246 Pa. 478 | Pa. | 1914
Opinion by
This is a proceeding to have damages assessed for land appropriated by the defendant company in widening its railroad. Some years ago the defendant obtained by grant a strip of land lying along and parallel to the Monongahela river in Fayette County, being part of a tract containing about 194 acres, on which it constructed a railroad with four tracks. There were about forty acres bottom land and the residue was a hill or upland. Desiring to widen and improve its road, the defendant company appropriated the strip of land lying between its right of way and the river, being about 2,300 feet in length and of an average width of about 150 feet, and also a strip of the same length and about 22% feet wide adjacent to and on the opposite side of the defendant’s original right of way. The two pieces of land contain in the aggregate about ten or eleven acres. The parties filed a stipulation agreeing that an amicable action should be entered and the question of damages tried as though viewers had been appointed, appeal taken from their award, and an issue framed to be tried by a jury. The trial resulted in a verdict of $72,918 for the plaintiff, and judgment having been entered thereon the defendant has appealed.
We have examined with care the twenty-eight assignments filed in the case and the printed argument of the learned counsel in support of them, and we fail to discover any reversible error in the record. The learned judge submitted the case to the jury in an elab
The first assignment alleges the court erred in not granting a new trial because the verdict was grossly excessive and contrary to the weight of the evidence, and because of after-discovered evidence. We fully agree that a trial court should protect the defendant by setting aside an excessive verdict and directing a retrial of the cause. This is a duty which should be resolutely performed whenever the occasion arises, so that the law may be vindicated and the rights of the litigants may be protected. But in the present case we are of opinion that the evidence clearly warranted the verdict and that the court did not abuse its discretion in refusing a new trial. The damages sustained by the plaintiff company by reason of the appropriation of part of its land was the difference in the market value before and after the taking as affected thereby. In ascertaining the value of the whole tract prior to the taking, it was the duty of the jury to consider not only its present use and condition but any use to which it was then adapted or any prospective use which at the time gave it a present value, excluding, however, any use which was merely speculative and to which it could not reasonably be anticipated the land would in the future be applied. In Shenango, Etc., R. R. Co. v. Braham, 79 Pa. 447, 453, Paxson, J., delivering the opinion said: “In estimating the market value of land, everything which gives it intrinsic value is a proper element for consideration ......It is the general market value for any purpose that will induce persons to purchase, which is the true test.” In Boom Co. v. Patterson, 98 U. S. 403, 407, Field, J., said: “In determining the value of land appropriated for public purposes, the same considerations
Referring now to the evidence, the competency of which we shall notice hereafter, it is apparent that the verdict is not only not excessive, but is well within the amounts fixed by the plaintiff’s witnesses. They testi
The defendant sets up as another ground why a new trial should be granted the contents of the affidavits of two of plaintiff’s officers appended to reports made to the auditor general of this State, and filed in his office
The second assignment doubtless was filed because appellant’s counsel overlooked the court’s answer to the point for charge which is alleged to be erroneous. In the printed brief, counsel say that the general tenor of the point is unobjectionable but it states a fact not supported by the testimony. It appears in the assignment of error as printed in the appellant’s paper-book that the answer was simply “affirmed,” which would be open to the appellant’s criticism. The court, however, did not simply affirm the point, but answered it by saying: “The
A point for charge should be stated so that the trial judge may either affirm or deny it, Seifred v. R. R. Co., 206 Pa. 399, and he is not required to explain or qualify it, or add anything to his answer. Under our more recent rulings, we cannot say that the court erred in refusing the defendant’s first point which is the subject of the third assignment. In Pennsylvania Schuylkill Valley R. R. Co. v. Reading Paper Mills, 149 Pa. 18, 20, we said: “Such title is sometimes called an easement, but it is a right to exclusive possession, to fence in, to build over the whole surface, to raise and maintain any appropriate superstructure including necessary foundations and to deal with it within the limits of railroad uses as absolutely and as uncontrolled as an owner in fee......It would seem to be rather a fee in the surface and so much beneath as may be necessary for support, though a base or conditional fee terminable on the cessor of the use for railroad purposes.” In Pittsburgh, Fort Wayne and Chicago Railway Co. v. Peet, 152 Pa. 488, 492, Paxson, J., delivering the opinion says: “The vice of this argument consists in treating the plaintiff’s right as a mere easement or right of way. It is a great deal more than a right of way. It has the actual possession of the property, and that possession is exclusive, at all times and for all purposes, except where a way crosses it.......The estate acquired by a railroad company by a condemnation of land is often spoken of as an easement, but the term is used in a loose way for the purpose of distinguishing it from a fee.” In Dilts v. Plumville Ry. Co., 222 Pa. 516, 525, it is said: “The interest which a railroad company acquires in real estate by the right of eminent domain is well settled in this state. It is not a fee nor is it an easement in the proper sense of that word.” In the very recent case of Brown v. Surety Co.,
There is no merit in the fourth and fifth assignments. The purpose of the redirect examination complained of in the fourth assignment was simply to have the witness explain some things brought out in the cross-examination, which is always permissible or, at least, is in the discretion of the court. The answer criticised in the fifth assignment was admissible, as it was the opinion of an expert on a relevant matter of which the jury were not capable of judging: Stocker v. Schneider, 228 Pa. 149, 156.
