Mark Morrel Ruth Morrel v. Nationwide Mutual Fire Insurance CompanyMark Morrel Ruth Morrel v. Nationwide Mutual Fire Insurance Company
Affirmed by published opinion. Judge KING wrote the opinion, in which Judge WILKINS and Judge WILLIAMS joined.
OPINION
Mark and Ruth Morrel obtained a money judgment against The Miller Group Construction Company, Inc. (the “Contractor”) in the United States District Court for the District of Columbia. When they
Nationwide now appeals, arguing that (1) the District of Columbia judgment was obtained by fraud and upon defective service, and (2) the Morrels may not recover under the insurance policy because the Contractor breached its obligations thereunder. We reject Nationwide’s position on both issues and affirm.
I.
On April 10, 1995, the Morrels hired the Contractor to renovate their home in Bethesda, Maryland. The parties entered into a written construction contract. While performing the renovations, the Contractor seriously damaged the Morrels’ house.
On August 12, 1995, the Morrels submitted a claim for this damage to Nationwide. Thereafter, Nationwide opened a file for the Morrels’ claim and had the property inspected several times. During the course of the next year, Nationwide continued to investigate the Morrels’ claim.
As of July 1996, the Morrels still had not been compensated for the damage to their property. Consequently, on July 22, 1996 — and as authorized by Article 10.8 of the construction contract — the Morrels commenced an arbitration proceeding against the Contractor in accordance with the rules of the American Arbitration Association. In their filings with the arbitrator, the Morrels named as defendants “The Miller Group Construction Company, Inc.” and its president, Paul D. Miller. In letters dated September 22 and October 8, 1996, the Morrels notified Nationwide of this arbitration proceeding. An arbitration hearing took place on October 15, 1996. Despite receiving notice, neither Nationwide, nor Mr. Miller, nor the Contractor participated in the arbitration. On November 11, 1996, the arbitrator awarded the Morrels a total of $36,774.25 in damages. However, the award was made against Mr. Miller personally, and not against the Contractor. 1 The award was affirmed by the American Arbitration Association on December 20,1996.
The Morrels were dissatisfied with the arbitration award. On February 7, 1997, they filed an Application to Correct or Vacate Arbitration Award (the “Application”) in the United States District Court for the District of Columbia. 2 The Application named as defendants Paul D. Miller and “The Miller Group Construction Company.” The Morrels had the Application personally served on Mr. Miller, who also accepted service on behalf of “The Miller Group Construction Company,” as its president. On May 6, 1997, the Morrels sent Nationwide a copy of the Application and all accompanying pleadings by certified mail. Nationwide apparently received these documents the next day. 3
On July 28, 1997, the Morrels wrote Nationwide and demanded that it satisfy the District of Columbia judgment. Nationwide refused. In its letter of August 22, 1997, Nationwide explained that the Contractor had failed to meet its obligations under its liability insurance policy with Nationwide (the “Policy”). More specifically, Nаtionwide claimed that, in violation of the Policy, the Contractor had failed to (1) assist Nationwide in investigating the Morrels’ claim; (2) notify Nationwide that the Morrels had sued the Contractor; and (3) send Nationwide copies of any documents relating to the Mor-rels’ suit or otherwise cooperate in the defense of that suit. Given these facts, Nationwide argued that the Contractor’s breach excused Nationwide from paying the Morrels’ claim.
In December 1997, the Morrels attempted to execute the District of Columbia judgment on the Contractor, but the United States Marshal’s Service was unable, after repeatеd attempts, to locate Paul Miller, and the judgment was returned unsatisfied.
On January 26, 1998, the Morrels initiated this diversity action against Nationwide in the district court for the Eastern District of Virginia. The Morrels sued under Section 38.2-2200 of the Virginia Code, which authorizes “direct action” suits against liability insurers. Both parties moved for summary judgment, and the district court ruled in favor of the Morrels. It concluded that the District of Columbia judgment was facially valid and that, as a result, the district court lacked authority to look behind or set aside that judgment. Additionally, the district court found that Nationwide had delayed too long in notifying the Morrels that it would invoke the Contractor’s failurе to perform under the Policy as a defense to liability. Consequently, the district court concluded that Nationwide had waived any defense arising out of its insured’s breach of the Policy.
Nationwide now appeals to this court, contesting the validity of the District of Columbia judgment in favor of the Morrels and the district court’s conclusion that Nationwide had waived its defenses based on the Contractor’s breach of the Policy.
II.
