, or the Avork AAras done, in preference to any prior lien or incumbrance or mortgage upon the land upon which said buildings, erections, improvements or machinery have been erected or put; and any person enforcing such lien, may have such building, erection or machinery sold under execution, and the purchaser may remove *666the same within a reasonable time thereafter.” Section 4209 provides that the lien for work and materials “shall be preferred to all other incumbrances which may be attached to or upon said buildings ... or other improvements, or the ground, or either of them, subsequent to the commencement of such buildings or improvements.” It is over the construction, interpretation and application of the phrase, “subsequent to the commencement of such buildings or improvements,” that this contest is really made. While there have been many decisions by our appellate courts on this phrase, counsel have referred us to no decision of those courts which specifically meets the facts in this case, nor has our OAvn search through them furnished us Avith one that can be said to definitely and authoritatively determine it.

We have been referred to Douglas v. Zinc Co., 56 Mo. 388; Reilly v. Hudson, 62 Mo. 383; Hall v. Mullanphy Planing Mill Co., 16 Mo. App. 454; Hydraulic Brick Co. v. Bormans, 19 Mo. App. 664; Hall v. St. L. Mfg. Co. 22 Mo. App. 33; McAdow v. Sturtevant, 41 Mo. App. 220; Reed v. Lambertson, 53 Mo. App. 76; Hammond v. Darlington, 109 Mo. App. 333, all Missouri cases. It is true that in Hydraulic Brick Co. v. Bormans, this court holds that the statute is to be given a literal construction, but the rule as announced by our Supreme Court in Walden v. Robertson, 120 Mo. 38, l. c. 43, and Lumber Co. v. Clark, 172 Mo. 588, l. c. 598, now is that these are remedial statutes and to be liberally construed. But in the Hydraulic Brick Company case no question arose as to work done under a new contract, that under the old having entirely ceased, and a careful examination of all these cases has failed to furnish us with any one in Avhich the proposition here involved has been squarely presented for decision. True there are expressions and declarations in all of them, as in the Hydraulic Brick Company case, which standing alone might be said to settle this question; but *667in none of them are present such a state of facts as here presented, nor such a statement of a principle, as if1 applied to these facts, may be said to govern. The main question here presented is this: When the erection of a building has been commenced under contracts and on plans looking to its completion, but, before completion, work is stopped on it and the contract abandoned, do those contractors and materialmen who thereafter undertake its completion, under new contracts made with them, have a right to a lien for work and labor done and materials furnished by them under these new contracts, on the land or improvements, prior and superior to the lien of a mortgage or deed of trust, placed on the land and duly of record, after cessation of all construction work under the first contract, but prior to the doing of work and labor or furnishing material under the new or second contracts? In brief, do the claims of these' subsequent contractors, assuming that the lien notice contains the averments hereinbefore referred to, relate back to the first contract and first work, to which contract and work they were not parties or privies, and so cut off the intervening mortgage from its lien on the land? It is a matter of common knowledge that buildings are commenced on plans which the owner is unable to carry out. Work stops until more funds can be provided. The owner is not ready or able to go on. A familiár illustration of this is at hand in this city. Two well-known church edifices, each planned with great towers, wrere commenced forty or fifty years ago and carried to completion except as to the towers. If those towers are now built, shall the materialmen and laborers carry their right to liens back over the forty or fifty intervening years and cut out any and all deeds of trust, which, in those intervening years, may have been put upon the land? Such a construction does not seem reasonable.

Probably the courts of no State have adhered more strictly to what is known as “the first spade rule” than *668has that of Pennsylvania. Thus, in In re Denkel’s Estate, 1 Pearson (Pa.) 213, a case quoted approvingly by our court in Hydraulic Brick Co. v. Bormans, 19 Mo. App., l. c. 670, it is held that “all the mechanics’ liens commence at the date of the first stroke of the axe or spade used in making the house.” But in Fordman’s Appeal, 78 Pa. St. 120, the Supreme Court of that State held that persons engaged in the building finished after cessation of work under a prior contract, “could not carry back the lien for work and materials beyond the time of the recommencement of the building.” It is true that this was under a Pennsylvania statute which enacted that the lien “shall not be construed to extend to any greater or other estate in the grounds on which any building may be erected, than that of the persons in possession at the time of commencing said building and at whose instance the same is erected.” We have practically and substantially the same provision in our lien law, which provides (sec. 4202), that the land “shall be subject to all liens created by this article, to the extent and only to the extent of all the right, title and interest owned therein by the owner or proprietor of such building, erection or other improvement, for whose immediate use or benefit the labor was done or things were furnished.”

