Malden Mills Industries, Inc. v. Maroun (In Re Malden Mills Industries, Inc.)Malden Mills Industries, Inc. v. Maroun (In Re Malden Mills Industries, Inc.)
I. BACKGROUND AND PROCEDURAL HISTORY
On February 1, 1990, Malden Mills Industries, Inc. (the “Debtor”) and Alfred G. Maroun (“Maroun” or the “Landlord”) entered into a lease (the “1990 Lease”) pursuant to which the Debtor leased 40,000 square feet in a 250,000 square foot mill building in Lawrence, Massachusetts, built around 1910 and known as the Loomweve Building (the “Building”). Under the terms of the 1990 Lease, Maroun was responsible for making “all reasonably required non-structural repairs of the leased premises” and for maintaining “the structural integrity of the leased premises and the building which the leased premises are part, including without limitation, the integrity of the roof and its support structure.” In 1996, the Debtor needed additional space for one of its divisions that was destroyed by fire in December 1995. Accordingly, the Debtor and Maroun agreed to amend the lease and the Debtor was allowed to take possession of the entire Building. In order to accommodate its operations, the Debtor needed to retrofit the Building which involved removing some interior partitions and walls, cutting holes in the second floor, upgrading the electrical and plumbing services, and installing a “tank farm,” i.e., a series of tanks used to mix chemicals needed to process goods. Maroun consented to these modifications in writing. • At the time of the lease amendment in 1996, the Debtor commissioned an appraisal of the Building which documented without specificity the poor condition of the Building at the time, including a leaking roof and rotting floors. The 1990 Lease, as amended, expired on August 31,1999.
On November 1, 1999, the Debtor and Maroun entered into a new lease (the “1999 Lease”). Under the 1999 Lease, the responsibility for making structural repairs to the Budding was assigned to the Debtor. The Debtor was required to maintain the Building “in as good a condition and repair as at the beginning of the Term, reasonable wear and tear only excepted.” In the 1999 Lease the word “Term” is defined as the period “from November 1,1999 and through October 31, 2006.” As part of the 1999 Lease, the parties expressly agreed to rescind the 1990 Lease, the amendments thereto, and the Debtor’s notice of its intention to exercise an option to purchase the Building contained in an April 4,1996 letter.
On November 29, 2001, the Debtor filed a bankruptcy petition under Chapter 11. The Debtor promptly sought to reject the
On March 4, 2002, Maroun filed a proof of claim seeking $4,479,702.45. The claim consisted’ of two components: $1,965,918.45 for rent and taxes due through the end of the 1999 Lease term and $2,513,784.00 for damage to the Building resulting from alterations and deterioration. On August 2, 2002, the Debtor filed an objection to Maroun’s claim.
Maroun filed a motion for summary judgment on or about September 12, 2002, requesting that the bankruptcy court grant him summary judgment as to certain matters pending in an adversary proceeding between the parties, most importantly with respect to the Debtor’s objection to Maroun’s claim. The Debtor filed a cross-motion seeking summary judgment in its favor. On October 24, 2002, the bankruptcy court issued an order granting summary judgment in part to the Debtor and limiting Maroun’s lease rejection damages to $413,176.08.
The bankruptcy court held an evidentia-ry hearing on December 2 and 6, 2002, on the remaining issues raised by the parties, specifically, the outstanding issues regarding the Debtor’s objection to Maroun’s claim, the Debtor’s motion to abandon the personal property left in the Building, Maroun’s motion to compel the Debtor to pay postpetition use and occupancy charges related to the ongoing presence of the personal property in the Building, and the Debtor’s complaint against Maroun for turnover. On January 29, 2003, the bankruptcy court entered a series of orders that generated the appeals in these cases. The court reaffirmed its summary judgment findings on Maroun’s lease rejection damages and capped them at $413,176.08. The court allowed Maroun’s claim for damage to the Building in the amount of $2,513,784.00. The court entered an order allowing the Debtor’s abandonment of the personal property left at the Building but ordered the Debtor either to remove the personal property from the Building or to reimburse Maroun for the cost of removal within thirty days of the court’s order. Lastly, the court entered an order compelling the Debtor to pay Maroun use and occupancy charges of $200,002.00 1 for the period from January 28, 2002, the effective date of the lease rejection, through January 27, 2003, as well as an additional $547.93 per day until the personal property was removed from the Building. The court further determined that the Debtor did not possess an easement to use and maintain steam pipes that run through the Building and awarded $1.00 for use and occupancy of the Building by the steam pipes.
