Manning v. School District No. 6

124 Wis. 84 | Wis. | 1905

Maeshalu, J.

There is hardly room for argument but that tbe breaches of contract pleaded by appellant, if established by evidence, were sufficient to modify or entirely defeat respondent’s claim, and perhaps call for a judgment against him. Therefore, they were pleadable as a defense and a counterclaim as well. Heckman v. Swartz, 55 Wis. 113, 12 N. W. 439; Kauhauna E. L. Co. v. Kauhauna, 114 Wis. 327, 343, 89 N. W. 542. We shall assume tbe learned circuit judge appreciated that and grounded tbe decision that no counterclaim was stated, not upon tbe theory that facts sufficient to support one were not disclosed, but that they were not so stated as to comply witb tbe statutory requisites on the subject. It really makes no difference whether tbe breaches of contract were stated as a defense only, or as a defense and counterclaim, so far as reducing respondent’s claim is concerned, if, as alleged, be did not substantially perform bis contract. In that event be could only, at best, recover tbe reasonable value of bis work and material, on a proper basis, wbicb were appropriated by appellant. If be substantially *90but not fully complied with bis contract, be could only properly recover tbe contract price, less sucb deductions as -would,, under proper rules for measuring tbe damages caused thereby, make tbe same good to appellant, — and no counterclaim was-necessary to secure sucb deductions, tbougb a claim therefor-was pleadable as one. In short, all tbe breaches of contract alleged in tbe answer to tbe extent of defeating respondent’s claim were pleadable as defensive matters, and were also pleadable as a counterclaim compelling respondent to confess or deny tbe same, if appellant so desired.

Do those matters disclosed by. tbe answer, which were-pleadable as a counterclaim, constitute one under tbe circumstances ? We apprehend tbe court decided that in the negative upon tbe theory that in tbe paragraph of tbe answer suggesting the subject of counterclaim no breaches of contract were alleged expressly or by reference to thg preceding allegations where sucb breaches were set forth as defensive matters.

In seeking out what tbe pleader intended we must bear in-mind that “in tbe construction of a pleading for tbe purpose-of determining its effect its allegations shall be liberally construed, with a view to substantial justice between the parties.” Sec. 2668, Stats. 1898. “Every reasonable intendment and presumption is to be made in favor of tbe pleading.” Morse v. Gilman, 16 Wis. 504. No pleading is to be condemned for want of an allegation therein of any essential fact which one can discover tbe pleader claimed to exist and intended to state therein, if the same can be read therefrom by reasonable inference, “though its allegations be in form uncertain, incomplete, and defective.” Miller v. Bayer, 94 Wis. 123, 68 N. W. 869; Ean v. C., M. & St. P. R. Co. 95 Wis. 69, 69 N. W. 991. For example, a complaint in a case to-recover on contract is to be viewed as if it merely stated the-making thereof, compliance therewith, and the amount due-thereon, without any particulars. Contrary to the common-*91law rule, it is to be construed most strongly in favor of instead of against a pleader in case of a formal demurrer thereto (Morse v. Gilman, supra), and if the objection be taken for insufficiency other than by such a demurrer, for the purpose of sustaining it, it is to be viewed with still greater liberality (Hazleton v. Union Bank, 32 Wis. 34; Teetshorn v. Hull, 30 Wis. 162).

Much has been said on the subject under discussion, particularly in recent years, to the end that the great change wrought by the Code in the manner of construing pleadings might be fully appreciated. Eor sufficiency of facts pleaded the Code looks to the substance, not to form. Its basic principle is that the administration of justice should not be embarrassed by technicalities, strict rules of construction, and useless forms. In harmony with that the proceedings mapped out for litigants to follow were by the architects of the Code-made as simple and plain as practicable; , Then they provided that every pleading shall be construed as sufficiently stating everything necessary to the cause of action or defense intended, which can be found alleged therein, expressly or inferentially, looking at the language thereof in its full reasonable scope; and it was further provided that all errors in proceedings, not prejudicial, shall be regarded as immaterial. Sec. 2829, Stats. 1898. This rule was deduced in Kliefoth v. Northwestern I. Co. 98 Wis. 495, 74 N. W. 356, from previous decisions on the subject;

“In determining whether a complaint states a cause of action the question is not whether the plaintiff used the most appropriate language in stating his case, but whether the language used will permit a construction which will sustain the-pleading, and to that end such effect should be given to its allegations as will support rather than defeat it, if that can be done without adding, by way of construction, material words not necessarily implied, or giving to the language used a meaning that cannot be reasonably attributed to it.”

