146 N.E. 342 | NY | 1924
On March 25, 1898, an order was entered in the office of the clerk of the county of New York confirming the "first partial and separate report" of commissioners of estimate and assessment previously appointed in the above-entitled proceeding. This report contained all the awards made for all the lands, tenements and hereditaments acquired in the above-entitled proceeding. It did not contain any assessment for benefit, but the order provided "that the said commissioners present their report as to assessments for benefit in their final separate report." The American Express Company owned a parcel of land at the corner of Broome and Elm streets. The city acquired part of this land in this proceeding. This part was denominated on the maps as Damage Parcel No. 71, and an award was made of $36,226 for this parcel. On or about February 6, 1899, *224 a voucher of the finance department was prepared in the sum of $40,122.28, which sum represents the amount of the award, together with interest from May 1, 1897, the date of vesting of title herein under a special statute covering these proceedings, to February 9, 1898. On the same day a warrant was drawn for this amount and the American Express Company was notified by the comptroller that the warrant in payment of the award would be ready for delivery on February 9, 1899. The American Express Company did not call for the warrant and it was not delivered to it. It has not been canceled, but is apparently still outstanding. On February 18, 1903, an order was entered confirming the "last partial and separate report" of the commissioners which contained all the assessments for benefit, including an assessment in the sum of $6,537.56 against "Benefit Parcel No. 5946" which represented that portion of the property of the American Express Company which was not acquired by the city in this proceeding. This assessment was paid by the American Express Company to the city, but it made no demand for the payment of the award to it by the city until May 31, 1921. The city then refused to pay the award on the ground that under the provisions of sections 376 and 378 of the Code of Civil Procedure (now section 44 of the Civil Practice Act) the award is conclusively presumed to be paid.
Civil Practice Act (§ 44) reads as follows:
"§ 44. When satisfaction of judgment presumed. A final judgment or decree for a sum of money or directing the payment of a sum of money, rendered in a court of record within the United States or elsewhere, or (a judgment of a court of this state not of record) docketed (in a county clerk's office upon a transcript filed therein pursuant to law), is presumed to be paid and satisfied after the expiration of twenty years from the time when the party recovering it was first entitled to a mandate to enforce it. This presumption is conclusive, except as *225 against a person, who within twenty years from that time makes a payment or acknowledges an indebtedness of some part of the amount recovered by the judgment or decree, or his heir or personal representative, or a person whom he otherwise represents. Such an acknowledgment must be in writing and signed by the person to be charged thereby. A person may avail himself of the presumption created by this section under an allegation that the action was not commenced, or that the proceeding was not taken, within the time therein limited."
A remedial right arising from the non-performance of a duty is extinguished when the Statute of Limitations deprives the right of its judicial remedy. When the statute says that the presumption of payment arising from lapse of time is conclusive it means that, when the limitation applies, the fact of non-payment is immaterial and may not be shown to rebut the conclusive presumption. (Fisher v. Mayor, etc., of N.Y.,
1. Was the first partial and separate report as to awards when confirmed by the court a final judgment of the Supreme Court, or was the final judgment in the *226
proceeding the order confirming the assessments for benefit? Consolidation Act, § 990, in terms provides, as in force when the lands were taken, that the report when confirmed shall be final and conclusive. Matter of Nunez (
2. When did the party recovering the judgment first become entitled to a mandate to enforce it? Although the award became a judgment it was to be enforced, not as judgments in common-law actions are enforced, by execution, but under the provisions of law relating thereto. Former section 1001 of the Greater New York charter, in force on the date of the entry of the order of confirmation, provides as follows:
"§ 1001. All damages awarded by the commissioners of estimate and assessments with interest thereon from the date of said report, and all costs and expenses which may be taxed, shall be paid by The City of New York to the respective persons and bodies politic or corporate mentioned or referred to in said report, or in whose favor such costs or expenses shall be taxed. Interest shall cease to run on sums awarded as damages six months after the date of the confirmation of said report unless within that time demand therefor be made upon the comptroller. Said damages, costs and expenses shall be paid from the *227 fund for street and park openings provided for in this act, and by existing laws. The person or persons to whom awards shall be made in such proceedings, and the person or persons in whose favor costs and expenses may be taxed, shall not have an action at law against The City of New York for such awards, costs, or expenses, but the court in which said proceedings have been had, upon the application of any such person or persons, in case of the failure of the comptroller of said city to pay the same within thirty days after demand therefor, shall require and direct the comptroller to pay said awards, costs, and expenses from the said fund, and enforce said order or mandate in the same manner as other orders and mandates of said court are enforced. * * *."
But the provision that the comptroller may have thirty days after demand before the court shall issue its mandate does not prevent the running of the statute. At most it extends it for thirty days. The right to payment is a constitutional right, not a legislative creation. The award is due immediately. The duty of payment is absolute. (N.Y. Const. art. 1, § 6; U.S. v.Rogers,
3. What was the nature of the obligation of the city to pay the award?
The relation of the claimant and the city is that of vendor and vendee, debtor and creditor. The city owes the amount of the award to claimant. (Kahlen v. State of N.Y.,
The singular anomaly is here presented of the refusal of the city to pay a just debt because it is in a position to defeat claimant's remedy. Ethical considerations may condemn its attitude. The beneficent purpose of the statute as expressed in the act of James I, "for quieting of men's estates and avoiding of suits" is not served. Yet the city authorities would have been remiss in their *229 duty if they had recognized the natural obligation in this proceeding. They lacked authority to waive the provisions of the statute. Relief must be sought elsewhere. The Statute of Limitations does not pay the debt. It merely deprives claimant of its remedy. That it does effectually exclude claimant from the courts by denying remedial justice is too plain to permit us to allow good conscience to prevail or to permit particular instances to destroy the force of well-established rules of law.
The order should be reversed, with costs in all courts, and the claimant's motion denied, with ten dollars costs.
HISCOCK, Ch. J., CARDOZO, CRANE and ANDREWS, JJ., concur; McLAUGHLIN, J., not voting; LEHMAN, J., not sitting.
Orders reversed, etc.