The appellants, Mr. and Mrs. Mason, brought this action for damages arising from the appellees’ asserted failure to complete a contract by which they were to construct a dwelling house for the Masons. The trial judge directed a verdict for the defendants, on the ground that the plaintiffs’ proof of damages was insufficient to enable the jury to fix the pecuniary loss. For reversal it is contended that the proof was sufficient.
The trial judge was right. The measure of damages in a case of this kind is the difference between the unpaid portion of the contract price and the reasonable cost of completing the construction. Sternberg Dredging Co. v. Dawson,
Even so, the appellants, citing Crow v. Russell,
We note that the appellants did establish a breach of contract on the part of the contractors, All-Servis Builders, Inc., and Albert Cullipher, and therefore might have sought nominal damages. The point is not before us, however, as no such request was made in the trial court, nor has the point been argued on appeal. Even if the issue had been raised, we do not remand a cause for a new trial merely because nominal damages were not awarded. Crutcher v. Choctaw, O. & G. R.R.,
Affirmed.