It is not infrequently that mere indefiniteness in a pleading. *92.is challenged as insufficiency. The pleading may be indefinite and open to a motion on that ground, and yet its allegations be clearly susceptible of a reasonable construction sustaining it, constituting a complete answer to a general demurrer. Miles v. Mut. R. F. L. Asso. 108 Wis. 421, 427, 84 N. W. 159:

Now there can be no reasonable doubt but that appellant’s ■counsel intended to plead the breaches of contract and conse■quences thereof stated in the defensive part of the answer as part of the statement of a counterclaim. This language is unmistakable: The cost of completing the plant, “in addition .to the sum of five hundred and seventy-five dollars already reserved by the defendant, will amount to five hundred dollars, and defendant pleads the same as a counterclaim in this action; the defendant denies each and every allegation of plaintiff’s complaint not hereinbefore admitted and prays judgment of this court for the said sum of five hundred dollars.” True, the particulars as regards the departure from the contract were not stated in that part of the answer specially devoted to the counterclaim. But if they were necessary to be mentioned, to pass the test of sufficiency, they were all stated in detail prior thereto, followed by an allegation that they were pleaded as a defense, which was immediately followed by the language we have quoted commencing with the words “Defendant further says that to make such heating plant adequate,” etc. The most formal way was for the pleader to state tjie breaches as a defense and then restate them as a part of the counterclaim. A good substitute for such a restatement is to refer to the prior allegations in a general way as to be deemed repeated as a part of the cause of action constituting the counterclaim. However, any reasonable indication that the breaches pleaded as a defense are intended to be also stated by way of counterclaim, under the liberal rules we have mentioned, would justify their being so regarded.

*93We are not unmindful of the statement in Rood v. Taft, 94 Wis. 380, 384, 69 N. W. 183, that without some appropriate-words in that part of the answer devoted to the attempt to. state a counterclaim, referring to the allegations in the defensive portion and mating the same part of the statement' constituting the counterclaim, they cannot be so treated. The-court did not intend thereby to declare that an express reference in the counterclaim to such allegations incorporating them into the statement of the counterclaim is absolutely essential. Such a doctrine would invade the statutory rule for the construction of pleadings to which we have referred. There must be an appropriate reference, as said, but it need not be an express reference. If defensive allegations can be reasonably deemed restated as a part of the cause of action constituting the counterclaim, that is sufficient. We shall not-undertake to analyze or justify what was said in Rood v. Taft with reference to the facts of that case. It is sufficient to say that the opinion should not be construed as holding that. nothing short of words of express reference to defensive matters in the answer unmistakably incorporating the same into that part of the pleading devoted to the counterclaim will have that effect, irrespective of whether the plaintiff read the-pleading as containing a counterclaim and replied thereto.

Here, as we have indicated, defendant alleged breaches of' contract, following the same with an allegation that they were-pleaded as a defense, following that by a paragraph denying all allegations of the complaint not theretofore admitted, and alleging that it would require expenditures to the amount off $1,075 to complete the contract, which, not only by reasonable but by necessary inference, referred to the departures from the contract before, alleged. That was coupled with language to the effect that the situation rendering the expenditure of the sum mentioned necessary to complete the contracff was pleaded as a counterclaim.

There is nothing in Brauchle v. Nothhelfer, 107 Wis. 457, *9483 N. W. 653, inconsistent with, the foregoing. In that case there was no allegation in the body of the complaint indicating a purpose to state a counterclaim.

In giving to a pleading, as a whole, the most favorable construction it will reasonably bear, to the end that the evident purpose of the pleader to state a counterclaim may not be defeated, some significance should be ascribed to -the circumstance, when it exists, that all defects were waived by plaintiff, so far as it was competent for him to do so, by replying. Perhaps such circumstance was not given proper weight in Hood v. Taft. In Irvin v. Smith, 60 Wis. 172, 18 N. W. 722, facts not denominated as a counterclaim, but followed by a prayer for affirmative relief, regardless of the informalities, were held to contain one upon the plaintiff’s indicating that he so viewed the pleadings by replying thereto, and waived the defect. In Voechting v. Grau, 55 Wis. 312, 13 N. W. 230, it was said that the purpose of the statute requiring facts, relied upon as a counterclaim, to be pleaded as such, 'is to enable the plaintiff to know to a reasonable certainty -the pleader’s intention; that the reason of the statutory rule fails when the plaintiff is so satisfied, though the formal requirement is not complied with, and he acts accordingly by replying. To the same effect is Selleck v. Griswold, 49 Wis. 39, 5 N. W. 213.

