3 Ind. 148 | Ind. | 1851
McCoy sued Manville before a justice of the peace, on the following account:
“ For plastering 700 yards for the defendant by the plaintiff upon the defendant’s brick dwelling-house in Milton township, Jefferson county, Indiana, in the fall of the year 1848; said work including lathing, but not materials, and being worth per yard 12£ cents, which will make the damages hereby demanded $87 50.”
The cause went by appeal to the Circuit Court, was there tried by a jury upon the general issue, and the plaintiff obtained a verdict for a fraction over 25 dollars. A motion for a new trial being overruled, judgment was entered on the verdict. The evidence and instructions are upon the record. The evidence tends to establish that the plastering sued for was done under a special contract, by which McCoy was to plaster Manville’’s house at a certain price per yard, and within a certain time; that he failed to complete the work within the time; that Man-ville procured another person to complete it; and that the part performed by McCoy was not done in a workmanlike manner; but no amount of damage accruing to Manville from McCoy's failure to complete the work in time is shown, nor does it appear that Manville paid any higher price for the completion of the job than he had agreed to pay McCoy for the same work.
The Court instructed the jury that “ if they found there was a special contract between the parties, by which McCoy agreed to plaster Manville’s house upon certain terms, and within a specified, or a reasonable time, and in a workmanlike manner, to be paid for on the completion of the job; and that, after part performance, McCoy failed or refused to perform the balance within the time, or in the manner agreed upon, without any fault or default of Manville, and the work done, or part performance, was of such a nature that Manville was necessarily compelled to accept it, McCoy is not entitled to recover for the work done; but if the work done was of such a nature that Manville could accept or reject it at his option, and he chose to accept it, McCoy is entitled to recover for the reasonable value of the work.”
Upon the evidence, .conflicting as it is, we cannot disturb the judgment below.
This principle is laid down by the attorney for the plaintiff in error, viz: that where a mechanic undertakes to do a job of work, the proprietor furnishing the materials, he is bound to make a good job or get no pay, even though the materials be of so inferior a description that good
We think the doctrine contended for, as a general proposition, is not correct; though it may be in some cases. If the proprietor furnished the materials under the direction, and upon the judgment of, the mechanic, and the work completed from them was, on the whole, of no advantage to him, perhaps the mechanic should receive no pay, because it would be his own fault that he used poor materials. But if the proprietor did not so furnish them, but did it upon his own judgment, and directed the mechanic to use them at all events, it would not be the fault of the latter, if, from bad materials, the work, when done, was of an inferior quality. In this case, it is not shown that the materials were used upon the judgment of the plasterer, and there is some evidence tending to show the contrary.
We see no error in this case
The judgment is affirmed, with 2 per cent. damages and costs.
See McKinney v. Springer, ante, p. 59.—Epperly v. Bailey, ante, p. 72.—Heaston v. Colgrove, post.