Section 38.2-2000 of the Virginia Code required Nationwide to include language in the Policy providing for “direct action” against Nationwide by certain judgment creditors of its insured:
No policy or contract insuring or indemnifying against liability for ... injury to or destruction of property, shall be issued and delivered in this Commonwealth unless it contains in substance the following provisions or other provisions that are at least equally favorable to the insured and to judgment creditors:
That if execution on a judgment against the insured or his personal representative is returned unsatisfied in an action brought to recover damages for injury sustained or for loss or damage incurred during the life of the policy or contract,then an action may be maintained against the insurer under the terms of the policy or contract for the amount of the judgment....
Nationwide’s challenge to the district court’s grant of summary judgment arises from the language of
Having reviewed the district court’s grant of summary judgment de novo, we disagree with Nationwide.
See Monumental Paving & Excavating, Inc. v. Pennsylvania Mfrs. Ass’n Ins. Co.,
A.
1.
Before reaching the substance of Nationwide’s challenge to the District of Columbia judgment, we address a procedural matter that caused some confusion below. The district court concluded that, because the District of Columbia judgment appeared to be valid on its face, the district court lacked authority to look behind the judgment to determine whether it had been properly issued. Instead, the district court suggested that Nationwide could attack the District of Columbia judgment only in the court that had issued it.
The district court underestimated its authority here.
Further, and also in contrast to a motion for relief, an independent action may be brought in a court other than the one that issued the contested order: “A federal court can entertain an original action to enjoin or otherwise grant relief from a judgment ... rendered not only by it, but also by another fеderal court.” 7 Moore’s
Federal Practice
at 60-366; see
also Abbott,
The facts of Aetna Casualty & Surety Co. v. Abbott are analogous to this case. In Abbott, a bank customer won a judgment in Maryland state court against Ta-koma Park Bank, bаsed on the disappearance of property from the customer’s safe deposit box at the bank. When the judgment was returned unsatisfied, the customer sought to enforce the judgment against the bank’s liability insurer in the United States District Court for the District of Maryland. The insurer countered that the state court judgment was void because the plaintiff and the bank had conspired to defraud the state court. Id. at 41. The district court disagreed and granted judgment on the pleadings for the bank customer.
On appeal, this court addressed the insurer’s fraud defense.
Id.
at 43. importantly, we did not conclude that the fáeial validity of the state сourt judgment barred our substantive review of the insurer’s fraud defense. Instead, we rejected the fraud allegations on their merits, holding that the insurer had not stated them with particularity sufficient to satisfy
Here, as in
Abbott,
the plaintiffs obtained a judgment in another jurisdiction against the defendant’s insured, and they now seek to enforce it in the Eastern District of Virginia against the insurer. The insurer now, as in
Abbott,
raises equitable defenses to the judgment, including contentions that the judgment is tainted by fraud. As a result, the district court was permitted to treat Nationwide’s defenses as a
2.
Nationwide first argues that the default judgnient against its insured, The Miller Group Construction Company, Inc., is defective because the Application to Correct or Vacate, filed in the United States District Court for the District of
Nationwide’s argument is premised on a thin reed — a misnomer in the spelling of the name of its insured — and is merit-less. It has long been the rule in this circuit that service of process is not legally defective simply because the complaint misnames the defendant in some insignificant way. As we recognized many years ago:
A suit at law is not a children’s game, but a serious effort on the part of adult human beings to administer justice; and the purpose of process is to bring parties into court. If it names them in such terms that every intelligent person understands who is meant ... it has fulfilled its purpose; and сourts should not put themselves in the position of failing to recognize what is apparent to everyone else.... As a general rule the misnomer of a corporation in a notice, summons ... or other step in a judicial proceeding is immaterial if it appears that [the corporation] could not have been, or was not, misled.
United States v. A.H. Fischer Lumber Co.,
Here, there is simply no possibility that Paul Miller, the president of the insured corporation who accepted service on its behalf, did not understand that the Application filed by the Morrels naming “The Miller Group Construction Company” sought to bring The Miller Group Construction Comрany, Inc. into court. The lack of the abbreviation “Inc.” misled no one. Indeed, we have held that the inclusion of an unnecessary “Inc.” in a defendant’s name does not make the complaint defective.
A.H. Fischer Lumber Co.,
Moreover, the body of the Application refers to both the construction project performed by the Contractor and the ensuing arbitration, to which the Contractor was indisputably a party.
7
Perhaps most significantly, a copy of the construction contract giving rise to this entire controversy was attached to the Application; the contract is between the Morrels and “The Miller Group Construction Co. Inc.” If there was any confusion as to what business entity the Application sought to name, the allegations in the Application and its attachments dispelled that confusion.
See Barsten v. Department of Interior,
Finally, Nationwide’s own correspondence with the Morrels points out the unlikelihood that the Application could have caused any confusion. In its letter of August 22, 1997, Nationwide refers to its insured alternately as “The Miller Group Construction Company, Inc.” and “The Miller Group Construction Company.”
8
3.
