114 N.Y. 331 | NY | 1889
I think the defendant’s exception was well taken to the submission to the jury of the question of interest upon the amount of damages they should find against the defendant. The action was to recover for breach of contract. In such cases whether interest is recoverable does not rest in the discretion of the jury, but it is a question of law for the court, while in actions sounding in tort when the recovery of interest is permissible "it is, with some exceptions, a question for the jury. (Duryee v. Mayor, etc., 96 N. Y. 478.) The rule upon the subject may appear to have been involved in some uncertainty, but now it seems to be reasonably well defined in this state. In McMaster v. State (108 N. Y. 542), the claim was for damages founded upon a breach of contract for the supply of materials for and services in the construction of a public building. The damages, resulted from the refusal of the state to permit the contractor to proceed with the work to its completion, as provided by the contract. And such damages consisted of a loss of profits, which would have been realized by performance of the work at the contract-price. The court held that interest was not allowable even from the time of the commencement of the action or proceeding, because the claim was unliquidated, and a there was no possible way for the state to adjust the same and ascertain the amount which it was liable to pay.” And reference was made to White v. Miller (71 N. Y. 118; 78 id. 393). That was an action to recover damages resulting from breach of warranty upon sale of a quantity of cabbage seed. The referee on the first trial allowed interest upon the damages from the time the crop would have been harvested. The court held that was error, for the reason that “ the demand was unliquidated and that the amount could not be determined by computation simply, or reference to market values.” (71 N. Y. 134.) On the next trial the plaintiffs were allowed to recover interest
In McMahon v. New York and Erie Railroad Company (20 N. Y. 463), the action was to recover for work performed and materials furnished by the plaintiff in construction of the defendant’s road. The defendant had refused to have measurements made by its engineer, which was a condition precedent to payment. The court referred to the doctrine of Van Rensselaer v. Jewett, and by Selden, J., said that the court there went as far as was reasonable to go, and held that interest was allowable upon the ground that the defendant was in default for not having taken the requisite steps to ascertain the amount of the debt. In McCollum v. Seward (62 N. Y. 316), and Mercer v. Vose (67 N. Y. 56), the actions were to recover the amount due for services upon a quantum meruit. The claims were unliquidated, and the recovery of interest from the time of the commencement of the action was sustained. The former of the last two cases was decided upon authorities there cited, and was followed by the other. The doctrine of that line of . cases is, that in actions for services rendered or goods sold, etc., when the debtor is in default for not paying pursuant to his contract, the creditor is entitled to interest by way of damages. (Newell v. Wheeler, 36 N. Y. 244; Mygatt v. Wilcox, 45 id. 306.) And that is upon the theory that the amount may be known or ascertained and computed, actually or approximately, by reference to market-values. (Sipperly v. Stewart, 50 Barb. 62; Van Rensselaer v. Jewett, 2 N. Y. 135, 140; De Lavallette v. Wendt, 75 id. 579.) There may be cases, from the nature of which it appears that this cannot be done, to which the rule allowing interest is not applicable. (Smith v. Velie, 60 N. Y. 106; De Witt v. De Witt, 46 Hun, 258.) And, so far as I have observed, it has not been extended to actions to recover unliquidated damages for breach of contract, unless
My conclusion is that the plaintiff was erroneously allowed to recover interest, and that the judgment should be modified accordingly.
This action was brought to recover damages, on the part of the plaintiff and respondent, against the defendant, the Hew York Central & Hudson Rivei Railroad Company, appellant, for breach of a contract made. and entered into between them in respect to the building of an elevator in the city of Hew York. There are two separate and independent stipulations in the contract for the breach of each of which plaintiff seeks to recover damages. The instrument provided, among other things, that Grill & Mansfield should furnish materials, j>erform the work in erecting the superstructure of the elevator over the waters, upon piers in the Hudson river between Sixtieth and Sixty-first streets 'in the city of Hew York, and should finish the same within five months from the time of the commencement of the work, 'and should receive as their compensation therefor the sum of •$331,500, and the further sum of $500 per day for each day : less than that occupied in its construction.
