This is an action to foreclose a mechanic’s .lien, filed against moneys due or to' grow due the defendants, the surety companies, which, for brevity, will be designated the fidelity and bonding companies respectively, on a contract between the Armstrong & > Bolton Company and the city of New York,, bearing date, .the 20th. day of April, 1899, for the construction of the high and low-pressure steam plant, dynamo and electric lighting plant and. .'kitchen in the new city prison at Centre, Franklin and Leonard streets, for tile gross sum of $93,325. The Armstrong &.Bolton Company abandoned the work and the fidelity and bonding companies performed it as sureties. " ,
The Armstrong & Bolton Company, the original contractors, abandoned the contract in March, 1900. The fidelity and bonding companies were duly notified of the default of their principal and called upon to perform. They thereupon took charge of the work, and through the defendant Wood, who was their duly authorized. agent, and, in his name, made a sub-contract.with the Barron & Cooke Heating and Power Company, which will be referred to
Wbod, representing the fidelity and bonding companies, also con
The claim and lien of the Pierce Company now held by the trustee in. bankruptcy and the judgment recovered will, for the sake of brevity, be.referred to as those of the Pierce Company.
The more important propositions presented on the appeal will be stated and discussed separately.
First. The personal judgment in favor of Kieley cannot be sustained. Unless the fidelity and bonding companies and Wood, appellants, have waived their right to object to a recovery by Kieley of a personal judgment against them herein, it would seem,,under well-settled principles, that his failure to file a lien is fatal to the judgment in his favor. If he had in good faith filed a lien he might have recovered a personal judgment even though the lien were declared invalid; but, having filed no hen, he had no standing to institute a suit in equity in his own behalf. And if he-could not have brought the action he cannot, as a defendant, recover affirmative relief on a purely legal claim, unless the appellants have clearly ■waived their right to a jury trial and have submitted their liability to the decision of the court herein. (Deane Steam Pump Co. v. Clark, 84 App. Div. 450; S. C., 87 id. 459 ; Masons' Supplies Co. v. Jones, 58 id. 231; affd., 172 N. Y. 598 ; Nussberger v. Wasserman, 40 Misc. Rep. 120,125.) The plaintiff alleged that Kieley completed the contract as assignee of the Barron & Cooke Company. Kie'ley, in his answer, admits that he completed the work, but denies that he • . did so as assignee of his principal. He neither alleges that he completed it under, a new and independent contract with Wood of the fidelity and bonding companies, whom Wood represented, nor did he demand a personal judgment against them. His only prayer for relief is that the complaint be dismissed “ and. that lie have such other and further relief in the premises as may seem just and proper and as may be warranted by the proofs adduced at the trial.” Having filed no. lien he was not entitled to any part of the fund which was the subject of the litigation, because that fund, barring the statutory rights of lienors, was due and payable to the contractors; and having failed to' demand a personal judgment against the fidelity and bonding companies, or a determination of any controversy between him and
The further contention that the judgment should be sustained ' upon the ground that the court was empowered by section 3403 of the Code of Civil Procedure to determine the equities between the parties and that at the close of the case the parties acquiesced in the announcement of the court’s intention to determine the equities , between the defendants, is not tenable. Counsel were justified in inferring that the court contemplated nothing more than what was ■ authorized by said Section of the Code of Civil Procedure; and that only authorizes an adjudication upon ^equitable claims and confers no authority to award .judgment upon. legal claims like that of' Kieley. (Alyea v. Citizens’ Savings Bank, 12 App. Div. 577; affd., 162 N. Y. 597.)
Second, The judgment dismissing the liens of the plaintiff and of defendant Daniels is erroneous, and they are entitled to a reversal. . The findings that Kieley did not undertake to complete the contract as surety and that he acted under a new and independent contract, are, if supported at all by evidence, against the weight of the evidence ; and the- conclusion of law that he is, therefore, entitled to the fund, is' erroneous. ' Pursuant to the terms of the. contract, Wood gave Kieley notice of the default of his principal and called upon him to perform.; Kieley had ail interview with Wood as the result of that notice. He did not decline to perform as surety. He knew that if he did not perform, Wood could complete and charge the cost over and above the balance unpaid on the contract to him. Both he and Wood expressly testified that he elected to and did undertake to perform as surety. This was his right under the principles of subro
It is not necessary .to decide whether the defendant Daniels should
The objection now raised that her answer has not been served on her codefendants against her right to a judgment of foreclosure, with leave to sue the principal and surety on the undertaking given' to discharge her lien, may, if deemed fatal, be obviated before the new trial. Some parts of the opinion in Martin v. Fiahive (112 - App. Div. 347) appear to he inconsistent with these views, but they were not essential to the decision. There a lienor of a sub-contractor sued to foreclose his lien. The sub-contractor had failed to complete, and the general contractor then undertook to" complete on account of his sub-contractor. He, too, failed to complete, and then the owner performed on his account. It was held that the lien attached to the surplus owing to the contractor after deducting the cost of completion. The court, however, observed that the position of the general contractor in taking charge and completing was the same as if they had been the assignee of their sub-contractor’s contract or his sureties, and cited /among other authorities therefor, Harley v. Mapes Reeves Construction Co. (supra), an opinion written by the same justice, which held that where a surety com- . pletes, the lien attaches to the entire balance unpaid,' without deduction for the cost of completion, and Smith v. Lange (supra) where this court held the same as between a lienor and the assignee of the contractor.
