Matter of FMC Corp. v. New York State Dept. of Envtl. ConservationMatter of FMC Corp. v. New York State Dept. of Envtl. Conservation
Argued March 21, 2018; decided May 1, 2018
Matter of FMC Corp. v New York State Dept. of Envtl. Conservation, 143 AD3d 1128, reversed.
OPINION OF THE COURT
Wilson, J.
The Appellate Division held that neither title 9 nor title 13 of article 27 of the Environmental Conservation Law authorized respondent Department of Environmental Conservation (DEC) to unilaterally remediate the significant threat posed by hazardous wastes petitioner FMC Corporation (FMC) had released onto neighboring properties. We conclude that the Appellate Division erred in foreclosing the possibility that title 9 authorized DEC‘s unilateral action and that the interpretation of title 13 adopted by both parties authorized DEC‘s unilateral remediation effort. We therefore reverse the Appellate Division‘s order and dismiss FMC‘s
I. Background
FMC owns and operates a 103-acre pesticide production facility in Niagara County. Over nearly a century of operation, that facility has released significant quantities of hazardous wastes including arsenic, lead, cyanide, acetone, DDT, and carbofuran. Many of those wastes have migrated onto adjacent properties including a school, recreational watercourses, croplands, and several hundred residences. FMC continues to store hazardous wastes and to formulate pesticides on the site.
The title 9 permitting process requires applicants to undertake corrective actions for all releases оf hazardous waste (
In its petition, FMC asserted four causes of action. The first two, which the Appellate Division rejected, made essentially procedural objections to DEC‘s Statement of Basis, claiming it should have been promulgated pursuant to the federal Resource Conservation and Recovery Act instead of the New York Environmental Conservation Law аnd that DEC had denied FMC recourse to the dispute resolution mechanisms contained
FMC‘s arguments are limited to its third cause of action, which alleges that DEC‘s decision to implemеnt CMA 9 unilaterally, rather than through FMC, was arbitrary and capricious. The Appellate Division, after reversing Supreme Court‘s order dismissing the petition as untimely, held that DEC‘s decision to implement CMA 9 itself was arbitrary and capricious, and granted FMC‘s petition on that basis (Matter of FMC Corp. v New York State Dept. of Envtl. Conservation, 143 AD3d 1128, 1135 [3d Dept 2016]). It later granted DEC‘s motion for permission to appeal to this Court (Matter of FMC Corp. v New York State Dept. of Envtl. Cоnservation, 2017 NY Slip Op 63646[U] [3d Dept 2017]).
II. Discussion
The parties agree that DEC had several options through which it could have sought an order requiring FMC to undertake CMA 9 (see e.g.
A. Title 9
Title 9 regulates hazardous wastes “now being generated and sites now being used for disposal of such wastes” (L 1979, ch 282, § 1). It requires any person generating, transporting, treating, storing, or disposing of hazardous wastes to obtain a
The permitting scheme is augmented by DEC‘s аuthority to seek substantial civil and criminal penalties against violators and by its having the funds and flexibility required to clean up violations. Section 27-0914 prohibits “possess[ing] . . . dispos[ing] of . . . [or] deal[ing] in hazardous wastes without authorization.” Title 71 contains the penalties for doing so, which can include fines and damages payable to the state superfund (
Here, DEC maintains that it was authorized to undertake CMA 9 because FMC had unlawfully disposed of hazardous waste, including through a number of releases between 1980 and the present. The Appellate Division disagreed. Instead, it held, FMC was “operating lawfully pursuant to its ‘interim status’ ” “at all relevant times” (FMC Corp., 143 AD3d at 1134).
The conclusion that an entity with a permit or permission to operate under interim status cannot, as a matter of law,
Although FMC‘s interim status did not provide it a safe harbor, a reversal of the Appellate Division on that point would
Were title 9 DEC‘s only avenue of recourse, those disputes would have to be resolved. However, it is usually not our function to evaluate the sufficiency of such evidence in the first instance. Here, DEC also relied upon title 13, to which we now turn.
B. Title 13
Unlike title 9, which regulates working industrial facilities, title 13 concerns inactive hazardous waste disposal sites. Remedial programs—title 13‘s equivalent to title 9‘s corrective actions—at those sites are governed by section 27-1313. That section authorizes DEC to order the owners, operators, or other parties responsible for an inactive hazardous waste disposal
Although the section evidences the legislature‘s preference for using a post-hearing order to “place the burden of remedying these sites on those responsible for the presence of waste material,” it also authorizes DEC to develop and implement remedial programs “in the event the responsible party [is] unknown, unable or unwilling to ameliorate the situation” (Matter of New York State Superfund Coalition, Inc. v New York State Dept. of Envtl. Conservation, 18 NY3d 289, 292-293 [2011]). In its petition and throughout the course of this litigation, FMC reads the section to describe four independent circumstanсes in which unilateral agency action would be appropriate: (a) “[w]henever a person ordered to eliminate a threat to the environment . . . has failed to do so within the time limits specified in the order“; (b) “[i]n the event that the commissioner . . . is either unable to determine who may be responsible, or is unable to locate a person who may be responsible“; (c) “[w]henever the commissioner has made findings [оf imminent danger] pursuant to [subdivision (3) (b)]“; and (d) “if, in the discretion of the department, it is cost-effective for the department to develop and implement such a remedial program” (
DEC‘s cost-effectiveness determination can be broken into two analytically separate pieces: the choice of CMA 9 and the choice to proceed unilaterally. FMC no longer contests that DEC‘s Final Statement of Basis demonstrated CMA 9 was a cost-effective alternative to CMAs 1 through 8.
Thus, the sole outstanding question is whether DEC determined that unilaterally implementing CMA 9 was a cost-effective alternative to ordering FMC to proceed. FMC is correct that the Final Statement of Basis, which was issued before DEC chose to proceed unilaterally, does not address that question. However, DEC‘s decisiоn to proceed unilaterally demonstrates it determined that path was cost-effective. Subdivision (5) (d) exempts DEC from having to reduce the grounds for that determination to writing and, other than a conclusory allegation that private action is always cheaper than public action, FMC has proffered nothing under the four statutory factors or otherwise to contradict the presumption that DEC‘s action was reasоnable under the circumstances.4 DEC‘s year-long unsuccessful negotiations to obtain FMC‘s agreement to perform the work provides record evidence that relying on FMC
Having established that title 13 provides an avenue for DEC tо use the state superfund to unilaterally remediate the relevant properties, it remains only for DEC to establish that it met the additional conditions imposed by the state superfund statute. When proceeding under title 13—although not when proceeding under title 9—that statute requires DEC, absent exigent circumstances, to have first made “all reasonable efforts to secure voluntary agreement to pay the costs of necessary remedial actions from owners” (
Accordingly, the order, insofar as appealed from, should be reversed, with costs, the petition dismissed, and the certified question answered in the affirmative.
Chief Judge DiFiore and Judges Rivera, Stein, Fahey and Feinman concur; Judge Garcia taking no part.
Order, insofar as appealed from, reversed, with costs, petition dismissed and certified question answered in the affirmative.