The use of the above citations must not be construed as 'holding that a pleading not containing facts constituting and intended to be stated as a counterclaim should be held to state one because so viewed by the plaintiff, as indicated by his replying thereto, or for any other cause. The act of replying simply waives all mere formalities and uncertainties. The counterclaim, the same as a complaint, must include in some way a statement of facts constituting a cause of action in favor •of one party against the other. No fact which would be essential to a cause of action in a complaint can be properly omitted in stating the same cause in an answer, but the statement 'in the latter need not necessarily include a repetition of the *95facts alleged as defensive matter or in tbe complaint. If they are referred to expressly, or inferentially, so as to make reasonably clear the purpose of the pleader to rely upon them as a part of the counterclaim, that satisfies the test of sufficiency. In short, the same rules apply to one pleading as to the other.

In Cragin v. Lovell, 88 N. Y. 258, the rule was laid down thus:

“A separate defense may contain all the requisite allegations within itself to make it a perfect counterclaim, or it may refer to papers annexed, or to other parts of the answer, or to the complaint, and the matters thus referred to are just as much a part of the counterclaim as if written at length therein.”

That is very much the same rule as was stated in Hood v. Taft, 94 Wis. 380, 69 N. W. 183, but upon reading the opinion it will be seen that express reference to matters outside of that portion of the pleading devoted to the counterclaim but appearing in the pleading was not regarded as essential. The alleged defect in the counterclaim was in that it was not alleged that certain real estate was located in the state of Louisiana. The court referred to several circumstances as answering the objection, one being that it was alleged in the complaint that the land was located in Louisiana; that the answer drawn to meet that statement contained no denial thereof, which in effect admitted it and thereby incorporated the allegation in that regard into the answer. Other features of the pleading were mentioned as showing that the counterclaim, without any express mention of the fact, alleged that the realty was located in Louisiana.

Applying the foregoing to the case in hand, all matters necessary to the counterclaim not expressly stated in the paragraph devoted thereto, but otherwise appearing in the pleading, were, within the spirit of Rood v. Taft, supra, “by appropriate words of reference” incorporated into such counterclaim.

Erom the foregoing we may deduce this as a rule of plead*96ing: Matters once stated in a complaint or answer may be reasonably regarded as incorporated into tbat part of tbe answer apparently devoted to tbe statement of a counterclaim if referred to for tbat purpose, directly or circumstantially, and when tbe plaintiff by replying indicates tbat be considers them so incorporated, tbat view should prevail, unless tbe language of tbe counterclaim as a whole very clearly will not admit thereof.

Tbe evidence of a witness who fully qualified himself to-testify as an expert regarding tbe expenditure required to-mate tbe beating and ventilating plant comply with tbe contract was received, and at tbe close of the testimony was stricken out because tbe witness failed to state in detail the-particulars of tbe work which would necessitate such expenditure. Tbe theory of respondent’s counsel was tbat tbe evidence was incompetent because no foundation was laid therefor in tbe answer and tbe motion ruled on was made on tbat ground. Tbat was untenable, as we have seen, since a counterclaim was sufficiently pleaded. Tbe cost of making good tbe departure from tbe requirements of tbe contract to tbe extent of defeating plaintiff’s claim, was proper in any event, and tbe facts in tbat regard were pleaded as a defense. If, when tbe evidence of tbe expert was offered, upon a proper objection being made, tbe court in tbe exercise of its discretion bad excluded it until tbe witness first stated tbe particulars upon which be based bis conclusion, tbe ruling might pass without much criticism, but to receive tbe evidence and then strike it out, as was done at tbe close of defendant’s case, because upon tbe examination in chief tbe basic details were not given, although there was full unimproved opportunity afforded respondent on cross-examination to go into tbat subject, especially when no objection was made on tbat ground, is plainly error.

A witness was interrogated as to circumstances leading up to tbe contract, and tbe evidence in tbat regard was excluded. *97No reason is given why it was material, and we are unable to perceive any.

Complaint is made because a statement by an employee of respondent, wbo was present some of the time when the plant was being tested, as to whether it was then acting efficiently, was not permitted to be given in evidence. We assume the ruling was based on the theory that there was no satisfactory showing that the employee was authorized to represent respondent for the purpose of testing the capacity of the'plant. We see no good reason for overruling the trial court on the question of competency involved.

Written reports made.by the expert employed by appellant to examine the plant as regards whether it satisfied the contract, and which were sent to the respondent, when offered in evidence by appellant, were excluded. That ruling must be approved. Such reports were mere declarations in tire interest of appellant made out of court. At best they were mere hearsay.