We cannot sustain the several assignments alleging error in the admission of certain testimony of the plaintiff company because the estimates of the values given by its witnesses were based upon mere speculation as to a possible future use of the land. The testimony disclosed that the land was not only suitable for a manufacturing site, coke plant, etc., but that owing to its location and adaptability it has a present market value for such purposes. The situation of the property on the Monongahela river, navigable from Pittsburgh several miles south of plaintiff’s land with rail transportation to Pittsburgh on both sides of the river, and the evidence showing the necessity for locations for manufacturing plants within the territory, the learned trial judge was right in not holding that the uses to which the property was adapted and could be applied and on which the witnesses based their estimates of its value were speculative or fanciful. It would have been plain error for the court to have excluded this testimony and held as a matter of law that the plaintiff’s property was either not available for such uses or that it could not reasonably be ex
We do not agree with the defendant that the plaintiff’s witnesses were not competent to prove that the land was available for use as a manufacturing site or its value for such use. These witnesses resided in Pittsburgh or in the Monongahela Valley, some at least had long experience in selling properties for manufacturing sites, not only on the Monongahela river but on the Ohio and Allegheny rivers, they knew what was required for a manufacturing site and were familiar with the prices at which lands along those rivers adapted to such use were sold or at which they were held by the owners. It is true we have held that to qualify a witness to testify to the damages sustained by the owner of land appropriated under eminent domain proceedings he must know the land before and after the taking and in a general way have such knowledge of it that he can properly estimate its market value. This rule must be regarded as settled law, as it has uniformly been followed in this State. We have not held, however, that expert testimony is not competent to prove that the land taken is specially adapted to a valuable use, and its value for that special use. On the contrary, the rule is settled that expert witnesses are competent to prove the value of the land for any special use to which it is reasonably adapted: Harris v. Railroad Co., 141 Pa. 242; Gearhart v. Water Co., 202 Pa. 292; Cox v. Philadelphia, Etc., R. R. Co., 215 Pa. 506. In the former case we said (p. 252): In estimating the value of the lot before the taking, its
We held in Hanover Water Co. v. Ashland Iron Co., 84 Pa. 279, and it is supported by the reasoning in Schuylkill River E. S. Railroad Co. v. Stocker, 128 Pa. 233, that assessments for taxes are not competent evidence to aid a jury in assessing damages in condemnation proceedings. This of itself, we think, is a sufficient reason for refusing to interfere with the court’s discretion in excluding the questions as to the assessed value of lands in that vicinity asked plaintiff’s expert witnesses on cross-examination. As pertinently suggested by plaintiff’s counsel, if assessments are not evidence of the value of the property, it is immaterial whether the witnesses knew them or not. Their well-understood unreliability as showing the real or market value, if known
The ninth and tenth assignments are not'sustained. They allege error in excluding answers to certain questions. While the special reasons assigned by plaintiff’s counsel for excluding the testimony are manifestly without merit, yet the ruling must be sustained on the ground that the questions were mere repetitions of others which had been answered. Hence, the exclusion of the answers was within the discretion of the court. The fourteenth assignment complains of what substantially had already been answered without objection, and the subject of the nineteenth assignment is simply an explanation or amplification of what the witness had already said. The cross-examination complained of in the twenty-fifth and twenty-sixth assignments was entirely proper to test the credibility of the witness. The examination of the witnesses, Lindy and Miller, does not disclose an abuse of the court’s discretion in excluding their testimony and, therefore, the twenty-seventh and twenty-eighth assignments are not sustained.
Judgment affirmed.