II. JURISDICTION
The Bankruptcy Appellate Panel (the “Panel”) has jurisdiction to hear ap
III. STANDARD OF REVIEW
We review factual findings for clear error and legal conclusions
de novo. Werthen v. Werthen (In re Werthen),
IV. DISCUSSION
The parties to these appeals have raised a number of interrelated issues involving the obligations of a chapter 11 debtor in possession and the claims of a lessor of nonresidential real property upon rejection of an unexpired lease and abandonment of personal property at the former leased premises. The Debtor and the official committee of unsecured creditors (the “Committee”) as appellants and cross-ap-pellees collectively raise four issues:
1.Whether the bankruptcy court erred in determining that the Debtor was liable to the Landlord for alterations and deterioration to the Building?
2. Whether the bankruptcy court erred in assessing damages for the alterations and deterioration of the Building at $2,513,784.00?
3. Whether the bankruptcy court erred in imposing use and occupancy charges and the costs of removal of abandoned personal property against the Debtor as administrative expenses?
4. Whether the bankruptcy court erred in ruling that the Debtor did not possess an easement to maintain a steam line in the Building?
The Landlord also raises four issues as appellee and cross-appellant:
5. Whether the bankruptcy court erred in limiting the Landlord’s claim for breach of the 1999 Lease upon rejection to $413,176.08?
6. Whether the bankruptcy court erred in limiting the damages against the Debtor for continued use of the steam pipe to $1.00?
7. Whether the bankruptcy court erred in limiting the Landlord’s claim for administrative use and occupancy charges for storage of abandoned personal property to only the portion of the Building in which such property is actually stored, rather than the entire Building?
8. Whether the bankruptcy court erred in allowing the Debtor to present the testimony of an expert as a rebuttal witness?
The factual and legal arguments surrounding these issues are interwoven in the fabric of this case and the provisions of the Bankruptcy Code.
2
Accordingly, the Panel shall discuss these issues in the context of the application of specific provisions of the Bankruptcy Code, and the policy judgments implicit in those provisions, to the
For the reasons set forth in this opinion, we affirm in part, vacate in part and remand to the bankruptcy court for proceedings consistent with this opinion.
A. Landlord’s Claim for Prepetition Damage to the Building
1. Liability of the Debtor
The largest portion of Maroun’s claim is based upon damage to the Building. Mar-oun’s right to recover money for such damage arises under one or more of the parties’ agreements, specifically, the 1990 Lease, the 1999 Lease, and any amendments thereto. Accordingly, the Panel must determine whether the bankruptcy court erred in determining that the Debtor was responsible for such damage and that Maroun was entitled to a claim for such damage in the amount of $2,513,784.00.
The construction of a contract, such as a lease, presents a question of law for the court.
Kallman v. Radioshack Corp.,
At the time the Debtor began to lease portions of the Building in 1990, it was responsible for the routine maintenance of the Building while Maroun was responsible for “all reasonably required non-structural repairs” and any structural repairs. This arrangement was not altered by various amendments to the 1990 Lease nor by the April 1996 letter in which Maroun consented to the Debtor’s proposed modifications to the Building that would permit the Debtor to move one of its operations into the Building. At the time of the Debtor’s bankruptcy filing the operative agreement between the parties was the 1999 Lease. Under the 1999 Lease, the Debtor was required to maintain the Building “in as good a condition and repair as at the beginning of the Term, reasonable wear and tear only excepted,” with the Term being defined as the period “from November 1, 1999 and through October 31, 2006.” Responsibility for making structural repairs to the Building was also assigned to the Debtor. As part of the 1999 Lease, the parties agreed to rescind the 1990 Lease, the amendments thereto, and the Debtor’s notice of its intention to exercise the option to purchase contained in the April 1996 letter.