A witness who kept a diary in which he noted down from day to day the state of the weather and was able thereby to testify positively as to the temperature at a time material to the case, but could not do so other than in connection with his knowledge that when he made the memorandum he recorded the truth of the matter, was not permitted to testify on the subject upon the theory that the governing rule is to the effect that a person cannot testify by the aid of a memorandum, unless after referring thereto he can recall to mind the fact and testify from present remembrance. This court has held otherwise on many occasions, in harmony with most if not all elementary authorities on the subject. Hill v. State, 17 Wis. 675, 679; Schettler v. Jones, 20 Wis. 417; Riggs v. Weise, 24 Wis. 545; Stubbings v. Dockery, 80 Wis. 618, 50 N. W. 775; Bourda v. Jones, 110 Wis. 52, 85 N. W. 671; Nehrling v. Herold Co. 112 Wis. 558, 88 N. W. 614; 1 Greenl. Evidence, § 437; Phillips, Evidence (3d ed.) § 411; *983 Jones, Evidence, §§ 877-886. In Schettler v. Jones, supra, the court, speaking by Dixon, C. J., said:

“We think the sounder and better rule to be, that if the witness can swear positively that the memoranda or entries were made according to the truth of the facts, and consequently that the facts did exist, that is sufficient, though they may not remain in his memory at the time he gives his testimony. He may testify from the entries, and when he does so he swears positively to the truth of the facts stated in them.”

True, the rule thus stated was not at the time of its declaration extended to a mere private memorandum, but there is no good reason for not so extending it, where the competency of the witness is clearly established by his positive testimony as to present recollection that when he made the memorandum it was in accordance with the truth as he then knew the fact to be, and so it was held in Bourda v. Jones, supra. The rule was there broadly stated thus:

“A witness, in testifying, may properly use a memorandum ' which he knew when made, or by subsequent verification thereof, to be correct, even though he does not possess present remembrance of the correctness of the matters referred to therein, after seeing the paper and examining it.”

Quite as broad language as that forms the text in 3 Jones, Evidence, at § 884. This is the language used there:

“It is now well settled that a memorandum or writing may be used by the witness, not only when he can swear from actual recollection, but in some cases where the witness, after referring to such writing, can swear to a fact, not because he remembered it, but because of his confidence in the correctness of the writing/'

Anri again at § 886, as regards the use of a memorandum as an independent instrument of evidence:

“Although it is clear that the document is not admissible as evidence when it so recalls the facts to the mind of the witness that he remembers them and can testify from his act*99ual recollection, it bas frequently been beld tbat another rule prevails when the witness, after examining tbe memorandum, com/mi testify to an existing knowledge of the fact, independently of the memorandum, but can testify that, at or about tbe time tbe writing was made, he lenew of its contents and of their truth or accuracy.”

'"^Complaint is made because tbe’ court not only refused to permit tbe witness to testify by tbe aid of bis memorandum, known by bim to bave been correctly made, since be bad no present recollection of tbe facts after examining tbe paper, but refused to permit tbe paper to be introduced in evidence. Tbe judicial idea was tbat tbe only permissible use of a memorandum is to refresh tbe memory of tbe witness. Respondent’s counsel suggested to tbe court tbat tbe inquiry should be restricted substantially to this: “Do you remember after looking at tbe memorandum,” etc. ? Tbat is clearly wrong, as we bave seen. Not only was it permissible for tbe witness to testify from tbe memorandum when the only remembrance be bad on tbe subject was tbat it was correctly made, but it was proper to receive tbe memorandum in evidence as part of tbe witness’s testimony. Bourda v. Jones, 110 Wis. 52, 85 N. W. 671; Nehrling v. Herold Co. 112 Wis. 558, 88 N. W. 614. Some authorities go further, bolding tbat in such circumstances as before suggested tbe memorandum may be used as an independent evidentiary instrument. Insurance Companies v. Weides, 14 Wall. 375; Kent v. Mason, 1 Ill. App. 466. This court bas adopted what may be called tbe middle course, tbe one supported, as it is believed, by tbe •great weight of authority. Mr. Jones in bis work on Evidence at § 886, speaking on tbe subject, says: “In such cases, both tbe testimony of tbe witness and tbe contents of tbe memoranda are beld admissible. The two are tbe equivalent of a present positive statement of tbe witness, affirming tbe truth of the contents of tbe memorandum.’ ” That language was fully indorsed in Nehrling v. Herold Co., supra:

*100“The rule is that a witness may refresh bis recollection from a memorandum made by himself or by others, if he saw the memorandum while the facts were still fresh in his memory, and if he then knew it to be correct. In .such case, if the witness cannot state the facts readily from personal recollection after using the memorandum, but can state that he knows the paper was correct when made, the paper itself may be put in evidence, and the statement of the witness and the contents of the paper together are equivalent to the present positive statement of the witness affirming the truth of the facts stated in the memorandum.”

