514 A.2d 677 | Pa. Commw. Ct. | 1986
Opinion by
Mathies Coal Company appeals an Environmental Hearing Board (EHB) order upholding limitations by the Department of Environmental Resources (DER) on the amount of iron, manganese and aluminum in the discharge from Mathies’ treatment plant. These limitations were imposed in an amended National Pollutant Discharge Elimination System (NPDES) permit which allowed an increased discharge from the plant. We affirm in part, reverse in part and remand.
Our scope of review of an EHB decision is limited to a determination of whether an error of law has been committed, constitutional rights have been violated or any findings of fact are unsupported by substantial evidence. Einsig v. Pennsylvania Mines Corp., 69 Pa. Commonwealth Ct. 351, 452 A.2d 558 (1982).
In support of its ruling, EHB stated that (1) DER was required to apply the specific water quality standards in 25 Pa. Code §93.7, (2) DER calculated the effluent limitations from a formula (mass balance equation)
Moreover, because such discretion exists, DER must consider, where applicable, the economic and aquatic impacts of its actions pursuant to Section 5(a) of The Clean Streams Law.
DER contends that Mathies has waived its right to challenge the use of the mass balance equation to calculate the effluent limitations because it did not specifically do so below. However, by contesting DERs failure to consider the economic and aquatic effects of limiting the discharge, Mathies certainly contested DERs use of the formula to effect the limitations.
The weight to be given each factor considered when issuing a permit must be determined by DER based on the circumstances.
The Environmental Hearing Board order, No. 82-212-G dated June 10, 1985, is affirmed in part, reversed in part and this case is remanded for proceedings consistent with the foregoing opinion.
Jurisdiction relinquished.
DER asserts that it uses the following mass balance equation to determine the concentration of a pollutant which may be discharged without contravening the water quality standards in 25 Pa. Code §93.7:
[Q7-10 x concentration of pollutant already in receiving stream]
+
[proposed volume of discharge x unknown concentration of pollutant]
(25 Pa. Code §93.7 standards) (total flow)
25 Pa. Code §93.5(b), which defines the Q7-10 (otherwise known as design stream flow), provides:
(b) Application of design stream flow. The accepted design stream flow, to which the water quality criteria as set forth in this chapter shall apply, is the actual or estimated lowest 7-consecutive-day average flow that occurs once in 10 years for a stream with unregulated flow, or the estimated minimum flow for a stream with regulated flows, except where the Department determines that a more restrictive application is necessary to protect a particular designated or existing use. Where the lowest 7-con-secutive-day average flow that occurs once in 10 years is zero, the Department shall specify the design flow based on the identified or estimated flow at that point where a use identified in §93.4 (relating to Statewide water uses) becomes possible.
This section provides:
(a) Application of effluent limitations. The water quality criteria prescribed in this chapter for the various designated uses of the waters of this Commonwealth apply to receiving waters and are not to be necessarily deemed to constitute the effluent limit for a particular discharge, but rather one of the major factors to be considered in developing specific limitations on the discharge of pollutants. Where water quality criteria become the controlling factor in developing specific effluent limitations, the procedures set forth in §95.3 (relating to waste load allocations) will be employed.
Act of June 22, 1937, P.L. 1987, as amended, 35 P.S. §691.5(a). This section provides, in pertinent part:
(a) The department, in adopting rules and regulations, in establishing policy and priorities, in issuing orders or permits, and in taking any other action pursuant to this act, shall, in the exercise of sound judgment and discretion, and for the purpose of implementing the declaration of policy set forth in section 4 of this act, consider, where applicable, the following:
(1) Water quality management and pollution control in the watershed as a whole;
(2) The present and possible future uses of particular waters;
*315 (4) The state of scientific and technological knowledge;
(5) The immediate and long-range economic impact upon the Commonwealth and its citizens.
(Footnote omitted.)
We recognize that DER may not consider economic or aquatic impacts when enforcing a mandatory regulation which permits no discretion. East Pennsboro Township Authority v. Department of Environmental Resources, 18 Pa. Commonwealth Ct. 58, 334 A.2d 798 (1975). However, as we explained, this is not presently the case.
Although the Carlisle Court held that economic and aquatic effects must be considered by DER when issuing orders, it is clear under Section 5(a) that such consideration is required when “issuing orders or permits.’ (Emphasis added.) See Concerned Citizens for Orderly Progress v. Department of Environmental Resources, 36 Pa. Commonwealth Ct. 192, 387 A.2d 989 (1978).
Such weight may change where the discharge to be regulated would be the only discharge into the receiving waters.
The EHB decision contested herein affirmed two earlier EHB determinations. In one of these, dated January 14, 1985,
In view of the Boards ruling that the discharge monitoring point does not move downstream, even if the Q(7-10) at the discharge point is zero, there is no further point to contesting before the board the actual Q(7-10) at the point of discharge. Even assuming the design flow for Mathies’ NPDES permit were calculated at a point of first use downstream from the actual discharge point, the iron and manganese effluent limitations in Mathies’ NPDES permit either would not change or would result in only an insignificant relaxation.
We hold that EHB correctly concluded that (1) the stipulation removed from contention the issue of the Q7-10 value to be used in calculating the effluent limitations and (2) the proper compliance monitoring point is the discharge point.