American Fire Ins. Co. v. Pringle, 2 Serg. & R. (Pa.) 139, is a case with most of its features common to the case at bar.- The Supreme Court there held that the lien dated from resumption of the work before then discontinued, and was subject to the lien of a mortgage given after the commencement of the building, but between the date of cessation of all work on it and subsequent resumption. To like effect is Stevenson v. Stonehill, 5 Wharton (Pa.) 301, and Hageman v. Fanj, 19 Co. Ct. Reps. (Pa.) 660. We see no essential difference between our lien law and that of Pennsylvania on this matter, and while of course the decisions of the court of that State are not controlling on us, they are by *669judges of high authority and the reasoning in them commends itself to us as sound.

On consideration of the question, our conclusion is, that section 4209 refers to the commencement of the construction under which the work was done, that is, the construction under the new and distinct contract, and not to the commencement of construction under the old and abandoned contract, a contract between which and the new contract there is neither privity of contract, of interest, nor of parties. There is no hardship or injustice in such a position; certainly none in this case. The plantiff knew that the buildings and improvements were not to be completed by the old contractor or under the old contract. He knew, either actually or by constructive notice from its record, of the existence of the deed of trust and that it was in force when he contracted to go on with his contract, so that he entered upon the work with his eyes open, and there is no suggestion of fraudulent concealment.

The foregoing is substantially the opinion filed in this case when it was first argued before us, and we concluded that opinion as follows: “We therefore hold in this case at bar, that the deed of trust is a lien on the lots, prior in right to the lien of plaintiff as contractor furnishing’ material and doing labor; that plaintiff is entitled to a general judgment against defendant Mode and to a lien on her equity of redemption in the lots, as also to a lien, prior in right to the other defendants, who are owners of the notes and deed of trust, on the improvements, with the further right, given by section 4205, to satisfaction out of those improvements by sale and removal thereof, if the debt is not otherwise made.” Accordingly we ordered that the judgment of the circuit court be reversed and the cause remanded with directions to that court to proceed in accordance with this opinion, Judge Goode concurring in it in full, Nortoni, J., dissenting from the first ground of reversal assigned but concurring in the bal*670anee of the opinion and in the conclusion arrived at. Thereafter counsel for appellants filed a motion for rehearing, on the ground, among others, that so much of the foregoing order as holds the improvements subject to the claim of the plaintiff, as subcontractor, for a mechanic’s lien superior in right to that of the appellants, as holders of the deed of trust is erroneous, counsel claiming that the rights of plaintiff are subject to those of the defendants, both in the land and in the improvements. Other grounds for rehearing are assigned, but as this is the material one and the consideration of Avhich disposes of the matter, Ave avüI not notice any of the others. It avíII be observed that in our former opinion Ave did not discuss this particular phase of the case, satisfying ourselves Avith the statement that section 4205, R. S. 1899, covered the matter and that a decree should be entered in accordance Avith that section. Our attention having been particularly called to this branch of the case by this motion for rehearing, Ave have gone into the examination of it with much more thoroughness than we gave it before, and have arrived at the conclusion that our former judgment was incorrect in holding that the lien of the deed of trust on the improvements was subordinate to the lien of the plaintiff for labor and materials and that plaintiff had a right to satisfaction of his lien out of the improvements, to be made by sale or removal thereof, if the debt was not otherAvise made. As will be seen by the foregoing part of our opinion, we have decided that the addition to or completion of the building was done under a distinct contract made and entered into after the work done under the original contract had ceased and after that contract had been abandoned. As shown by the evidence in the case, before the new contract was made or the neAV work done, the deed of trust under which defendants claim was placed upon the property. At that time the property consisted both of the lot and of the building, so far as the building had then been *671erected, and the presumption of law is that the mortgagee loaned his money and took the deed of trust on the faith of the lot and improvements as they then were. The cases hereafter to he referred to establish this proposition, and they establish it in construing what is section 4205, R. S. 1899, which says that the lien shall attach to a building, erection or improvement for which the material was furnished or the work done; in preference to a prior lien, incumbrance or mortgage upon the land upon which they were put. These words, “upon the land upon which they were put,” must be assumed to have been used intentionally; that is, they refer to naked land. It is this section and these words upon which the sole claim for priority of a mechanic’s lien on the land must rest. But this section does not in terms make provision for the case of a mortgage which covers both the land and improvements then on it. Its fair construction has been held to be that it is not intended to cover the case of improvements made upon land theretofore unimproved, nor to improvements on the land when the prior lien was given. It has been held in adjudicated cases on this identical section, and on like sections in the laws of other States having lien laws which, so far as this point is concerned, are identical with our own, that this language refers to the construction of an independent or detached building, improvement or erection on the land, placed thereon subsequent to a deed of trust or mortgage; and that it does not refer to an improvement, alteration, repair or reconstruction of a building before made and standing Avhen the mortgage was given nor to an addition to it. This has been held and the reason for it very clearly set forth by a decision of this court in the case of Haeussler v. Thomas, 4 Mo. App. 463, the decision being rendered by Judge Haydüjn, one of the ablest laAvyers Avho ever sat upon the bench of this court, in which that judge cites many cases in support of the conclusion arrived at by the court, to the effect *672that the word “improvement,” as used in this section of the statutes, means, not an addition to a building already constructed, but to an independent structure on the land. The opinion cites and quotes a case in which it was held that where, as against a mortgagee holding a mortgage on a lot and a building thereon, a lien was claimed for lumber furnished under contract with the owner, partly for putting a third story on the house already built, partly for erecting a stable, that the part of the claim for material used in erecting the new structure had preference to the lien of the mortgage, while that part of the claim which was for subsequent repairs upon the house covered by the mortgage, must give place to the latter. The case from which Judge Hayden adopts this as the law is that of Getchell & Tichenor v. Allen, 34 Iowa 559, l. c. 562-563. An examination of that case and of the sections of the Iowa statutes there referred to, shows in the first place that Judge Hayden's reference to it is accurate, and in the next place that the Iowa statutes are almost identical with our own on this branch of the case. The same proposition was before the United States Circuit Court for this circuit, in the case of Taylor et al., Trustees, etc., v. Burlington, etc., Ry. Co., reported 4 Dillon’s Circuit Court Reports 570, s. c., 4 Central Law Journal 536, a decision by Judge Dillon, concurred in by District Judge Love, in which the case of Getchell & Tichenor v. Allen, supra, is referred to and followed.