Further complaint is made because the court refused to-permit proof of the reply of one of the teachers employed in the building to plaintiff’s inquiry as regards the temperature in her room when he claimed he was engaged in testing the plant. The conversation between plaintiff and the teacher, so far as testified to, was drawn out on cross-examination of' plaintiff. The reply of the teacher was excluded because the-conversation was not a proper subject for cross-examination. On that ground, if on no other, the ruling was correct.

The court instructed the jury that if plaintiff substantially complied with the contract he was entitled to recover of defendant the balance unpaid thereon. That is not the law. The proper rule is stated in Ashland L., S. & C. Co. v. Shores, 105 Wis. 122, 81 N. W. 136, in effect, thus: When a contract has not been fully, but has been substantially, performed, in that it has been in good faith complied with in all essentials to the full accomplishment of that which was contracted for (Manitowoc G. Co. Works v. Manitowoc G. Co. 120 Wis. 1, 97 N. W. 515), and the contract labor and material wrought into the property of the proprietor has been appropriated to the use intended, such contractor is entitled to recover the contract price, less such deductions therefrom as will make-good to the proprietor the imperfections in the work. Such equivalent for the imperfections and the substantially completed work are regarded as affording the proprietor the full *101performance of tbe contract to wbicb be is entitled. So far as tbe imperfections can be remedied without any great sacrifice of work and material wrought into tbe subject of the contract and tbe proprietor’s property, tbe contract price is to be reduced by so naucb as will measure tbe reasonable cost of applying suck remedy, and otherwise tbe contract price is to be rebated to tbe extent of tbe diminished value of tbe subject of the contract by reason of tbe defects. Tbe learned ■court’s idea that substantial performance calls for tbe full contract price is entirely wrong. One who contracts with another for tbe erection of any structure or tbe installation of a plant of any kind for a stipulated price is entitled to tbe full benefit thereof in consideration of rendering tbe full price therefor. If be only receives substantial performance, be is, of course, upon proper proof entitled to such rebate from tbe agreed price as will constitute a fair equivalent for tbe difference between such and full performance of tbe agreement, and in an action for such price tbe damages mentioned are properly pleadable, either as a matter of defense or as a counterclaim. Tbe very idea suggested by tbe term “substantial performance” is that tbe contractor has delivered something less than what be agreed to, and that tbe full consideration for tbe full price, according to tbe terms of tbe contract, being due to tbe proprietor as a matter of right, tbe courts must accord him a remedy wbicb, in some form, will secure to him that right.

Error is assigned because tbe court refused to instruct tbe jury, at tbe request of appellant’s counsel, as follows:

“Before tbe plaintiff can maintain bis suit to recover this $575, tbe school board must be satisfied that tbe plant, put in by tbe plaintiff, is sufficient to warm tbe building in all its parts, in the coldest weather, to a temperature of seventy degrees, — this to be done in connection. with ventilation that would also change tbe air in all parts of the building at least three times an hour. *102nial of its satisfaction, or in making such, claim in bad faith, but the board, acting in good faith, had a right under this contract to withhold this money until they were satisfied that the plant would do the work which the plaintiff had agreed it should do. Now if yon find they were not satisfied of this, the plaintiff cannot recover in this action.”

*101“Tbe school board would not be justified in a capricious de-

*102The request was based on the circumstance that the third payment was payable when the plant was completed, tested, and made to work satisfactorily, and the last payment was not to be payable until the weather was sufficiently cold to demonstrate that the plant was capable of doing the work it was guarantied to do. The learned court seems to construe the word “satisfactorily” as meaning that the plant should, as matter of fact, answer the requirements of the contract in a physical sense and do the work agreed upon. Appellant’s counsel contend the meaning to be that the plant should work satisfactorily to the purchaser, and insist that so long as the members of the board, acting reasonably, were not satisfied, the prime essential to the last payment being collectible was wanting. It seems to us the latter construction is the correct one. In Parr v. Northern E. Mfg. Co. 117 Wis. 278, 93 N. W. 1099, where a similar situation was dealt with, this court so held. There the language considered was this: “The die to be subject to our approval and not to be accepted unless it operates satisfactorily.” The court said in respect thereto:

“The only meaning which can be logically attributed to this contract is that the machine was to operate satisfactorily to the defendant. . . . The respondents seem to claim that, if they could prove by the preponderance of the evidence that the machine in fact did good work, the contract has been fulfilled. This is not the law in this state. When such a contract is made, the article must be, in fact, satisfactory to the purchaser, or he is not bound to take it. . . . His dissatisfaction . . . must be real and in good faith.”