In respect to the time of commencing the work it was provided, “ that said parties of the first part hereby further agree ' to commence the erection of the elevator within five days after notice of 'the engineer that the foundations are ready, and complete the same ready for use, of all the lofting elevators within five months thereafter.” The plaintiff alleges that he performed the work within the time by about thirty days, and was thus entitled to receive under the contract $500 a day for the thirty dáys, amounting to $15,000. The plaintiff also claims to recover of the defendant damages for not having the foundation ready for the erection of the elevator within five days of the time when defendant, through its engineer,
The case has been twice tried at Circuit and has been to the General Term three times, and to the Court of Appeals once. On the appeal to the Court of Appeals that court laid down certain principles upon which plaintiff’s rights depend under the contract and its several provisions, and is to be found in 102 Hew York, page 205.
Upon that appeal it -was held by this court, in substance, that the two stipulations contained in the agreement for breach of which the action is brought were independent of each other, and that the plaintiff could, upon proper proof, recover the $500 jper diem for the time that was unexpired for the completion of the structure; and that, also, upon proper proof he was entitled to recover any damage which he sustained by reason of the extra work and moneys paid out in the doing of the work or that portion of the work which he did before the foundations were in the condition required to be by the contract.
The case, of course, must be disposed of upon this appeal in accordance with the principles laid down in the former appeal, and it is not perceived, upon an examination of the case as now presented, but that the last trial was conducted in accordance with the principles thus laid down by the court on the former appeal. Hence we perceive no error in those respects. The question in regard to the rule of damages, so far as interest was concerned, at least upon the sums which plaintiff might prove and become entitled to under the rulings on the former appeal, were not disposed of by the court on the former appeal, but were left to be raised upon such evidence and findings as should be had upon a subsequent trial. Upon the last trial the plaintiff proved, and the jury found, upon sufficient proof, in our judgment, that the plaintiff was entitled to recover $500 per day for the thirty days between the commencement of the work, within which the work could have been done if tliefoun
According to my apprehension of the case upon this appeal, the only question for our consideration remaining is, whether or not the plaintiff is entitled to recover interest upon these two sums as found by the jury, or upon either of them, as damages. The general rule, no doubt, is, that interest cannot be allowed upon claims for unliquidated damages, but by legislation in some instances or, in respect to a certain class of actions and by decisions of courts, cases of unliquidated damages, in which interest will not be allowed, are becoming more rare. We think the rule still is, that, where the- damages are entirely unliquidated, and where the jury have to take numerous elements of uncertainty and doubt and speculation into account in rendering a verdict, the old rule still applies. But where the elements which enter into and form a part of the considerations which the jury are to determine upon in respect to the amount of damages are simple and reasonably certain, the tendency of the decisions of the court is in the direction of an extension of the rule in various cases of unliquidated damages where formerly the rule of allowing interest would not be permitted. It is done for the purpose of making a party who has sustained damage by reason of the failure of another party to perform his agreement, some compensation or some mderrmifry for the loss which he has sustained. Some cases have left this question doubtful, whether in the cases where a party may be entitled to interest the jury may find that interest as damages in their discretion, or whether the court, as matter of law, may direct, if they find a verdict for a party, to also include in or to add to the amount of damages the interest which has accrued from the time of the commencement of the suit, or from some former time when the cause of action accrued, or a demand of payment was made. Whether
The question, then, recurs whether or not the plaintiff was entitled to interest as matter of law or have it submitted to the discretion of the jury whether interest should have been allowed upon these two claims for damages as found by the jury. There would not seem to be many elements of uncertainty or speculation in the claim of $500 a day for thirty days. The only thing the jury had to do in respect to that claim was, under the charge of the court and upon the whole evidence in the case, to determine how many days short of the five months the plaintiff did complete this elevator in; and, further, how many other days less than five months he might have completed the contract in if the foundations had been ready as agreed.