There is no ambiguity in the 1999 Lease regarding the obligations for maintenance and structural repairs. Under the clear terms of the 1999 Lease, the responsibility for maintenance and structural repairs fell on the Debtor. The Debtor agrees that these were its responsibilities. However, the Debtor argued below that Maroun was not entitled to his claim for damage arising out of the failure to make structural repairs because the damage that he complained of occurred prior to the term of the 1999 Lease which commenced November 1,1999.
Under Massachusetts law, the general rule for measuring damage to real property is the diminution in market value or the cost of repair.
See Trinity Church v. John Hancock Mut. Life Ins. Co.,
However, recovery of repair costs is limited to the reduction in market value of the premises.
Belkus,
Although the general rule for measuring property damage is diminution in market value, “market value does not in all cases afford a correct measure of indemnity, and is not therefore ‘a universal test.’ ”
Trinity Church,
Where replacement or restoration cost is used as the measure of damages, a
It is clear that the standard for measuring damage to realty in Massachusetts is diminution in market value or the cost of curing the injury, whichever is less. In unusual situations, restoration costs may be awarded but must be adjusted for depreciation and obsolescence. 3
3. The Damage Award
At trial, the Debtor’s appraiser testified that the value of the Building, as of September 24, 1999, was $645,000.00 using the sales comparison approach and $650,000.00 using the income approach. Maroun presented evidence that the cost to restore the Building to its pre-Malden occupancy was $2,513,784.00. The bankruptcy court found that the Debtor’s appraiser based his values on the Building containing 166,100 square feet while the parties had agreed that the Building contained approximately 250,000 square feet. Consequently, the bankruptcy court discounted the reliability of the Debtor’s appraisal. The bankruptcy court rejected the Debtor’s argument that it was not liable for damages to the Building prior to the commencement of the 1999 Lease based upon certain circumstances and occurrences during the term of the 1990 Lease. Specifically the bankruptcy court found that:
1. Maroun purportedly did not have access to the building after April 1996 and therefore he did not know about the level of destruction that had been visited upon his property.
2. The Debtor always led Maroun to believe that it intended to exercise its option to purchase the Building.
3. The Debtor did not notify Maroun about the deteriorating condition of the Building.
Based upon its finding that the Debtor’s appraisal evidence was unreliable and the Debtor’s conduct under the 1990 Lease, the bankruptcy court awarded Maroun a claim in the amount of the cost to restore the Building to its condition prior to the Debtor’s occupancy. 4
The bankruptcy court did not explain why the apparently unambiguous language of the 1999 Lease with respect to the beginning of the Term coupled with the recision of the 1990 Lease and the exercise of the option to purchase does not limit Maroun’s claim for damage to the Building to injury occurring after November 1,
Accordingly, the portion of the bankruptcy court’s order allowing Maroun’s claim in the amount of $2,513,784.00 shall be vacated and the determination of Mar-oun’s claim for damages to the Building shall be remanded to the bankruptcy court for proceedings consistent with this opinion.
B. Debtor’s Abandonment of Personal Property in the Building
1. Effective Date of Abandonment
The Debtor filed a motion to abandon personal property and fixtures located in the Building on April 22, 2002. The bankruptcy court entered an order allowing the Debtor’s abandonment on January 29, 2003, but ordered the Debtor either to remove the personal property from the Building itself or to reimburse Maroun for the cost of its removal within thirty days of the court’s order. The Debtor and the Committee have appealed that order on the grounds that the bankruptcy court erred in not permitting retroactive abandonment of the personal property and by conditioning the Debtor’s abandonment where such property was not necessary for the preservation of the Debt- or’s estate. Maroun did not appeal the Court’s order allowing the Debtor to abandon the property.
