76 Cal. 578 | Cal. | 1888
Suit to foreclose laborers’ liens. The plaintiff is the assignee of twenty-six liens for labor performed upon certain mining claims owned and operated by the Big Flat Gravel Mining Company. The proceedings arose under and are to be governed by the law as it stood in 1880. Each lien is set up in a separate count. The court below gave judgment for the plaintiff, and the appeal is by the company and one Paris, who held a judgment lien.
1. The contract set forth in the notices of lien are different from the contracts set forth in the complaint. The notices all set forth contracts for labor at a fixed rate. The lien of. Heath, which is the first in the complaint, may be taken as a type of them all. Its statement of the contract is as follows, viz.: That the company “ entered into a contract with said S. R. Heath, under and by virtue of which said labor was performed, and the following is a statement of the terms, time given, and condition of said contract: To work at general blacksmithing in and upon said premises for an indefinite time, at the rate of seventy-five ($75) dollars per month, payable on demand.” In addition to the above, all the liens (except that of Heath) speak of “the contract price.” Independent of these latter words, however, we think it
Such difference was a ground of demurrer for ambiguity. (Frazer v. Barlow, 63 Cal. 71.) The demurrer specified the ambiguity, and should have been sustained. In addition to this, the notices of lien, when offered in evidence, were objected to on the ground of a variance; and it was error to overrule said objections.
The foregoing is sufficient to dispose of the appeal; but inasmuch as certain questions, which will arise upon a retrial, have been argued, we proceed to consider them.
2. It is contended for appellants that there was a misjoinder of causes of action. The facts are, that the company owned about five hundred acres of placer-mining ground, which (according to the map at page 380 of the
The position is, in the first place, that the cause of action as to the John Mains claim should not have been joined with the cause of action as to the whole five hundred- acres, and that said five hundred acres consisted of at least four separate claims, which should not have been joined with each other or with the ditch; and in the second place, that there is stated a cause of action as to certain machinery, “ giants,” pipe, etc., which, if “ lienable ” at all, ought not to have been joined with the claims.
We do not think there was a misjoinder. Section 1195 of the Code of Civil Procedure provides that “any number of persons claiming liens may join in the same action.” This provision, it will be observed, does not say whether the lien must be all upon the same property or simply against the same person. We' incline to the former construction. But we think that since the several claims all adjoin each other, with the ditch as a
Taking the several claims to constitute one piece of property for the purposes of the mechanic’s lien law, we think there was no misjoinder of causes of action. All the liens were upon the John Mains claim, and the ditch and improvements, and the fact that three of them included something further is not material. The court can adjust the rights of the parties by its decree. (See, generally, People v. Hager, 52 Gal. 171; Brady v. Kelly, 52 Cal. 371.)
With reference to the iron pipe, giants, etc., we think they must be regarded as part of the mine, whether they were attached to it or not; for the Civil Code provides that all “machinery or tools used in working or developing a mine are to be deemed affixed to the mine.” (Civ. Code, sec. 661.)
The complaint is not very satisfactory in some of the above respects; but as the case must be reversed for the matter first mentioned, it can be amended so as to conform to the principles above stated.
3. It is contended for the appellants that the statement in the notices of lien as to the name of the person
4. It is urged that several of the claims are not “lien-able.”
The lien of Heath shows that he was a blacksmith. He worked in the blacksmith-shop, which was upon the property, sharpened picks and drills, made pipe, and did other necessary work. It is said that this was not labor upon the mining claim. But, as we have shown, the tools and machinery used in working and developing a mine are “deemed affixed to the mine.” (Civ. Code, sec. 661.) Hence it would seem to follow that work upon the tools and machinery, while they are so used, is work upon the mine. This applies to several liens.
The notice of lien filed by Ah Jake states that “the said Big Flat Gravel Mining Company was to pay to the said Ah Jake the sum of fifty dollars per month for his individual labor and services, and also the further sum of one dollar per day for the labor of one certain class which he might furnish, and the sum of one dollar and twenty-five cents per day for the labor of another certain class.” It is said that Ah Jake could not have a lien for the labor which he furnished in accordance with the above; that the laborers so furnished should have filed liens themselves; and that there could not be two liens for the same labor.
It will be observed that the contract stated in the notice of lien is, that the sums to be paid for laborers furnished by Ah Jake are to be paid to him. He was the original contractor, and the laborers were the subcon
There are some small matters shown by the evidence which are not “lienable,” as, for example, the deer and bear meat supplied by Morris. This should be deducted from the amount due him; but we do not think it vitiates his lien for what was due. We do not deem it incumbent upon us to go through the mass of small details collected by counsel for appellants. It is sufficient to say that the character of the work should not be scrutinized too strictly. If the labor had a legitimate connection with the working of the mine, it is sufficient within the meaning of the lien law.
5. It is contended that where the laborers worked by the month, the notice of lien should be filed within thirty days from the end of each month. This assumes that each month is separate and distinct from every other month, and requires a separate notice of lien. But we do not think that this can be implied from the words “ within thirty days .... after the performance of any labor in a mining claim.” Upon the same reasoning, we should have to say that persons who worked by the day should file a separate notice for each day’s work.
The other points do not require special notice. We therefore advise that the judgment be reversed, and the cause remanded, with directions to sustain the demurrer, with leave to amend.
Belcher, C. C., took no part in this opinion.
For the reasons given in the foregoing opinion, the judgment is reversed, and cause remanded, with directions to the court below to sustain the demurrer, with leave to amend.