■ Third. The court was not warranted in decreeing a judgment of ■ foreclosure of the Pierce Company’s lien without the presence of the Eddy Company, the sub-contractor for whom it did the work and furnished the material. The judgment, although in form only
The learned counsel for the Pierce Company maintains broadly that neither contractors nor sub-contractors are necessary parties to the action. The fidelity and bonding companies. were not only-interested as claimants • to the fund adversely to the Pierce Company, but they as contractors had bonded the lien' and thereby
It would seem also, although it is not now necessary to decide the proposition, that the answer of a lienor setting up his lien and claim and demanding a judgment of foreclosure which would entitle him to part of the fund, or become the basis of an action on the bond, even though no personal judgment be demanded, should be served on the contractor and sub-contractor when made parties to the suit. Otherwise, they have no notice, of the claim to enable them to litigate it, and the judgment demanded is, in effect, a determination . of the ultimate rights between defendants. (Code Civ. Proc. § 521.) In Wilson v. Niagara City Land Co. (79 Hun, 162) two justices expressed the opinion- that a defendant lienor was not required to serve his answer setting up his lien upon the owner; but the positions of owner and contractor are quite different. In Ostrander v. Heart (130 N. Y. 406) — not an action to foreclose a mechanic’s lien, however — it'was decided that a judgment against the plaintiff in favor of one defendant determines nothing as between ■ the defendant and a codefendant unless the answer was served upon the codefendant. (See, also, Savage v. City of Buffalo, No. 1, 49 App. Div. 577 ; Balch v. City of Utica, No. 2, 42 id. 567; Freem. Judg. [4th ed.] § 158; 2 Black Judg. [2d ed.] § 599; Edwards v. Woodruff, 90 N. Y. 396 ; Albany City Savings Inst. v. Burdick, 87 id. 40 ; Beveridge v. N.Y.E.R. R. Co., 112 id. 1; Stephens v. Hall, 2 Robt. 674; Tracy v. N. Y. Steam Faucet Co., 1 E. D. Smith, 349, 354, 355.) If on the trial the plaintiff had consented to discontinue'the action, or to a dismissal of the complaint, it is difficult to see how any issue would remain to be tried, if the answering lienors had not served their answers upon the contractor, who, owing to the fact that the lien liad been transferred to the undertaking, was the.only party in interest. If the answer of the Pierce Company, asserting its lien and demanding judgment on its claim,
Fourth. The other lienors should, also have-been . brought in. Formerly an action to foreclose a mechanic’s lien.might have been .brought against the owner alone,.and prior lienors were not neces- ■ sary parties unless the plaintiff questioned the validity or" priority of their liens; but subsequent lienors who desired to contest .the validity Or priority of the plaintiff’s lien might have been admitted as parties On their own motion. (Sullivan v. Decker, supra; Foster v. Skidmore, 1 E. D. Smith, 719 ; Kaylor v. O' Connor, Id. 672; Kenney v. Apgar, 93 N. Y. 539.) Later, by .section-17 of chapter 342 of the Laws of 1885, subsequent lienor's and incumbrancers were required to be made parties in an action brought to foreclose a lien in a court, of. record. (Brown v. Danforth, 37 App. Div. 321; Egan v. Laemmle, 5 Misc. Rep. 224, 227.) Now, however, by an.express provision of the Code, all.lienors, whether prior or subsequent, are declared to be. necessary parties, to such an action, in a court of record. (Code Civ. Proe. § 3402), and even if. omitted by mistake or through an irregularity in indexing the liens, they must be brought in on motion by the plaintiff, or by order of the court on its own motion. (Gass v. Souther, 46 App. Div. 256;
It follows that the judgment, in so far as it has been appealed from, should be reversed and a new trial granted, with separate bills of costs to the appellants appearing separately to abide the event.
Patteííson, P. J., Clarke and Scott, JJ., concurred; Ingraham, J., concurred in result.
Judgment, in so far as appealed from, reversed, and new trial ordered, costs to apjoellants appearing separately to abide event. Settle order on notice. -
See Lien Law (Laws- of 1897, chap. 418), § 20, subd. 5, added by Laws of 1898, chap. 169, and amd. by'Laws of 1902, chap..- 37.— [Rep.
See Laws of 1897, chap. 418, § 20, subd. 5, added by Laws of 1898, chap. 169, and amd. by Laws of 1902, cha'p. 37.— [Rep.