Marcus Garvey Square, Inc. v. Winston Burnett Construction Co. of California, Inc.Marcus Garvey Square, Inc. v. Winston Burnett Construction Co. of California, Inc.
Lead Opinion
This is a cross-complaint by a general contractor against the building owner, mortgage lender, and several federal agencies connected with the building project to recover the balance allegedly due under the construction contract. The case was originally filed in California Superior Court and was removed pursuant to
I.
The facts of this case were largely stipulated. In 1969, the Federal Housing Administration (FHA), a subdivision of the Department of Housing and Urban Affairs (HUD), began negotiations for the construction of a low and moderate income housing project in San Francisco’s Western Addition district. In their final form, the plans called for the construction of a 101 unit apartment complex, to be named Marcus Garvey Square (the Square). A nonprofit California corporation, Marcus Garvey Square, Inc. (MGS), was created to own the Square. MGS was composed of various community groups and had no other assets. The project was to be financed by a mortgage from Home Savings & Loan (Home), a California corporation, which would be insured by the FHA and HUD pursuant to
On September 1 and 10, 1970, a number of documents relating to this project were executed. For the purposes of this litigation the crucial documents were:
1) A construction contract between MGS and Burnett which called for construction of the Square by September 10, 1971 at a price not to exceed $1,710,-040.00.
2) A Building Loan Agreement between MGS and Home, whereby Home agreed to provide $2,175,300.00 for the project.
3) A Mortgagor’s Agreement between Home, MGS, and the Secretary of HUD, whereby HUD agreed to insure the mortgage.
Burnett had earlier arranged for payment and performance bonds which ran to MGS and were assignable to the Secretary. Boise Cascade Co. (Boise) agreed to indemnify the bonding company for any losses suffered on these bonds. All of these documents, and almost all of those connected with the project, were HUD or FHA specified and approved.
Construction began on September 18, 1970. Pursuant to the contractual arrangements, Burnett would requisition a progress payment from MGS on an FHA form, MGS would certify the amount to Home, and Home would then obtain FHA insurance for the amount of that particular progress payment. The FHA was committed to provide mortgage insurance, but only as advances were made and only for amounts actually advanced. Ten per cent of each progress payment was retained by Home, to be paid over when the Square was completed.
For reasons not specified in the record, construction of the Square was delayed. On October 11, 1971, Boise notified HUD that Burnett had been merged into Boise and Boise had assumed all Burnett’s rights and obligations. Boise completed the Square January 20, 1972, more than four months late. The last FHA insurance certificate was issued March 2, 1972, and counting the amount Burnett received from that advance, Burnett received a total disbursement of $1,540,150.32. Under the construction contract, MGS still owed Burnett $169,-889.68, primarily the contract retentions.
However, the day before this last insurance certificate was issued, MGS defaulted on its loan. Allegedly, the late construction was a major factor in the default. Home notified HUD of its intention to assign the mortgage to HUD and receive insurance benefits. The assignment was executed October 27,1972, and it transferred all Home’s interest in the project to the Secretary of HUD. On instructions from HUD, Home had reduced the principal amount of the loan by the amount of funds not disbursed, including the contract retentions, before the assignment. The mortgage HUD was assigned therefore, did not include the retentions.
MGS brought suit against Burnett in California Superior Court for either the damages from the late construction or enforcement of an arbitral award for those damages. Burnett counter-claimed for the contract retentions, and cross-complained against Home, HUD, FHA, and the Secretary. The action was removed to the district court pursuant to
II.
The issues presented by this appeal are primarily jurisdictional. In order to decide
In order to understand the jurisdictional problems presented, it is necessary to analyze Burnett’s claims. It should be stressed at the outset that Burnett seeks money damages only, specifically the amounts alleged to be due under the construction contract. Burnett offers several theories for its recovery of this money. Burnett claims to be a third party beneficiary of both the Building Loan Agreement and the Mortgagor’s Agreement, to have an equitable lien on the undisbursed mortgage proceeds, and to be entitled to payment as a completing surety. Burnett also argues that the Secretary is obligated to pay Burnett under provisions of the National Housing Act,
III.