It may have been thought by the learned court by reading that case that the language of the contract classed it with *103those providing expressly that the subject of tbe sale shall be satisfactory to the purchaser; that such feature distinguished the case from this and was the controlling one. Such is not, however, the case. The court regarded the words “unless it operates satisfactorily” by themselves, as meaning, by necessary implication, satisfactory to the purchaser. That is quite plainly indicated by the language of the opinion, notwithstanding cases referred to-, where the words “satisfactory to the purchaser” were used in the contract, since the case was largely grounded on this language in 1 Mechem, Sales, § 664, and supporting authorities, which were brought to the attention of the court:

“In many cases it is expressly stipulated that the sale shall not result unless the buyer is satisfied; but this express stipulation is not necessary. Where a proposition of sale is made to a person upon the condition that he need not purchase unless the article is satisfactory, the necessary inference, even in the absence of an express statement, is that he need not buy unless the article is satisfactory to him.”

The following authorities support the text: Singerly v. Thayer, 108 Pa. St. 291, 2 Atl. 230; U. S. Electric F. A. Co. v. Big Rapids, 78 Mich. 67, 43 N. W. 1030; Adams R. & B. Works v. Schnader, 155 Pa. St. 394, 26 Atl. 745; Brown v. Foster, 113 Mass. 136. In Singerly v. Thayer, supra, the court said:

“He, therefore, was the person to decide and declare whether it was satisfactory. He did not agree to accept what would be satisfactory to others, but what was satisfactory to himself. This was the fact which the contract gave him the right to decide. . . . He was the person who was to test it and to use it. No other persons could intelligently determine whether in every respect he was satisfied therewith.”

That applies very aptly to the case in hand. The agreement, in effect, was that the proper officers of the appellant should determine the question whether the apparatus was or was not satisfactory to it in view of the clause of the contract *104that it should do the work satisfactorily, as regards heating and ventilation, as specified. The court ignored that very valuable feature of the contract and submitted to the jury the question which the parties agreed should be decided by appellant’s officers.

There are authorities which support a different construction of such contracts as the one before us, as will readily be seen by an examination of those cited in the note to the text in Mechem which we have quoted. It seems, however, that the view taken by this court is the correct one. The natural inference from language in a sale contract stipulating that the subject thereof shall be of a specified character and be accepted and paid for only upon its proving satisfactory, is that the person to be satisfied is the purchaser; that the words “to the purchaser” or some equivalent words after the word “satisfactory” are to be regarded as a part of the contract by reasonable if not necessary implication.

Complaint is made because the court instructed the jnry, in effect, that if respondent did not satisfactorily complete the contract he was yet entitled to recover the actual value of the plant as he installed it at the time of the installation thereof, less payments made by appellant. The instruction is erroneous on several grounds:

(a) There being no basis in the complaint for a recovery quantum meruit, none was proper without an amendment thereto. Trowbridge v. Barrett, 30 Wis. 661; Thomas v. Hatch, 53 Wis. 296, 10 N. W. 393; Manitowoc S. B. Works v. Manitowoc G. Co. 120 Wis. 1, 97 N. W. 515.

(b) There was no proper evidence of the reasonable value of the plant on the basis of the contract rate, supporting a claim for recovery quantum meruit. So there was but one course to pursue and that was to dismiss the complaint. Manitowoc S. B. Works v. Manitowoc G. Co., supra.

(c) In case the complaint and evidence were sufficient to support a recovery quantum meruit, it was error to instruct *105the jury that the measure thereof was the actual value of the plant, less payments made. Such a rule, as counsel for appellant well contend, would permit the jury, upon competent evidence of the facts, to compel a purchaser to pay more for an inferior article than the contract price for a good one. The proper measure of recovery in such circumstances, as we have indicated, is the reasonable value at the contract rate, not exceeding the contract price, less payments made. Manitowoc S. B. Works v. Manitowoc G. Co., supra; Bishop v. Price, 24 Wis. 480; Walsh v. Fisher, 102 Wis. 172, 78 N. W. 437. In two of the cases cited this court quoted, with approval, from Allen v. McKibbin, 5 Mich. 449, 455, as a clear explanation of the foundation principle governing such situations, this language:

“A party in default can never gain by his default, and the other party can never be permitted to lose by it; and the price thus determined is the true basis of recovery on a quantum meruit."