The amount per day was fixed by the agreement of the parties at $500. Hence to ascertain the amount the plaintiff was entitled to in this respect, was simply to take the number of days which were and might have been saved from the' whole period of five months in the construction of the building, which was thirty (as found by the jury), and multiply that thirty by five hundred, and to cast the interest upon that product from the commencement of the suit until the day of the trial. That certainly was not a difficult thing to do, and there was no element of uncertainty about it except the number of days they should determine, from the evidence, had been saved from the five months. The other claim, which was fixed by the verdict of the jury at $802, did not contain a great many elements of uncertainty, for every element could be established quite accurately and plainly by the evidence in the
It seems to me that there are many cases reported in which interest from the commencement of the action has been allowed and approved by the court, where the elements of uncertainty were much more numerous and of much more difficult, ascertainment.
The cases referred to and relied upon by appellant’s counsel were cases in 108 New York, 557, and in White v. Miller (71 N. Y. 118, and the same case cited again at 78 N. Y. 393). In those cases interest was not allowed, for the reason that the demand was unliquidated, and was so dependent upon various uncertain and speculative elements that the court was unwilling to allow it.
The latter case was an action to recover damages for a breach of warranty in the sale of cabbage seeds. They had been sold and represented upon the sale to have been seed of a particular kind, and that they would produce a crop of a certain character. It turned out that the seeds were defective, of a different kind, and did not produce the crop which the party sought to raise. The plaintiff sought, in that action, to recover the difference in the value of the crop as raised from imperfect seed of a different character from the value of a crop, such as would be produced from the seed of another
We have carefully studied the vei-y able brief of appellant’s counsel, and we have been unable to perceive, either in the reception or rejection of testimony, or in the charge to the jury, any violation of well-settled principles in this class of cases or any departure from the principles laid down in this case on the former appeal in the able opinion of Judge Rug-er in this court. We have also looked with some degree of care at the exceptions to evidence and to the judge’s charge, and we do not perceive any error that should justify another trial of this action.
I think that the allowance of interest from the time of the commencement of the action to the day of the trial was proper, and the judgment should, therefore, be affirmed, with costs.
All concur with 'Potter, J., except upon the question of interest, upon which question all concur with Bradley, J., except Potter, J.
Judgment modified by striking out allowance for interest.
Upon a subsequent motion for reargument the following opinion was handed down:
The first review in this court was of a judgment of the General Term affirming judgment entered upon dismissal of the complaint directed by the court upon the trial. And upon that trial the evidence offered by the plaintiff to prove damages resulting from the alleged breach of the contract was excluded. The court on such review having determined that the contract required that the foundations be so far completed as to enable the contractors to prosecute the work to the utmost advantage and economy before the notice should be given by the defendant’s engineer, held that the giving such notice before that time was a breach of the contract; and as the plaintiff and his associate, without waiver of any rights in
First. That the right to that allowance rested upon a mere condition dependent upon performance within the stipulated time, which could be set in motion only by the notice of the engineer, and must terminate with the expiration of such time from that when the notice was given; and that such promise of the defendant, when made, was merely an offer without the support of any consideration.
. Second. That the per diem allowance so provided for, dependent upon such event, did not constitute prospective profits ; and founded upon the breach of the contract did not come within the meaning of gains prevented. We think the agreement to pay this per diem amount may be treated as made with a'view to increased compensation, in the event there mentioned, for the work which the contractors undertook to perform for the defendant, as represented by the provision that “ in consideration of the faithful performance of all the covenants and agreements herein contained by the parties of the first part to this agreement, the said party of the second part hereby agrees to .pay to the said parties of the first
It is deemed, unnecessary to further extend the expression of the considerations which led to the result given to the appeal when it was determined.
The motion for reargument should be denied.
All concur.
Motion denied.