In a related argument, Nationwide claims that the District of Columbia judgment is the product of fraud, because the final judgment itself names “The Miller Group Construction Company, Inc.,” while the Application had named “The Miller Group Construction Comрany.” Nationwide argues that this change in names was tantamount to the Morrels suing one company and then having judgment entered against another. This argument also is entirely meritless.
As explained above, the Morrels’ Application was sufficient to bring the Contractor before the district court for the District of Columbia, even though the Application did not get the company’s name precisely right. See id. As a result, we conclude that neither the court nor the Contractor could have been defrauded when, after the Contractor was properly made a party to the suit, a final judgment was entered that did get the Contrаctor’s name precisely right. Changing of the defendant’s name in the judgment form did not have the effect of entering judgment against “another company”; it simply corrected the name of a company that already was a defendant.
It is unclear in the record why the misnomer occurred and why the Contractor is named differently in the Application and the final judgment. Assuming that the Morrels discovered the error in the Application after it had been filed, the better practice would have been to move for permission to amend the corporate defendant’s name under
Because the Contractor had been served as effectively as if its correct corporate name had appeared on the Application, the inclusion of its correct name on the final judgment changed no legal aspect of the case and did not prejudice Nationwide. Consequently, this misnomer did not serve in any way to defraud the court or any party to the proceeding.
B.
Finally, Nationwide contends that the Morrels cannot recover against it “under the terms of the policy,” within the meaning of Section 38-2.200(2) of the Vir
A claimant seeking to bring a direct action against an insurer in Virginia stands in the shoes of the insured against whom his claim arose. Consequently, if the insured has breached the insurance policy, the insurer may assert this breach as a bar to the third-party claimant’s recovery.
E.g., Liberty Mut. Ins. Co. v. Safeco Ins. Co. of America)
Whenever any insurer on a policy of liability insurance discovers a breach of the terms or conditions of the insurance contract by the insured and the insurer intends to rely on the brеach in defense of liability for any claim within the terms of the policy, the insurer shall notify the claimant ... of its intention to rely on the breach as a defense. Notification shall be given within twenty days after discovery by the insurer or any of its agents of the breach or of the claim, whichever is later.
The ultimate purpose of the statute, as explained by the Supreme Court of Virginia, is to protect claimants such as the Morrels:
The obvious purpose of the statute is to require a liability insurer that intends to rely on a breach of the terms and conditions of the policy contract, in defense of any claim under the policy, to furnish prompt notice of such intention to the claimant ... so that steps may be taken by the claimant, a stranger to the insurance contract, to protect his rights.
Liberty Mut. Ins. Co.,
Here, Nationwide argues that the Contractor breached the provisions of the Policy requiring the Contractor to assist Nationwide in the event of a lawsuit. For example, subsectiоn IV.2(c) of the Policy requires the Contractor to “[cjooperate with [Nationwide] in the investigation, settlement or defense of the claim or suit.” J.A. 37. Nationwide contends that the Contractor provided no assistance whatsoever, and thus breached this provision of the Policy.
Assuming Nationwide is correct on this point, the question becomes whether — and if so, when — Nationwide notified
Because Nationwide notified the Mor-rels on August 22, 1997, that it would rely on its insured’s breach to defend against the Morrels’ claim, this notice was timely only if Nationwide “discovered” both the Morrels’ claim and the Contractor’s breach no earlier than August 2, 1997.
Second, Nationwide had discovered the Contractor’s breach of the Policy before August 2, 1997. The Supreme Court of Virginia has described “discovery” of an insured’s breach as a two-step process: “ ‘[DJiscovery’ of a breach entails, first, awareness by the insurer of facts tending to show there has been a violation of the policy provisions and, second, evaluation of those known facts culminating in a decision that a breach apparently has occurred.”
Liberty Mut. Ins. Co.,
In its opposition to the Morrels’ summary judgment motion, Nationwide demonstrates that it had effectively discovered the Contractor’s breach by the time it received the arbitration award. At this point, Nationwide admits that it was aware of the Contractor’s “previous breach of the terms and conditions of the policy.” J.A. 421. Such a statement indicates that, when it received the award, Nationwide was aware not only of the underlying facts, but had determined that they constituted а breach of the Policy.
Indeed, Nationwide cannot have concluded otherwise. In its letter of August 22, 1997, Nationwide acknowledges that the Contractor had not met “any” of its policy requirements since the Morrels’ home was first inspected; this inspection took place no later than September 1995. Consequently, in May 1997, Nationwide had known for at least nineteen months that the Contractor was not upholding its responsibilities under the Policy. Also at this time, Nationwide received the arbitration award — not from its insured, but from
At the latest, then, Nationwide had discovered the Contractor’s breach by May 7, 1997, when it received from the Morrels a copy of the District of Columbia pleadings, to which the arbitration award was attached as an exhibit. Because it was aware of the Morrels’ claim by that time as well, Nationwide had discovered both this claim аnd the Contractor’s breach more than three months before it notified the Morrels of its intent to rely on the breach as a defense to the Morrels’ claim. Nationwide therefore did not satisfy the statutory notification requirement of
Nationwide nevertheless contends that receipt of the arbitration award did not trigger its notice obligations under
The twenty-day clock of
III.