In 3 Sutherland, Damages (3d ed.) § 711, the subject is treated at length, this language being used:

“Hence the amount which may be recovered is the amount by which, were no payments made, the defendant would profit at the plaintiff’s expense; that is to say, the amount which represented the fair market value of the structure which, against the wishes of the defendant, has been put upon his land. This value the plaintiff must prove before he can recover. If the contract is a beneficial one to the landowner the contractor is not entitled to recover any margin of the benefit which the former secured by the making of the contract ; but the contractor is entitled to the value of the building as it is in the light of the landowner’s right to have the building built, and properly built, for the contract price.”

(d) The contract being entire the respondent was not, in any event, entitled to recover -quantum meruit for mere partial performance, as a matter of course.. In such a case, in the nature of things, there is no opportunity to accept or re-*106jeet the defective work by merely keeping it or returning it. It is incorporated into tbe proprietor’s property in such a way as to render him substantially powerless to do otherwise than to accept whatever is delivered. In such circumstances, notwithstanding mere part performance by the contractor in good faith and some enrichment of the proprietor at the contractor’s expense, under .the rale prevailing in this jurisdiction there can be no recovery at all without proof of acceptance other than such as is inferable from the mere fact that the improvement is retained and used. Manitowoc S. B. Works v. Manitowoc G. Co. 120 Wis. 1, 97 N. W. 515; Fuller-Warren Co. v. Shurls, 95 Wis. 606, 70 N. W. 683; Williams v. Thrall, 101 Wis. 331, 16 N. W. 509; Sherry v. Madler, 123 Wis. 621, 101 N. W. 1095. The evidence in this case certainly did not show, as a matter of law, any election to take the plant irrespective of whether it was defective or not. So the instruction wholly ignoring that subject, or assuming there was an acceptance because appellant did what it could not reasonably avoid doing, indicates that the learned court followed authorities in other jurisdictions than our own, of which it must be confessed there are many, and respectable ones too.

The only assignment of error remaining not sufficiently covered by those already discussed is that the verdict is contrary to the law and evidence. It is manifestly contrary to the law, as we have seen, mainly because the law was not coi rectly given to the jury. It was also contrary to the evidence in view of the law as it should have been given to them, as we have also seen. The evidence that appellant, acting in good faith through its officers, was dissatisfied with the plant seems conclusive. There was no evidence to warrant a recovery quantum meruit. If the jury found that the contract was substantially performed, which is left in much doubt by the way the case was submitted, we are inclined to agree with appellant’s counsel that the verdict is contrary to the evi*107dence on that point. We are unable to find any satisfactory evidence in the record that the capacity of the plant to warm the building to a temperature of seventy degrees in the coldest weather was established. The test relied upon was made-when, at the best for respondent, the temperature was but a few degrees below zero, — not the coldest weather by any means liable to occur in the climate of southern Wisconsin, as abundantly appears from the evidence, and which we may well say is a matter of common knowledge.

Other points bearing on the question of whether there Was substantial performance of the contract, such as that the air in the rooms should be changed three times per hour, the foul-air system and the ventilation of the building should be. improved and the dry-closet system should not be impaired, we shall not refer to in detail. It is sufficient to say that if the jury had, on the evidence, found against appellant on the question of substantial performance, laying aside Its right to pass on the response to the contract as to the working capacity of the plant and such response in fact, and the trial court, with appreciation of the legal limitations of that term, refused to set the findings aside, the verdict could not properly be disturbed, even if it be true, as claimed, that the evidence greatly preponderates against such finding. The agreement as to the performance of the plant when in operation in the coldest weather was the principal matter. Without some reasonable showing for respondent on that point, there is no foundation for a verdict of substantial performance. We are inclined to hold that such evidence. does not appear in the record. Possibly, if it were clear that the jury,.under proper instructions, found for respondent in respect thereto, and the trial court in ruling on the motion had that in mind, the verdict could not be disturbed. But the jury were not furnished any guide whatever as to what constitutes “substantial performance.” The case was given into their hands for consideration in such a way that they might have reached this con-*108elusion, and yet believe there was no such performance. The situation of the case is such, in any view that can be taken of it, that it must be retried. Therefox^e it is not thought best to analyze the evidence carefully as to whether it would sustain a finding favoi’able to respondent, though, as indicated, we are not entirely clear on the point.