Section 554 of the Bankruptcy Code- provides that “[a]fter notice and a hearing, [a debtor in possession] may abandon any property of the estate that is burdensome to the estate or that is of inconsequential value and benefit to the estate.” Upon abandonment the property reverts to the party with the possessory interest.
In re A.J. Lane & Co., Inc.,
The Debtor argues that it provided notice of its abandonment of the property in a pleading dated January 29, 2002, entitled “Response of Debtors to Motion by Alfred G. Maroun for Relief from Judgment or Order and Request for Authority to Abandon Certain Property,” in which it indicated its intent to abandon the tanks, after appropriate notice under the federal and local bankruptcy rules had been provided. The Debtor filed a separate motion to abandon on April 22, 2002, in which it asked the bankruptcy court to authorize and approve the abandonment of all property at the Building, other than property subject to its alleged utilities easement for the steam pipes, as of January 28, 2002, the date the 1999 Lease was deemed rejected. In its oral decision, the bankruptcy court did not order abandonment retroactive to January 28, 2002, or to April 22, 2002, the date the motion was filed; rather, it appears to have ordered abandonment effective January 29, 2003, the date of its order, subject to further conditions regarding removal and reimbursement.
In
Thinking Machines Corp. v. Mellon Fin. Servs. Corp. (In re Thinking Machines
While the Panel agrees with the Debtor, the Debtor’s argument ignores a statutory distinction between the rejection of a real estate lease and the abandonment of personal property by a trustee. Section 365(a) provides that a trustee may assume or reject an executory contract or unexpired lease “subject to the court’s approval.” Section 554 provides that “after notice and a hearing” the trustee may abandon property of the estate. The language in these two sections of the Bankruptcy Code is not identical. Assumption or rejection of an executory contract or unexpired lease is explicitly subject to the court’s approval while abandonment of property does not require court approval unless challenged by a party in interest.
See Erickson v. Baxter Healthcare, Inc.,
Accordingly, where abandonment has been challenged and thus is subject to review by the court, the date of any approved abandonment should be the date the notice or motion for abandonment was filed. However, in light of the decision in Thinking Machines, a bankruptcy court may, based upon specific findings and an appropriate record, order that such abandonment should have either retroactive or prospective effect. Because the bankruptcy court failed to explain why it ordered abandonment effective the date of its order the Panel vacates that portion of the abandonment order awarding a priority administrative claim for use and occupancy and determining January 29, 2003 as the effective date of abandonment. On remand the bankruptcy court should consider the effective date of the Debtor’s abandonment in light of this opinion and the decision of the First Circuit in Thinking Machines.
2. Conditions on Abandonment
With respect to the bankruptcy court’s conditioning the Debtor’s abandon
The bankruptcy court did not make a finding that the property left behind in the Building, which the Debtor sought to abandon to Maroun, posed an imminent threat to the public’s health and safety nor did the court articulate any other basis for imposing conditions as an exception to the abandonment power vested in a trustee or debtor in possession. In the absence of sufficient reason for limiting the abandonment power of the debtor in possession, the Panel must vacate that portion of the bankruptcy court’s order imposing conditions (i.e. removal of abandoned property) on abandonment. The Panel will address below whether, as a separate matter from the abandonment issue under § 554, the Debtor should be obligated to pay as an administrative expense the cost to have the abandoned property removed from the Building.
C. Landlord’s Damages for Debtor’s Rejection of the 1999 Lease
Section 365(d)(4) of the Bankruptcy Code provides that a nonresidential real property lease shall be deemed rejected unless it is assumed within sixty days after the order for relief. Section 365(g) of the Bankruptcy Code deals with the effect of rejecting an unexpired lease and provides that rejection constitutes breach of the lease immediately before the date of the filing of the petition. Rejection of a lease under § 365 is the equivalent of a termination by breach. Lawrence P. King,
Collier on Bankruptcy
¶ 502.03[7][b] (15th rev. ed.2003). The effect of such a breach is to permit a landlord, such as Maroun, to seek the allowance of its claim under § 502.