With respect to the statutory theory, it is clear that the district court had jurisdiction. If this part of the suit had been filed in the district court as a separate action, the district court would have had jurisdiction under
The Square was built pursuant to § 236 of the National Housing Act
Under the National Housing Act, the Secretary assumes no obligation to any party involved in a mortgage transaction except the mortgagee. Compare, United States v. Neustadt,
Even if such a right existed, it is doubtful that Burnett could enforce it on the facts presented here. The Square was complete before the Secretary acquired the mortgage. As we read
IY.
The contract theories present difficult jurisdictional problems. These difficulties arise because two separate distinctions must be made, and are often confused in the case
In addition to distinguishing between a grant of jurisdiction and a waiver of sovereign immunity, a distinction must also be made between suits against the United States and suits against the federal defendants. This distinction is required by the Supreme Court’s analysis in FHA, Region 4 v. Burr,
In FHA, Region 4 v. Burr, supra, the Court held that the sue or be sued clause (presently
Two possible sources for such funds have been suggested. One is the Special Risk Insurance Fund established by
A second possible source of funds is the undistributed mortgage proceeds. There clearly was a time when these proceeds were within the reach of the federal defendants. The Secretary could have instructed Home not to reduce the principal of the mortgage by the undisbursed amounts and could have taken assignment of those amounts as well as the mortgage. However, the Secretary chose not to act in this fashion. From the time the Secretary took assignment of the mortgage, the undisbursed proceeds ceased to exist as a separate, identifiable fund. If Burnett prevails on its claims that part of the undisbursed proceeds should have been paid to it, the recovery must come from the treasury.
We are aware of opinions holding that undisbursed mortgage proceeds do constitute a separate fund. See, e. g., Bennett Construction Co., Inc. v. Allen Gardens, Inc.,
It has been suggested that the Tucker Act is not an exclusive grant of jurisdiction, but merely a conditional waiver of sovereign immunity. If another waiver of immunity can be found, and some other basis for jurisdiction exists, the district court may properly hear the case. Several recent cases have found jurisdiction in the district court, on a variety of theories. See, e. g., Bor-Son Building Corp. v. Heller,
Alternative sources of jurisdiction are relevant only if there is an alternative waiver of sovereign immunity. The above cited cases, and Burnett in this case, all point to
The above discussion applies to the federal defendants, not Home. Home is neither an agency of the federal government nor entitled to invoke sovereign immunity doctrines on other grounds. However, the district court was correct in granting summary judgment in favor of Home. All Home’s rights and interests arising under this mortgage have been assigned to the Secretary,
VI.
The finding that the district court lacked jurisdiction in this case does not end the matter. Under
AFFIRMED and REMANDED.
Notes
. A default judgment had been entered against MGS earlier. Those parties referred to throughout this opinion as the federal defendants are the FHA, HUD, and the Secretary of HUD, acting in her official capacity.
. We emphasize again that Burnett requests monetary relief only. If Burnett sought injunctive or declaratory relief as well, the distinction between suit against the Secretary and suit against the United States would have to be drawn differently.
. It has been suggested that this case should be remanded so that the district court could determine if separate funds exist. We reject this course of action because it is clear that there are no separate funds among the possible sources argued below, and to permit the parties
Dissenting Opinion
dissenting.
I respectfully disagree. I would find that jurisdiction existed pursuant to
I find no merit to the contention that this litigation would involve a suit against the United States in derogation of its sovereign immunity. Home Savings and Loan Association is the mortgagee here or the lender of the funds. It is not a government entity. Burnett Construction Company is the prime contractor. Neither of them is subject to a claim that a suit against one or both of them violates the doctrine of sovereign immunity. Home Savings and Loan Association not only supports jurisdiction by reason of its relationship to the governmental entities but also by reason of the special contractual relationship it insisted on apart from and beyond the HUD contractual relationship to which it was a party.
On the merits, the general contractor has gone ahead and completed the project using its own funds to do so. It now faces a loss of those funds while Home Savings and Loan Association and the governmental entities obtain the project completed at the builder’s expense. Trans-Bay Engineers & Builders, Inc. v. Hills, supra.
I would hold that Burnett Construction Company is entitled to recover all of the retained funds together with any funds representing progress payments due and unpaid. I would reverse and remand for a determination of those amounts.