361 Mass. 540 | Mass. | 1972
This is a bill in equity in which the plaintiffs seek to recover payment for gravel and fill furnished to Michael Vitale Construction Co., Inc. (Vitale), a subcontractor for E. C. Blanchard Co. Inc. (Blanchard). This case and three companion cases were referred to a master who found that Blanchard and its surety Maryland Casualty Company (Maryland) were liable to the plaintiffs in the amount of $20,685.86. The master’s report was confirmed by an interlocutory decree of a judge of the Superior Court who entered a final decree ordering the defendants to pay the stated amount plus interest. The defendants appeal from the final decree. The evidence is not reported. In these circumstances, it is our duty to test the judge’s actions on the standard that the master’s findings of fact must stand unless they appear as mutually inconsistent, contradictory, or plainly wrong. Gil-Bern Constr. Corp. v. Medford, 357 Mass. 620, 622-623.
We state the facts as they appear in the master’s report and in the plaintiffs’ account which is incorporated by reference in the report. Pentucket Regional School District (Pentucket) contracted with Blanchard for the construction of a school building. Blanchard, as principal, and Maryland, as surety, furnished Pentucket with a performance bond as required by G. L. c. 149, § 29, as amended. About October 31, 1966, Blanchard contracted with Vitale to do the preliminary site work for the school. Vitale in turn engaged the plaintiffs to supply gravel borrow and fill for the site. The parties
On September 11, 1967, the plaintiffs mailed a registered letter to Pentucket containing a sworn statement of account as required by G. L. c. 149, § 29. The postal receipt was signed by an employee of Pentucket and returned to the plaintiffs. About September 13, 1967, Pentucket’s superintendent of schools acknowledged receipt of the statement and called it to the attention of the school committee at its next meeting. Because the school committee had no time stamp, no record was made of the receipt of the notice, nor was it entered in the minutes of the committee meeting. Finally, because the letter and statement were mislaid or misfiled, neither Blanchard nor Maryland was notified about them until June 28,1968.
1. The master’s certificate states that he prepared his draft report “in accordance with Rule 88 of the Superior Court Rules.” Since this rule applies to auditors’ reports rather than masters’ reports, the defendants argue that they have been prejudiced procedurally. We do not agree. While it is true that the master’s report in this case refers to Rule 88 of the Superior Court
2. The defendants also argue that the master’s finding as to the date on which the last delivery was made is wrong in view of his other findings and that this error resulted in his awarding the plaintiffs a greater amount than was actually due them. We disagree. “[I]t is the duty of this court on appeal from the final decree to see that the final decree is such as the law requires upon the facts found by the master.” Foot v. Bauman, 333 Mass. 214, 219. In the present case, the master found “that the . . . [plaintiffs] did furnish gravel fill, labor and materials as set forth in the [b]ill annexed to the . . . [plaintiffs’] [b]ill of [c]omplaint.” The bill referred to indicates that the last delivery was made on July 27, 1967. The master, however, stated in his report that the last delivery was made on July 7, 1967. While there is, therefore, an error on the face of the report, we believe that the error was inadvertent and has not been shown to have harmed the defendants. “Logically it would seem that the errors of the master did not affect the final decree.” Foot v. Bauman, supra, at 219. The final decree ordering them to pay $20,685.86 plus interest was clearly based on the statement of account and the figures contained therein and was in no way dependent on the inconsistent finding as to the date of final delivery. Also, the defendants’ statement that the master erroneously found that the “Mavrofrides transported material during the period on or about October
3. The defendants finally argue that the plaintiffs failed to comply with G. L. c. 149, § 29, in that, in the present case, the statute requires that (a) notice of claim for transportation charges be given within twenty days to the contractor principal, and (b) a sworn statement of claim to the contracting officer of Pentucket within ninety days.
There is no doubt that a substantial portion of the plaintiffs’ claim was for transportation charges from the gravel pit to the construction site. Similarly, there is no doubt that the Legislature by amending § 29 intended that notice of claims for transportation charges should be presented to the principal contractor within twenty days. St. 1962, c. 696. The issue presented here, however, is whether charges for material that in some instances include transportation costs, require, at least for their transportation charge component, a separate twenty day notice to the principal contractor. We conclude that they do not.
There is nothing in the language of § 29 to indicate that the Legislature intended a twenty day notice to the principal contractor for anything but separate transportation claims such as charges from a trucking firm or a railroad. Bills from these latter type carriers might not readily come to the principal contractor’s attention, especially if the trucker or railroad were engaged by a subcontractor and had no contact with the principal contractor. In this case, however, the report indicates that, although the plaintiffs were hired by Vitale, Blanchard was aware of the arrangement between the plaintiffs and Vitale, and, had, in fact, assured the plaintiffs of payment. We also observe that, in connection with the ninety day notice to the public authority, § 29 provides that such notice shall be filed “after the claimant
The defendants also argue that there was no evidence that the contracting officer or agent of Pentucket received the required sworn statement of claim within ninety days. The master found that an employee of Pentucket signed a registered mail receipt for a letter containing the plaintiffs’ statement of claim. The letter was mailed by the plaintiffs on September 11, 1967.
About September 13, 1967, Pentucket’s superintendent of schools acknowledged receipt of the letter. From these facts, the master was warranted in concluding that the requirements of the statute had been met. See Gil-Bern Constr. Corp. v. Medford, 357 Mass. 620, 622-623.
Decree affirmed with costs of appeal.