See In re Fin. News Network, Inc.,
Section 502(b)(6) limits the claim that a landlord may have for damages resulting from the termination of a lease.
The claim of the landlord for damages resulting from termination of. a lease islimited to the rent reserved by the lease, without acceleration, for the greater of either one year or 15 percent, not to exceed three years, of the remaining lease term following the earlier of the petition date or the date on which the landlord repossessed or the lessee debt- or surrendered the property. In addition, the landlord is afforded a claim for any unpaid rent due under a lease, without acceleration, as of either the date of the filing of the petition or the date on which the landlord repossessed the premises or the lessee surrendered them, whichever is earlier.
Lawrence P. King, Collier on Bankruptcy ¶ 502.03[7][a].
In the instant case, the Debtor’s rejection of the 1999 Lease was effective January 28, 2002, sixty days after the Debtor filed bankruptcy. The bankruptcy court ruled pursuant to § 502(b)(6) that Mar-oun’s damages arising from the Debtor’s rejection were capped at $413,176.08. The court based its ruling on the Debtor’s admission that one year’s rent totaled $413,176.08, which amount was greater than the rent owed for fifteen percent of the remaining term under the 1999 Lease.
The Landlord has appealed the bankruptcy court’s order on the grounds that the court erred in ruling that the 1999 Lease was a true lease and not a lease intended as security and that therefore the cap of § 502(b)(6) applied. In making its decision, the bankruptcy court reviewed the record before it wherein consistently from the beginning of the Debtor’s Chapter 11 proceedings Maroun had characterized the 1999 Lease as a true lease. The Panel does not find that the bankruptcy court committed clear error. It is apparent from the record that Maroun claimed the lease was intended as security only at some later date in the Debtor’s case. Maroun never raised the issue in the context of the Debtor’s lease rejection motion, Maroun’s motion for relief from the court’s rejection order, the parties’ stipulated order regarding lease rejection, Maroun’s motion to compel payment of postpetition use and occupancy charges, his response to the Debtor’s motion to abandon property, or the parties’ amended joint stipulation filed prior to the evidentiary hearings held in December 2002. For that reason, the bankruptcy court did not err in concluding that Maroun was judicially estopped from raising the issue. The bankruptcy court’s determination of the damages awarded to Maroun under § 502(b)(6) shall be affirmed.
D. Administrative Claim for Post-rejection Use and Occupancy
The bankruptcy court determined that the Debtor continued to occupy the Building post-rejection by virtue of leaving substantial quantities of personal property on the premises and, therefore, Maroun had an allowed administrative claim in the amount of $200,002.00 plus $547.93 per day after January 28, 2003. However, the bankruptcy court made a mathematical error in calculating the amount of the claim; under the court’s rationale the administrative claim should total $187,502.00 in addition to a per day charge of $513.70.
6
The
1. Claim for Use and Occupancy
The test described by § 502(b)(6) is the exclusive test concerning damage claims of landlords for termination of leases of real property; however, this section does not purport to limit administrative expense claims by landlords based upon postpetition use of the leased premises. Lawrence P. King,
Collier on Bankruptcy
¶ 502.03[7][g]. Prior to rejection, the Bankruptcy Code requires the debtor in possession to timely perform all of the obligations under a lease.
See
11 U.S.C. § 365(d)(3). Once a lease is rejected, the lessor’s rights under § 365(d)(3) cease.
In re Almac’s, Inc.,
Upon termination of the 1999 Lease on January 28, 2002, the Debtor had an obligation under state law and the 1999 Lease to return the Building to Maroun free from personal property.
