Matter of Bothar Constr., LLC v. DominguezMatter of Bothar Constr., LLC v. Dominguez
Calendar Date: December 16, 2021
Before: Garry, P.J., Lynch, Aarons and Reynolds Fitzgerald, JJ.
Couch White, LLP, Albany (Joel M. Howard III of counsel), for appellants.
Letitia James, Attorney General, Albany (Allyson B. Levine of counsel), for Commissioner of Transportation and others, respondents.
Adams LeClair, LLP, Rochester (Richard T. Bell Jr. of counsel), for Crane Hogan Structural Systems, Inc., respondent.
Reynolds Fitzgerald, J.
Appeal from a judgment of the Supreme Court (McGrath, J.), entered October 27, 2020 in Albany County, which, in a combined proceeding pursuant to
In May 2019, respondent Department of Transportation
In August 2020, petitioners commenced this combined proceeding pursuant to
Respondents contend that this appeal should be dismissed as moot because the project is substantially complete. “Typically, the doctrine of mootness is invoked where a change in circumstances prevents a court from rendering a decision that would effectively determine an actual controversy” (Matter of Dreikausen v Zoning Bd. of Appeals of City of Long Beach, 98 NY2d 165, 172 [2002] [citation omitted]). Where a change in circumstances involves the substantial completion of construction,
Crane Hogan received approval of the contract and notice to proceed on December 20, 2019. It began construction in February 2020 by cutting down trees and removing vegetation. In March 2020, it began excavating the shoulder and roadway and replaced curbs and sidewalks. Construction has proceeded for two years and approximately $17.7 million out of the $19 million in funds allocated to the project have been disbursed. This project involves a six-lane major thoroughfare in the City of Syracuse, Onondaga County, and has been disruptive to traffic and adjacent businesses. Although petitioners sought injunctive relief in August 2020, this was eight months after the contract was awarded and six months after construction began. Petitioner did not seek any injunctive relief from this Court.
Petitioners did not make sufficient efforts to preserve the status quo and safeguard their rights. Petitioners only sought to stay construction once, six months after construction commenced (see Matter of Citineighbors Coalition of Historic Carnegie Hill v New York City Landmarks Preserv. Commn., 2 NY3d 727, 729 [2004]; Matter of Sierra Club v New York State Dept. of Envtl. Conservation, 169 AD3d 1485, 1487 [2019]; Matter of Kowalczyk v Town of Amsterdam Zoning Bd. of Appeals, 95 AD3d at 1477). Although petitioners assert that they did not delay seeking injunctive relief, as the typical construction season in New York runs from April to November and the statute of limitations was tolled at the time, the construction season is extremely dependent upon the weather and fluctuates according to the weather conditions. It is not unusual for construction to begin in February and continue through December. The ongoing construction was highly visible to the public and to petitioners. Furthermore, staying the statute of limitations did not stay construction (compare Town of N. Elba v Grimditch, 131 AD3d at 157, Matter of Schupak v Zoning Bd. of Appeals of Town of Marbletown, 31 AD3d 1018, 1020 [2006], appeal dismissed 8 NY3d 842 [2007], and Matter of Defreestville Area Neighborhood Assn., Inc. v Planning Bd. of Town of N. Greenbush, 16 AD3d 715, 717 [2005], with Matter of Sierra Club v New York State Dept. of Envtl. Conservation, 169 AD3d at 1487).
Moreover, we see no evidence that the work was performed in bad faith, as Crane Hogan waited almost two months to begin construction after the contract was approved. Additionally, the work that has been completed could not easily be undone without undue hardship, as the removal of curbs and sidewalks would once again disrupt traffic patterns and commercial driveways and negatively impact adjacent business owners’ livelihoods (see Matter of Citineighbors Coalition of Historic Carnegie Hill v New York City Landmarks Preserv. Commn., 2 NY3d at 729; Matter of Dreikausen v Zoning Bd. of Appeals of City of Long Beach, 98 NY2d at 173-174; Matter of Weeks Woodlands Assn., Inc. v Dormitory Auth. of the State of N.Y., 95 AD3d 747, 747 [2012], affd 20 NY3d 919 [2012]). Further, we are unpersuaded that the exception to the mootness doctrine applies as there are no novel issues or public interest considerations such as environmental concerns warranting continuing review. Likewise, a controversy with similar issues is not likely to evade court review to justify our departure from the standard rules of mootness (see Saratoga County Chamber of Commerce v Pataki, 100 NY2d 801, 811 [2003], cert denied 540 US 1017 [2003]). Under these circumstances, we find that the appeal is moot and must be dismissed (see Matter of E.W. Tompkins Co., Inc. v Board of Trustees of Clifton Park-Halfmoon Pub. Lib., 27 AD3d 1046, 1047-1048 [2006], lv denied 7 NY3d 704 [2006]; Matter of Paden v Planning Bd. of Town of Mamakating, 270 AD2d 626, 626 [2000]).
Garry, P.J., Lynch and Aarons, JJ., concur.
ORDERED that the appeal is dismissed, as moot, without costs.
REYNOLDS FITZGERALD, J.