303 Mass. 251 | Mass. | 1939
The Rendle Contracting Company, a respondent, hereinafter called the Rendle Company, made a contract with the Commonwealth for the construction of a bridge and a portion of a highway in the town of Bolton, and the Maryland Casualty Company, a respondent, hereinafter referred to as the surety company, executed a bond, as surety, to secure payment by the Rendle Company for labor performed or furnished, and for materials used or employed in the construction. This petition was brought under G. L. (Ter. Ed.) c. 30, § 39, as amended by St. 1935, c. 472, § 1, to obtain the benefit of the security, and several claimants intervened. All claims have been disposed of except those of Sabatino Toscano and Joseph T. Ryerson & Son, Inc., hereinafter referred to as the Ryerson Company. The case was referred to a master whose report was confirmed by interlocutory decree. The final decree established Toscano’s claim in full against the security; it established the Ryerson Company’s claim but only in part against the security. The surety company and the Ryerson Company appealed. The evidence is not reported.
I. The only question raised by the appeal of the surety company is whether the statement of Toscano’s claim was filed in accordance with § 39, as amended, which provides that each “claimant shall file . . . a sworn statement of his claim, within sixty days after the claimant ceases to perform labor or furnish labor, materials, appliances and equip
The trial judge established the debt of the Rendle Company owed to Toscano in accordance with the findings of the master, and found and ruled that a lien for the total amount of the debt including principal and interest “is established against” the surety company.
Unless Toscano’s claim was filed in accordance with the quoted provisions of the statute he can establish no claim against the security. We find nothing in the report of facts by the master that warrants such conclusion as a matter of fact, and we think that the judge was not warranted in making such finding. There is nothing to control the bald finding of fact by the master that when Toscano filed his
We think that it was error to rule that the claim was filed in accordance with the provisions of the statute. It was pointed out in the case of Peerless Unit Ventilation Co. Inc. v. D’Amore Construction Co. 283 Mass. 121, 124, that the statute requiring security for payment for labor and materials furnished for public works is an outgrowth of the statute creating mechanics’ liens upon buildings and land of private persons, and that decisions under that law are in point in so far as they involve the construction of similar provisions of law in the statutes relating to liens connected with public work. Cook Borden & Co. Inc. v. Commonwealth, 293 Mass. 174, 180. The statute does not authorize the filing of a statement except when the work and labor have been done under such circumstances as to create a debt which is due and payable either then or at some future time. The “statement required cannot be made until everything is done that is necessary to create the relation of debtor and creditor, and until all labor and materials have been furnished which enter into the debt for which the lien is claimed.” General Fire Extinguisher Co. v. Chaplin, 183 Mass. 375, 377. Under the facts found there can be no apportionment of the contract price giving a lien for that part represented by the work done before the filing of the statement and there is no lien for that part represented by the work done afterwards. Angier v. Bay State Distilling Co. 178 Mass. 163. General Fire Extinguisher Co. v. Chaplin, 183 Mass. 375, 378. Peerless Unit Ventilation Co. Inc. v. D’Amore Construction Co. 283 Mass. 121, 125. As was pointed out in the last case cited, the decision in the case of Bay State Dredging & Contracting Co. v. W. H. Ellis & Son Co. 235 Mass. 263, “had no tendency to authorize the filing of a sworn statement before the work included in the claim is completed.” We find nothing in Barry v. Duffin, 290 Mass. 398, to support the contention of Toscano that there has been, or can be, any waiver of the failure to file the claim within the specified
The result is that so much of the final decree as is contained in the fifth paragraph is reversed and that in the decree as modified Toscano’s claim against the Rendle Company is to be established in the amount found due by the master, with interest to the date of final decree; that Toscano is to have costs against the Rendle Company in the sum of $26.90, and that the bill as to Toscano against the surety company is to be dismissed with costs of this appeal.
2. We think there was no error in the final decree as to the establishment of the claim of the Ryerson Company. The master found that the Ryerson Company, in accordance with its contract of April 22, 1937, with the Rendle Company, furnished steel for the construction of the bridge. This contract called for approximate amounts of steel but at fixed prices. The structural steel furnished under the contract was to be “shop” painted. All materials called for by the contract were delivered on different dates between May 22, 1937, and September 13, 1937. Orders or instructions were given from time to time as to the exact quantities of steel required by the Rendle Company and all steel furnished was “in every way satisfactory.” The last delivery was on September 13, 1937. The Ryerson Company had nothing to do with the erection or placing of the steel that it furnished. This work was done by the Rendle Company. “Steel in place” means to include two coats of field paint, “usually applied by those having the obligation to put the steel in place.” Nothing was said by the parties about field paint at any time until November 10, 1937, when the Rendle Company gave an order to the Ryerson Company for fifty gallons of field paint as distinguished from shop paint, and this paint was used in the construction of the bridge. The master found as a fact that the order of November 10, 1937 (which was the paint order) was something separate and apart from the order given in April for steel; and he stated that “unless, as a
. . .” The language quoted is identical, except as to the place where the claim is to be filed, with the language hereinbefore quoted as appearing in G. L. (Ter. Ed.) c. 30, § 39, as amended by St. 1935, c. 472, § 1, and in that case
The result is that only so much of the claim of the Ryerson Company as represents the cost of the paint furnished, together with interest and costs, is established against the security, and that there was no error in the final decree with respect to the establishment of the claim of the Ryerson Company.
The sixth paragraph of the final decree is to be modified by providing that the amount therein established against the security is to be paid by the clerk of courts out of the retained percentage now in his hands, as described in the first paragraph of the decree, and that the surety company is to have its costs of this appeal.
3. The final decree is also to provide for the disposition of any part of the retained percentage remaining in the hands of the clerk of courts after all other provisions of the decree have been complied with. As modified by what has been said, the final decree is affirmed.
Ordered accordingly.