In the case of Schulenburg v. Hayden, 146 Mo. 583, Judge Marshall, who delivered the opinion of the court, holds, at page 594, that the true construction to be placed upon what is now section 4205, R. S. 1899, is “that if there is a mortgage on the land, and a contractor, under contract with the owner of the equity of redemption, builds a new house upon the land, he has a mechanic’s lien against the house, and the house may be sold, and may be removed from the land by the purchaser, for this preserves to the mortgagee all the *673security he formerly had, aud secures, as far as possible, the payment to the contractor for the work and materials he employed in building the house.” But, says Judge Marshall, this is all that section means or guarantees, and, he says, this is made perfectly clear in the light of what is now section 4204, which confines the mechanic’s lien to the right, title and interest of the owner. Referring to what is now section 4209 of our statutes, Judge Marshall further observes that this section, of course, gives the mechanic’s lien a priority over subsequent mortgages, but that where the mortgage coviers the land and the house' and the house is partly destroyed by fire and a contractor reconstructs it under a contract with the owner of the equity of redemption, what is now section 4205, does not authorize the mechanic’s lien to tafee priority over the mortgage or to have a sale of the reconstructed house and its removal. “It may be,” says Judge Marshall, “that the reconstruction of the house would increase the security of the mortgagee, but he is not bound to rebuild the house — -he may be content with his security of the land and the ruins of the house' — which may be worth, as in this case, two-fifths of his mortgage. He has no power to prevent the owner of the equity of redemption from contracting with any person to reconstruct the house upon the faith of the credit of such owner, because he is not even entitled to foreclose his mortgage until condition broken, and is not entitled to exercise acts of dominion over the property (except to prevent waste) until he acquires title at the foreclosure sale. On the other hand, the contractor can- protect himself by not taking the risk, without the express consent of the mortgagee.”

The line of argument and decisions in these cases leads to the result -tliab section 4205 covers the case of unimproved lots or land; lots and land without erections and buildings upon them when the mortgage lien *674was created, and does not cover lots and lands with improvements then on them. In brief, does not disturb or interfere with the lien of a mortgage or deed of trust, when that mortgage covers the tract as well as improve ments then on it — using the word “then” with reference to what improvements were on the land at the date of the deed of trust or mortgage.

On the authority of these cases, as we understand them, and on our own interpretation of our statutes, Ave are compelled to hold that the decision of the learned trial judge was erroneous in holding that the lien of the materialman was superior in right to that of the holders of the secured notes, inasmuch as we have held that the making of these improvements, for Avhich the mechanic’s or materialman’s lien has been filed, Avas practically and in fact the entering upon a neAv construction under a neAv contract. The judgment of the circuit court is reversed and the cause remanded Avith directions to the circuit court to enter up a judgment for the amount of the debt found against the defendant Kate Mode and awarding plaintiff special execution therefor with the provision that if no sufficient property of the said defendant Kate Mode be found to satisfy the judgment and costs, that the same or the residue thereof be levied on the equity of redemption or interest of the said Kate Mode in the property described,- subject to the prior lien secured by the deed of trust, and that judgment be entered in favor of the defendants Fisher and Robinson.

All concur.
© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.