Matter of A. Colarusso & Son, Inc. v City of Hudson Planning Bd.
No. 536178
Appellate Division of the Supreme Court of New York, Third Department
June 22, 2023
2023 NY Slip Op 03397
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.
In the Matter of A. Colarusso & Son, Inc., et al., Respondents, v City of Hudson Planning Board, Appellant.
Calendar Date: May 2, 2023
Before: Aarons, J.P., Pritzker, Reynolds Fitzgerald and McShan, JJ.
Hinman Straub PC, Albany (David B. Morgen of counsel), for appellant.
Whiteman Osterman & Hanna LLP, Albany (John J. Henry of counsel), for respondents.
Aarons, J.P.
Appeal from an order of the Supreme Court (Henry F. Zwack, J.), entered August 9, 2022 in Columbia County, which, in a combined proceeding pursuant to
Petitioner A. Colarusso & Son, Inc. (hereinafter petitioner) is the sole member of petitioner Colarusso Ventures, LLC. Petitioner operates a mine and a plant in the Town of Greenport, Columbia County. As part of the mining operations, petitioner transports materials on a private haul road to a dock that it owns in the City of Hudson, Columbia County (hereinafter the City). Although a majority of the haul road is situated in the Town of Greenport, part of it is also situated in the City.
In 2016, petitioner sought to renovate the haul road and submitted site plan applications in connection therewith — one to the Town of Greenport Planning Board (hereinafter the Town Board) and another one to respondent. A dispute subsequently ensued between the Town Board and respondent as to who would serve as the lead agency pursuant to the State Environmental Quality Review Act (see
Separate from, but around the same time of, the foregoing, petitioner was also repairing the dock. During this repair, the City issued petitioner an order to remedy because the remedial work violated a provision of the Code of the City of Hudson. As a consequence, petitioner, in May 2017, applied for a conditional use permit to continue with the dock repair. This application included a short environmental assessment form. In August 2017, which was after the Town Board had issued its negative declaration relative to the haul road application, respondent determined that SEQRA review was necessary relative to the conditional use permit application. In December 2019, petitioner submitted a full environmental assessment form. In July 2020, respondent classified the conditional use permit application as a type 1 action and declared its intent to serve as the lead agency. In November 2021, respondent issued a positive declaration and directed petitioner to prepare a supplemental draft environmental impact
Petitioners thereafter commenced this combined
“[O]n a motion to dismiss pursuant to
As to the actual relief awarded on petitioners’ fourth cause of action, the dispute centers on whether Supreme Court directed respondent to grant petitioner‘s pending haul road application or to render a decision on the application. A review of the petition/complaint discloses that the latter was requested by petitioners. Indeed, this request is consistent with petitioners’ arguments on appeal. Furthermore, petitioners maintain that Supreme Court did not direct respondent
Respondent meanwhile believes that Supreme Court did, in fact, direct it to reach a certain result — i.e., granting the haul road application. To that end, the language employed by Supreme Court arguably suggests that respondent must grant petitioner‘s application. The court ordered that “site plan approval is directed to proceed” and noted in the decision that respondent “is directed to proceed with site plan approval.” The court further noted that petitioner was entitled to mandamus on “[respondent‘s] failure to grant site plan approval for that portion of the haul road which enters the City” (emphasis added). “Site plan approval,” as used by the court, could refer merely to the process of granting, conditionally granting or denying a site plan application. However, in view of the pertinent code provision requiring respondent to consider various factors “[i]n considering whether to approve a site plan” (
As such, to eliminate any doubt, and because petitioners are entitled to a decision by respondent on the haul road application, whatever that decision may be, Supreme Court‘s directive must be clarified. That said, the language of “site plan approval is directed to proceed” in the decretal paragraph of the court‘s order must be deleted and be substituted with “a decision on the haul road application is directed to issue forthwith.” Finally, to the extent that respondent challenges that part of Supreme Court‘s order directing that the haul road application is not subject to further SEQRA review by the City, such challenge is without merit (see Matter of Gordon v Rush, 100 NY2d 236, 243 (2003)). Respondent‘s remaining contentions have been considered and are either unavailing or improperly raised for the first time in reply.
Pritzker, Reynolds Fitzgerald and McShan, JJ., concur.
ORDERED that the order is modified, on the law, without costs, by deleting so much thereof as ordered that “site plan approval is directed to proceed” and substituting therefor “a decision on the haul road application is directed to issue forthwith“; and, as so modified, affirmed.