Having rejected Nationwide’s equitable challenge to the District of Columbia order, and having determined that Nationwide waived its defenses based on the Contractor’s apparent breach of the Policy, we affirm the district court’s grant of summary judgment in favor of the Morrels.
AFFIRMED.
Notes
.During the course of the arbitration proceeding it was discovered that the Commonwealth of Virginia had terminated the corporate status of The Miller Grоup Construction Company, Inc., on September 9, 1994. Paragraph 1 of the arbitration award states:
1. The Respondent, Paul D. Miller, is liable to Claimants in place of the Respondent, the Miller Group Construction Co., Inc. because the Commonwealth of Virginia terminated the corporate existence of the Miller Group Construction Co., Inc. prior to the formation of the Miller contract and, accordingly, Paul D. Miller is individually liable for the obligations created by the contract.
J.A. 99.
. Because the arbitration proceedings had taken place in Washington, D.C., the district court for the District of Columbia had jurisdictiоn over the Application.
See
. The claim file notes of Nationwide’s claims adjuster, Jim Reilly, contain the following en
J.A. 410.
. Subsection IV.3 of the Policy, entitled "Legal Action Against Us," authorizes direct action suits against Nationwide under certain circumstances:
No person or organization has a right under this Coverage Part ... [t]o sue us on this Coverage Part unless all of its terms have been fully complied with.
A person or organization may sue us to recover on an agreed settlement or on a final judgment against an insured obtained after an actual trial; but we will not be liable for damages that are not payable under the terms of this Coverage Part or that are in excess of the applicable limit of insurance.
J.A. 37.
. Summary judgment is appropriate under
. A party wishing to assert an independent action defensively should plead those defenses as affirmative defenses or compulsory counterclaims. 7 Moore’s Federal Practice at 60-370 n.27. We note that Nationwide did not plead fraud and insufficient process as either affirmative defenses or counterclaims. Nevertheless — and especially because we resolve these issues against Nationwide on the merits — we will not reject Nationwide’s defenses on the grounds that they were not properly pleaded. We note, however, that proper pleading of these defеnses might well have alerted the district court to the source of its authority to look behind the District of Columbia judgment.
. Nationwide attempts to create an argument out of the Application's description of the corporate defendant as "a sole proprietorship whose corporate existence was terminated by the Commonwealth of Virginia on September 9, 1994.” Rather than confusing the issue, this description appears to be aimed at carefully naming the company in a legally accurate manner. Whether the company had, or had not, technically converted into a sole proprietorship when it lost its corporate charter, all parties agree that its charter was revoked on September 9, 1994. Consequently, this description does not invalidate the Application.
. In pertinent part, Nationwide's letter read as follows:
Following the initial inspection of the Mor-rel’s[sicj house, Mr. Paul Miller nor anyone else associated with The Miller Group Construction Company did not provide Nationwide with any further assistance in resolving this claim.... The insured has an obligation to send us copies of any legal papers received in connection with the suit and cooperate with the investigation and defense of the suit. Again, the Miller Group Construction Company failed to meet any of these policy requirements.
In summary, the insured did not meet the requirements of their policy and therefore Nationwide has no obligation to pay any portion of the judgment against Paul Miller and The Miller Group Construction Company, Inc.
J.A. 477 (emphasis added).
. The parties agree that the pre-1997 version of the statute applies to the dispute at issue. Section 38-2.2226 was amended in 1997 and currently reads as follows:
Whenever any insurer on a policy of liability insurance discovers a breach of the terms or conditions of the insurance contract by the insured, the insurer shall notify the claimant or the claimant's counsel of the breach. Notification shall be given within forty-five days after discovery by the insurer of the breach or of the claim, whichever is later.... Failure to give the notiсe within forty-five days will result in a waiver of the defense based on such breach to the extent of the claim by operation of law.
. Nationwide suggests that it gave the Mor-rels appropriate notice in late 1996, when its claims adjuster, Jim Reilly, told the Morrels that “because he was unable to contact The Miller Group Construction Company, Inc. or Mr. Paul Miller, he was unable to respond to the Morrels’ claims and that he would be unable to respond to the Morrels’ claims until he had the cooperation of the policyholder....” J.A. 442. Assuming such a conversation took place, its content, as described by Nationwide itself, does not satisfy the notification requirements of