190 Iowa 365 | Iowa | 1920
— I. The defendants appellants Lamson were " and are the owners of a hotel building. They contracted with Dunphy to construct said building. He proceeded with the contract for a time, then abandoned it, became bankrupt, and the Lamsons were compelled to and did complete the building. The plaintiff furnished materials as a subcontractor. He had no right to a lien, because the Lamsons filed release bond under Section 3093 of the Code, with appellant Equitable Surety- Company as surety. But plaintiff demanded and obtained judgment for $5,276.33 against Lamson and said Surety Company. It is conceded plaintiff is entitled to that sum from someone. But the Lamsons contend they are not liable to plaintiff. If that is so, of course, the said surety of the Lamsons is not liable either.
The major defense is this: The contract between Lamsons and Dunphy, the principal contractor, was made April 26, 1913. The appellants say that whatever was the law on that day governs during whatever time was needed to perform said contract ; that, under the law existing when the contract was made, and existing so far as this contract is concerned at all times material, the Lamsons rightfully made payments under the contract to the principal contractor; that these payments and what was
1-a
1-b
Without reference to the new statute, .it was possible so to exercise the right to pay the principal as that the subcontractor could have such payments disregarded. That was always so, if the owner paid when he knew or should have known that subcontractors might make timely claim, and that payments to the principal contractor would deprive such possible claimant of satisfaction, and paid under a contract which, while it authorized payment to the principal contractor, also authorized taking adequate precaution against his being paid what subcontractors might need and later claim. To this appellant responds: (a) That Lamson may not be charged with such knowledge, or with negligence in not obtaining it; and (b) that, even assuming knowledge, the payments made were on contract compulsion, and had to be made, no matter how payment might affect subcontractors who should perfect claim after such payments had been made. It will conduce to clear, coherent treatment to take up these responses in inverse order.
2-a
Assume that, if the contract compelled the payments that were made to the principal contractor, the owner cannot be -held by a subcontractor as to what was paid the principal — did the contract so compel? We say there was no such compulsion. The contract permitted the owner to retain 15 per cent “as part security for the faithful performance thereof,” and this 15 per cent should not be paid “until expiration of 30 days after the perfect completion of said work,” and until “the payment of all claims for labor and material furnished. ’ ’ Also, that the building should be delivered “free from all claims, liens and charges,” and delivered “free from expense” to the Lamsons. And it was contracted that the principal contractor should employ subcontractors in the execution of any part of the work to the approval of the architects. Surely, such contract did not forbid
“If the contractor shall allow indebtedness to accrue for labor or materials which become liens on said building, or the ground upon which it stands, the Lamsons may refuse to make the payments as hereinbefore agreed until satisfactory evidence has been furnished that said indebtedness has been discharged, and if such evidence is not furnished him within a period of ten days after demand therefor in writing, the Lamsons may discharge such indebtedness and deduct the amount required therefor from the contract price.”
Had the owners obeyed the contract by reserving the 15 per cent until “the payment of all claims for labor and material furnished,” made known within 30 days after perfect completion of the contract work, there would now be available, roughly, some $5,000 more than is needed to pay the $24,308.41, which is the total of all the unpaid claims. Had that reserve been made, neither old nor new statute would hurt the appellants. The Lam-sons had the contract right to refuse paying anything until they were assured by evidence “satisfactory” to them as to the matters before stated. Had Lamsons proceeded as authorized by the contract, they would not now need to litigate with the unpaid claimants. They would not need to assert as a defense that they had no knowledge or means of knowing that such claims existed, or might exist.
3-a
Under the law, the facts stipulated establish that payment was made with knowledge, or its equivalent, that such payment might jeopardize the rights of subcontractors. Payment to the principal contractor according to contract will not save the owner from paying also any subcontractor who later files lien, even if such owner knew not more than that subcontractors are furnishing material or labor. Chicago Lbr. Co. v. Woodside, 71 Iowa 359; Nancolas & Howard v. Hitaffer & Prouty, 136 Iowa 341; Wheel
We added:
“The owner sees men furnishing labor or materials under the contractor, and neither sees nor hears anything more. Can he properly proceed to pay the contractor, upon the assumption that the men furnishing the labor or materials have been paid in advance, or contemporaneously with the furnishing of the labor or materials? We think not. Laborers are not usually paid in advance, nor strictly as the labor progresses, nor is material usually paid for in advance, nor as each item is furnished, where, as in this case, it is furnished from time to time, during a considerable period.”
The owner is liable to the subcontractor if he pays the principal contractor, knowing that subcontractors are furnishing material, even though he does not know that they have not been paid. Othmer Bros. v. Clifton & Bishop, 69 Iowa 656; Chicago Lbr. Co. v. Woodside, 71 Iowa 359; Cedar Rapids S. & D. Co. v. Heinbaugh, 183 Iowa 1236; Wheeler L., B. & S. Co. v. White, 164 Iowa 495; Fay & Co. v. Orison, 60 Iowa 136; Andrews & Smith v. Burdick & Goble, 62 Iowa 714; Nancolas & Howard v. Hitaffer & Prouty, 136 Iowa 341. In Gilchrist v. Anderson, 59 Iowa 274, the owner knew the contractor had to buy the material from someone, but he knew neither that any had been bought from plaintiff nor that any had been bought on credit. The owner was held liable. It was on the theory of having such knowledge as put on inquiry. The court declined to say that, while an owner is put on inquiry where he knows the names of the persons who have furnished materials, he is not put upon inquiry where he knows simply that materials have been furnished by someone; and it is said to be the test whether the owner could probably, in the exercise of reasonable diligence, have discovered that the plaintiffs were entitled to a lien.
