MAPP CONSTRUCTION, LLC, Plaintiff-Appellant v. M&R DRYWALL, INC., Defendant-Appellee.
No. 08-30420
United States Court of Appeals, Fifth Circuit.
Sept. 24, 2008.
294 Fed. Appx. 89
Summary Calendar.
Michael J. Remondet, Jr., Jeansonne & Remondet, Lafayette, LA, for Defendant-Appellee.
Before JOLLY, BENAVIDES, and HAYNES, Circuit Judges.
PER CURIAM:*
Appellant MAPP Construction, LLC (“MAPP“) appeals the district court‘s dismissal of this case for lack of jurisdiction. For the following reasons, we AFFIRM.
I.
On August 21, 2003, MAPP contracted with Southgate Residential Towers, LLC (“Southgate“) to construct a large-scale apartment and condominium complex in Baton Rouge called Southgate Towers. The contract between Southgate and MAPP states that any dispute between the parties arising out of the construction of the towers will be subject to arbitration.
MAPP subcontracted with Appellee M&R Drywall, Inc. (“M&R“) to perform stucco and sheet-rock work on the Southgate Towers project. The subcontract contained a clause that MAPP contends binds M&R to arbitrate any disputes arising out of the subcontract. Appellee M&R filed suit against Appellant MAPP in Louisiana state court, alleging breach of contract. That case was consolidated with a lawsuit by Southgate against MAPP. MAPP filed a “Motion to Stay, and Order Directing the Parties to Arbitrate” in the consolidated state court litigation and invoked the Louisiana Arbitration Act. The trial court denied MAPP‘s motion and concluded that the contractual provisions regarding arbitration did not bind M&R to submit disputes with MAPP to arbitration.
Appellant MAPP sought review of the trial court‘s decision by the Louisiana First Circuit Court of Appeal. That court denied the writ, finding no error in the trial court‘s conclusion that the contractual provisions regarding arbitration are ambiguous. The Louisiana Supreme Court denied MAPP‘s application for a supervisory writ. After the denial of its appeals, MAPP brought suit in federal district court, again asserting that M&R was bound to arbitrate. MAPP contended that M&R was bound under the provisions of the contract as interpreted under the Federal Arbitration Act (“FAA“). The district court dismissed the case for lack of jurisdiction, invoking the Rooker-Feldman doctrine, which prevents the federal district court from reviewing the final judgment of a state court. This appeal followed.
II.
The district court rightfully dismissed the case for lack of jurisdiction.
The Louisiana state court issued a final ruling on the issue of whether M&R is bound to arbitrate by the subcontract. Appellant argues that Rooker-Feldman does not bar the instant action because consideration of its federal petition would not require the federal district court to engage in direct review of the state court order. Appellant claims to assert an independent federal claim based on the
MAPP‘s claims under the
Appellant‘s contention that the federal district court has exclusive jurisdiction to hear his
At bottom, Appellant petitioned the district court to do exactly what Rooker-Feldman aims to prevent, entertain appellate review of a state judgment in a United States district court. Accordingly, we find that the district court properly determined that it lacked jurisdiction over Appellant‘s claim.
AFFIRMED.
