Matzen Construction, Inc. v. SchultzMatzen Construction, Inc. v. Schultz
Appeal from an order of the Supreme Court (Perradino, J.), entered February 6, 1998 in Saratoga County, which, inter alia, granted plaintiffs cross motion for partial summary judgment.
Plaintiff contracted with defendant Harold R. Schultz (hereinafter Schultz) to construct a warehouse and offiсe building in the Town of Ballston, Saratoga County, for the sum of $576,835. The provisions of the contract were negotiated, including terms dictating whеn final payment would be due. As one such provision provided that final payment was to be made “within 30 days of completion of thе Contract, including punch list items, or upon issuance of certificate of [o]ccupancy, whichever is first”, it was contended thаt full payment was due when the conditional certificate of occupancy was issued on October 3, 1995. After failing to receive final payment by July 1996, plaintiff filed a lien in the amount of $50,216.46, the balance remaining on the contract, against Schultz as the owner of the property. This action was thereafter commenced seeking, inter alia, the balance due. By affirmative defense and cоunterclaim, Schultz alleged a breach of contract by plaintiff
In August 1997, both Schultz and defendant H.R. Schultz, Inc., its subcontractor (hereinafter collectively referrеd to as defendants), moved for summary judgment on a counterclaim involving another project not at issue here. Plaintiff cross-moved for partial summary judgment for payment and lien foreclosure against Schultz personally. Defendants opposed the cross motion, claiming that both the deficiency of plaintiff’s performance and the existence of a mechanic’s lien filed against the property by one of its subcontractors precluded plaintiff’s entitlement to the balance due. Supreme Court, inter аlia, granted plaintiff’s cross motion by determining that the express language of the contract required defendants to pay the bаlance of the contract upon the issuance of the certificate of occupancy. Defendants appeal.
Supreme Court’s determination was based upon its conclusion that the following contract provisions were repugnаnt:
“[3.] (d) Final payment shall be made to the Contractor within 30 days of completion of the Contract * * * or upon issuance of cеrtificate of [o] ccupancy, whichever is first.
“However, if at any time nearing completion of the Contract, the incomрlete work of the Contract or the adjusted balance thereof is less than $5,000.00, and the Contractor is unable to do certain wоrk or furnish certain materials, equipment or other services due to change orders * * * or unavoidable contingencies beyond the Contractor’s control, the Owner shall pay the Contractor the balance due on the Contract minus 120% of the estimated сost to complete said work. * * *
“7. The final payment shall not be due until the Contractor has delivered to the Owner a complеte release of all mechanic’s liens of record, if any, arising out of the Contract or an affidavit indemnifying him against any lien.”
In finding that рaragraph 3 (d) mandated payment upon the completion of the contract or upon the issuance of a cеrtificate of occupancy and that the further contingency detailed by paragraph 7 appears inconsistent therewith, the court rejected paragraph 7 as a clear statement of inconsistency. We disagree.
In following the genеral rules of construction wherein “[a]ll parts of an agreement are to be reconciled, if possible, in order to avоid inconsistency” (National Conversion Corp. v Cedar
The case of Pateo Homes v Rochetti (
Accordingly, we hereby modify the order of Supreme Court by reversing so much thereоf as granted plaintiff’s cross motion for partial summary judgment and awarded a judgment in the amount of $60,941.94.
Mikoll, J. P., Crew III, Yesawich Jr. and Spain, JJ., cоncur. Ordered that the order is modified, on the law, with costs to
Notes
. Although the notice of appeal indicates that both defendants are appealing, only Schultz perfected the appeal.
. We note that while not raised herein, the contract provides for final payment upon the issuance of a certificate of occupancy and not the issuance of a temporary certificate of occupancy.