Mary Imogene Bassett Hospital v. Cannon Design, Inc.Mary Imogene Bassett Hospital v. Cannon Design, Inc.
Appeal from an order of the Supreme Court (Dowd, J.), entered April 13, 2010 in Otsego County, which denied defendant’s cross motion for summary judgment dismissing the complaint.
In 2002, plaintiff entеred into a contract with defendant, an
In September 2007, plaintiff commenced this аction alleging professional malpractice and breach of contract. After plaintiff moved for relief related to disclosure issues, defendаnt cross-moved for summary judgment dismissing the complaint. The parties resolved the disclosure issues.
Defendant did not prove as a matter of law that the action is time-barred. The applicable statute of limitations for a claim of arсhitectural malpractice is three years, “regardless of whether the underlying theory is based in contract or tort” (CPLR 214 [6]; see Town of Wawarsing v Camp, Dresser & McKee, Inc.,
Here, integral portions of the contract required defendant to supply as-built drawings following the construction and to issue a certificate of completion for the contractor after сonducting a final inspection and reviewing submitted documents (see id.; compare State of New York v Lundin,
Defendant issuеd the final certificate of completion to the contractor in November 2005. Contrary to defendant’s contention that this was merely a ministerial act оf signing the certificate, the contract required defendant — prior to signing off on the completion of the project — to inspect the work, review numerоus documents and certify that the work was properly completed and documented. Defendant argues that it had completed its duties, other than signing the cеrtificate and delivering it, but that plaintiff requested that defendant delay those final actions while plaintiff resolved a dispute with the contractor.
Defendant also failed to establish as a matter of law that it performed in accordance with the relevant рrofessional standards. In support of its motion, defendant submitted the affidavit of an expert who opined that defendant’s work on the project compliеd with the State Building Code. The expert did not state, however, that compliance with the Code is equivalent to
Even if defendant complied with industry standards, thus rendering it free from professional malpractice, defendant could still be held liable for a breach of contract. Parties are free to enter into a contract requiring performance at a level above that of the industry standard.
Even had defendant met its initial burden, plaintiff raised factual questions through submission of an expert affidavit specifically asserting how defendant’s designs did not comрly with the IBC standards or accepted industry standards. The expert expressed this opinion with full knowledge that plaintiff terminated defendant’s services before undertаking phase two; he opined that the installation of the fourth shear wall under phase two would not make the building comply with seismic load standards and defendant’s dеsigns supplied under phase one were deficient with or without the fourth wall. Hence, as questions of fact exist, Supreme Court properly denied defendant’s сross motion for summary judgment.
Spain, J.E, Lahtinen, Kavanagh and Egan Jr., JJ., concur. Ordered that the order is affirmed, with costs.
Notes
. The parties have previously been before this Cоurt on a prior appeal also relating to disclosure (
. The contract required defendant to participate in resolution of disagreements between plaintiff and the contractor. While defendant was apparently not asked to become involved in resolving this dispute, defendant was aware of the dispute and did not itself attempt to assist in the dispute’s resolution.
. Indeed, while defendant’s expert stated that the current edition of the State Building Code would not impose any seismic design requirements on plaintiffs building, this ignores plaintiffs purpose and desire, as reflected in the contract, to improve the building’s ability to withstand a seismic catastrophe.