The learned coui't, though using the term “substantial performance” many times in the instimctions as to each paidicu-lar feature of the agreement, yet singularly, as we have said, failed entirely to enlighten the jury as to what was meant thei'eby. That is a very unsafe way to submit a case. It is very liable to i*esult in the jury not passing upon the vital point at issue. The term ‘‘substantial pei'formance” is by no means without limitation of a legal nature. The role allowing a recovery on a contract for such performance is equitable in its nature. It is really a judicial invasion of stidct contract right out of l’egard for the contractor who would otherwise, without bad faith, but through mere inadvertence, suffer great or substantial loss, and the proprietor be correspondingly enriched, perhaps obtaining for all practical purposes just what he contracted for. Reing a relaxation which modifies the contract without the prepi’ietor’s consent, much care should be taken not to pei'nxit its abxxse to the latter’s prejudice, who is entitled, in strict right, to just what he contracted for and in the form agreed upon. To that end the jury should not be left to apply the role without any guide. They should be instructed that “substantial performance” means strict performance in all essentials necessary to the full accomplishment of the purposes for which the thing contracted for was designed. Failure as to any of such features, whether in good faith or bad faith, any departure from the contract, not caused by inadvertence, or unavoidable omission, any defect so essential “as that the object which the pai’ties intended to accomplish to have a specified amount of work pei'fonned in a particular manner is not accomplished,” *109is inconsistent with substantial performance of tbe contract. Manitowoc S. B. Works v. Manitowoc G. Co. 120 Wis. 1, 97 N. W. 515; Woodward v. Fuller, 80 N. Y. 312; Phillip v. Gallant, 62 N. Y. 256. Care should be exercised also to distinguish between that “substantial performance” enabling the contractor to recover upon the contract, and that other such compliance spoken of in the books, furnishing a basis for relief regardless' of the attitude of the proprietor as regards acceptance of the work, so long as he in fact, though unavoidably, has the benefit of what is done. The doctrine that a recovery can be had grounded upon the latter species of substantial performance prevails in many, and perhaps most, jurisdictions at this day. 3 Sutherland, Damages, § 711. It was adopted in Massachusetts as early as 1828 (Hayward v. Leonard, 7 Pick. 181), and has been there since firmly adhered to, as the numerous cases found cited in the text in Sutherland show. Authorities in other states that have adopted the same rule are there referred to in connection with the statement that the weight of modern authority is in harmony therewith. However, in this state if there were at any one period, as shown by the decided cases, some tendency in the same direction, it will be found that for a long period reaching up to the present time the adjudications have been in harmony to the contrary, the most recent cases being Manitowoc S. B. Works v. Manitowoc G. Co., supra, and Sherry v. Madler, 123 Wis. 621, 101 N. W. 1095.

Great caution should also be exercised, in submitting a case like this to a jury for a finding quantum meruit, to keep in mind, first, to authorize such a recovery the pleading, either originally or by amendment, should furnish a legitimate basis therefor; second, there must be acceptance, as before indicated, other than by doing what is unavoidable; third, the rate of recovery is not the reasonable or actual value in a general sense, but the reasonable value on the basis-of the contract rate. If, for instance, a contract calls for a *110structure at a price -which, is hut fifty per cent, of the reasonable value thereof, and the contractor fails to even substantially perform, but the circumstances are such that he is entitled to a recovery quantum meruit, the measure thereof is quantum meruit fro rata, or fifty per cent, of th,e reasonable value of the .structure in a general sense, that being the reasonable value to the proprietor under the circumstances, which is all he can be equitably required to pay.

Recapitulating, the important points to be observed on a retrial of this case are :

1. No recovery can be had on a contract, in any event, in the absence of satisfactory proof of at least "substantial performance," as that term has been explained, or a waiver thereof.

2. No recovery can be had on the contract, if the defendant, acting in good faith, was not satisfied with the plant.

3. No recovery can be had for mere substantial performance, except subject to such deductions from the contract price as will make appellant good for the difference between substantial and full performance.

4. No recovery can properly be had quantum meruit without a basis in the pleading therefor, and without proof of actual acceptance of the work.

5. If the work was accepted so that a recovery quantum meruit is permissible, the amount thereof must not be on the basis of the actual value, or the reasonable value in the ordinary sense, but on the basis of the reasonable value to the appellant in view of the contract, as before indicated.

By the Court. — The judgment is reversed, and the cause remanded for a new trial.

midpage