“These payments were according to the terms of the contract, and, as affecting them, the only issue to be determined is whether, at the time of making them, the owner had knowledge that plaintiff was furnishing the material. If she was aware of this, the law seems to be well settled that payment to the contractor will not constitute a defense.”
Nor can we agree that all held in Page & Son v. Grant, 127 Iowa 249, is that this is not so unless, when the owner pays, he
‘ ‘ The owner was not * * * justified in paying the principal contractor, even in strict accord with the terms of the contract,” if he has knowledge that subcontractors are furnishing material for the building. “If the owner observes the law, he cannot, of course, be made liable to subcontractors in such a way or to such an amount as to increase or add to the contract price of the building. * * * But by failing to observe his original contract as to time of payment, or to follow the law as to the rights of subcontractors, hé may become liable for more than the original contract price. ’ ’
In Jones & Magee Lbr. Co. v. Murphy, 64 Iowa 165, there is a review, and it is held to be the rule that the owner may settle in accordance with the terms of his contract, “if he has no knowledge and no reason to suppose that there are subcontractors.” It is held that, because the owner knew plaintiff was furnishing the lumber at the time it was going into the building, the fact that he paid in accordance with the terms of the contract is not sufficient to protect him.
Surely, it has been made plain that the contract with Dunphy distinctly recognizes, at the least, that there may be subcontractors. In Winter & Co. v. Hudson, 54 Iowa 336, such or less recognition held the owner, who merely knew that certain persons or subcontractors had furnished material used in the building. We said, in Fullerton Lbr. Co. v. Osborn, 72 Iowa 472, by the fact that the owner had provided in the contract (as here), he “has anticipated that there may be such liens, and has provided, so far as he can, that he may suffer no loss therefrom. In such case, he should inquire as to the existence of claims that may become liens. When such a provision is inserted in the .contract, it may well be supposed that some good reason therefor existed, such as the insolvency of the contractor. ’ ’ (And there is insolvency of the contractor in this case.)
We said, in Jones & Magee Lbr. Co. v. Murphy, 64 Iowa 165:
“Where the contract expressly recognizes the fact that there may be subcontractors, the owner becomes apprised at once that
In Slagle & Co. v. DeGooyer, 115 Iowa 401, at 403, it is recognized that, if the contract contemplates subcontractors, the owner must take notice that there will be subcontractors’ claims, and is not entitled to make payments without investigation.
•In Queal & Co. v. Stradley, 117 Iowa 748, the owner knew certain men were furnishing material for his building. He held more than enough to pay their claims. He had the right to, but did not, withhold this. And his contract had a provision authorizing him to protect against liens and charges against the principal contractor. The subcontractors prevailed. In Wheelock v. Hull, 124 Iowa 752, at 760, the importance of a clause providing for withholding funds by the owner is again emphasized. In Winter & Co. v. Hudson, 54 Iowa 336, the fact that the owner had provided in the contract that he "had the right to pay mechanics’ liens was regarded as a controlling circumstance. In Fullerton Lbr. Co. v. Osborn, 72 Iowa 472, it is pointed out what are the material points upon which the Gilchrist case and the Winter case are bottomed, and said that the first point in those cases was that contracts reserving the right to discharge mechanics’ liens are to be regarded as controlling.
Without any use of the new statute, the trial court was justified in holding appellants liable to plaintiff. The rights and duties of the Lamsons and their knowledge were such, and so dealt with by them, as to make them liable to plaintiff. Their own conduct makes a case for any claimant for the true worth of labor or material put by such claimant into the Lamson building. The new statute has charged them with no liability that did not exist before.
Prior to October 13, 1913, $57,891.43.
On October 13th, $5,000.
On October 20th, $5,251 and $5,000.
On November 10th, $20,950.
December 3, 1913, $15,000. ,
January 10, 1914, $21,370.47.
January 17, 1914, $3,700.
Notice, it does not appear what payments were made prior to the taking effect of the new statute; nor whether all was paid, or but a part, after July 4th, when the statute tóok effect. The time before July 4th and time after that date are both prior to October 13, 1913. So the fact that $57,891.43 was paid “prior to October 13, 1913, is no evidence that all was not paid between July 4th and October 13th.”
For all that appears, all of this 50-odd thousand dollars was paid after the new statute took effect. Assume it may not
The plaintiff has not been injured by refusal to give judgment against the Casualty Company. If the Lamsons and the Surety Company have been injured by that refusal, they have not asserted it in the suit we are dealing with; and we cannot, on this appeal, redress any injury they may have suffered. It follows that, on the cross-appeal as well as the main appeal, there must be an affirmance. — Affirmed.