Maplevale Builders, LLC v. Town of DanvilleMaplevale Builders, LLC v. Town of Danville
Lead Opinion
The respondent, Town of Danville (Town), appeals an order of the Superior Court (.McHugh, J.) abating “land use change tax” (LUCT) assessments issued to the petitioners, Maplevale Builders, LLC (Maplevale), Hoyt Real Estate Trust (Hoyt), and John H. and Maryann Manning, on the basis that the LUCT bills were untimely under
The following facts are supported by the record or are otherwise undisputed. In 2008, Hoyt appeared before the Danville Planning Board (Planning Board) seeking approval of a fifteen-lot residential subdivision. At that time, the parcel on which Hoyt sought to construct the subdivision qualified for current use taxation, see
On January 28, 2010, Hoyt received a certificate of registration for the subdivision from the Attorney General’s Office. See
On January 24, 2011, Maplevale petitioned the superior court to abate the June 2010 LUCT bills, see
Following trial, the trial court ruled that because all of the LUCT bills were untimely, the assessments could not be imposed. It found that by April 23,2009, all of the subdivision lots had “changed in use” because, as of that date, the Planning Board had granted final subdivision approval and the road had been completed. Accordingly, because the LUCT bills were not issued within the twelve-month statutory period, the Town was prohibited from imposing the assessments under RSA chapter 79-A. See
The Town first argues that the trial court erred in ruling that the lots had “changed in use” as of April 23, 2009. This presents an issue of statutory construction. See Formula Dev. Corp. v. Town of Chester,
RSA chapter 79-A reflects the legislature’s determination that it is in the public interest “to encourage the preservation of open space” and “to prevent the loss of open space due to property taxation at values incompatible with open space usage.”
To determine when action by an owner of a parcel has caused the parcel to change in use, we look to
The trial court applied the version of
When a road is constructed or other utilities installed pursuant to a development plan which has received all necessary local, state or federal approvals, all lots or building sites, including roads and utilities, shown on the plan and served by such road or utilities shall be considered changed in use, with the exception of any lot or site, or combination of adjacent lots or sites under the same ownership, large enough to remain qualified for current .use assessment under the completed development plan ....
The parties dispute the meaning of this exception. The Town argues that the exception allows it to issue LUCT bills on a lot-by-lot basis when disqualifying events (ie., physical changes) occur to each individual lot. This interpretation is supported by our precedent. In Van Lunen, we held that this version of
The petitioners argue, on the other hand, that the exception does not support a lot-by-lot assessment. They cite the concurring opinion in Formula Dev. Corp., which opined that “our statutory interpretation in Appeal of Estate of Van Lunen was incorrect. There is nothing in the plain language of
If the completed development plan contemplates that there will be undeveloped adjacent lots or sites that will be large enough to qualify for current use assessment, then these undeveloped adjacent lots or sites remain in current use. However, even if the completed development plan contemplates that there will be such undeveloped adjacent lots, the other lots serviced by the road or utilities still come out all at once.
Id. at 185-86.
In Van Lunen, we interpreted the statute at issue to allow for a lot-by-lot determination. See Van Lunen,
(1) whether the rule has proven to be intolerable simply by defying practical workability; (2) whether the rule is subject to a kind of reliance that would lend a special hardship to the consequence of overruling; (3) whether related principles of law have so far developed as to have left the old rule no more than a remnant of abandoned doctrine; and (4) whether facts have so changed, or come to be seen so differently, as to have robbed the old rule of significant application or justification.
Id. Having failed to brief any of the four stare decisis factors, the petitioners have not persuaded us that our decision in Van Lunen must be overruled. Cf. id.
Further, to the extent that the concurring opinion in Formula Dev. Corp. created any doubt as to the proper interpretation of
Viewing the trial court’s decision in light of Van Lunen, we conclude that it erred in ruling that all of the lots of the subdivision changed in use on April 23,2009, when the Planning Board granted final subdivision approval and the road had been completed. Under
Instead, the Town is “entitled to impose the [LUCT] on a lot-by-lot basis as disqualifying events occur[ ] for each individual lot,” so long as the conditions under
With respect to the lots included in the June 2010 LUCT bills, the Town requests that we “hold that the Town mailed the LUCT bills in a timely fashion” because Hoyt conceded in its original petition that a change in use occurred on March 6, 2010. However, “parties may not have judicial review of matters not raised in the forum of trial.” 74 Cox St. v. City of Nashua,
The Town next argues that the trial court erred by applying the incorrect version of
The determination of which version applies is relevant for the following reason. The trial court ruled that the subdivision lots had changed in use as of April 23, 2009. It then applied the twelve-month limitations period and concluded that because the Town failed to issue the LUCT bills before April 23, 2010, they were untimely. However, if the eighteen-month limitation period applies, the Town would have had until October 23,2010, to issue the LUCT bills; thus, the June 2010 LUCT bills would have been timely even under the April 23,2009 change in use date. Although we have vacated the trial court’s decision which applied the April 23,2009 change in use date, we nonetheless address the issue as to which version of the statute applies, as it “may arise on remand and . . . [the] parties discuss it in their briefs.” George v. Al Hoyt & Sons, Inc.,
The trial court did not apply the amended version of
When engaging in an Article 23 analysis, we distinguish new laws that affect substantive rights and liabilities from those that solely affect procedures or remedies enforcing those rights. In the Matter of Goldman & Elliott,
Here, as of the effective date of the amendment — April 1, 2010 — the twelve-month limitations period had not yet expired as to any notice or discovery of change in use that occurred on April 23, 2009; thus, the petitioners had no “vested right” to rely on that limitations period. See Gould,
As a final matter, the Town argues that the “certificate of registration” from the Attorney General’s Office constitutes a “necessary state approval” pursuant to
Vacated and remanded.
Concurrence Opinion
concurring specially. I join the opinion of the court except insofar as it elucidates the factors that may be considered in determining whether to overrule precedent. See ante at 105. Although my view as to the considerations that properly may warrant overruling precedent is broader than that espoused by the majority, see State v. Quintero,
Notes
Interestingly, the two justices who joined in the special concurrence in Formula Development Corp. also formed part of the court’s majority in Quintero. Yet, contrary to the narrow “four factor only” test for overruling precedent relied on in Quintero, in Formula Development Corp. these justices asserted that Van Lunen should be overruled in part merely because it was decided incorrectly, and without ever mentioning the four factor test. See Formula Development Corp.,