First Republic Corp. of Am. v. BayBank,
The basis of liability for use and occupancy by a tenant at sufferance is the tenant’s continued control over the premises which effectively deprives the owner of the use of the property.
Lowell Hous. Auth.,
The bankruptcy court awarded what it considered an appropriate use and occupancy charge for that portion of the Building used and occupied by the Debt- or’s personal property during the period between lease rejection and the time the property was to be removed from the Building. The Panel finds no error in the bankruptcy court making an award based upon only the space actually used by the Debtor and not the entire Building. The bankruptcy court’s decision does not reflect, however, any consideration of Mar-oun’s duty to mitigate damages. In Massachusetts, commercial landlords have a common law duty to mitigate the damage caused by a holdover tenant.
Krasne v. Tedeschi and Grasso,
In addition, any determination regarding Maroun’s claim for the value of the Debtor’s continued use and occupancy of the Building after lease termination will be affected by the bankruptcy court’s decision regarding the effective date of the Debtor’s abandonment of the property.
The failure to consider the impact of Maroun’s duty to mitigate damages or the impact of Massachusetts law after the effective date of the Debtor’s abandonment of the property would constitute a reversible error of law. If the bankruptcy court did consider those provisions of Massachusetts law on the allowed claim for post-rejection damages, the Panel is unable to review the bankruptcy court’s decision in the absence of any discussion or analysis by the bankruptcy court. Accordingly, the bankruptcy court’s determination of the amount of damages for post-rejection use and occupancy shall be vacated and remanded for proceedings consistent with this opinion.
2. Administrative Priority of Claim for Use and Occupancy
Under § 503(b)(1) a landlord may be entitled to a priority administrative claim for services provided during the postpetition, post-rejection period. Lawrence P. King,
Collier on Bankruptcy
¶ 502.08[2][a] (“If pursuant to an executory contract or lease, a debtor has possession of property of a nondebtor party, section 502(g) does not preclude the nondebtor party from seeking an allowed administrative expense for the value of the use of its property between the date of the filing of a debtor’s petition and the date of the surrender by the debtor of the property. This is because the basis for the potential administrative expense claim does not depend upon the terms of the provisions of the rejected contract or lease but rather arises under the standards contained in section 503 of the Bankruptcy Code.”). Thus, “[t]he failure to ‘immediately surrender’ the premises after a debtor rejects a lease may create an administrative rent claim and other consequences for a debtor .... § 503(b)(1)(A) governs the determination of postpetition rent owed to a lessor for the period after rejection of the lease until the property is vacated.”
Roberds, Inc.,
Section 503(b)(1)(A) provides that the bankruptcy court shall permit as an administrative expense “the actual, necessary costs and expenses of preserving the estate.” The First Circuit Court of Appeals has stated that “[i]n general, for a claim to qualify as an administrative expense under subsection 503(b)(1)(A), (1) it must have arisen from a transaction with the trustee or debtor in possession, rather than from a prepetition transaction with the debtor, and (2) the consideration supporting the claim must have benefitted the estate in some demonstrable way.”
Mason v. Official Comm. of Unsecured (In re
The First Circuit Court of Appeals has relied upon the United States Supreme Court’s statements in
Reading Co. v. Brown, 391
U.S. 471,
This circuit has extended the rule of Reading Co. to cover a civil compensatory fine imposed in a state court nuisance action ...; costs incurred by a purchaser of contaminated property from the debtor-in-possession for which the debt- or-in-possession was liable under federal environmental law ...; and penalties imposed by state environmental law....
Boston Reg’l Med. Ctr.,
The First Circuit Court of Appeals has clearly stated that granting priority status to creditors is contrary to the fundamental principle of bankruptcy law that a debtor’s limited resources should be distributed equally among similarly situated creditors and thus statutory priorities should be narrowly construed.
FBI Distrib. Corp.,
The Panel finds
Woburn Associates v. Kahn (In re Hemingway Transp., Inc.),
In making its determination that the Debtor should be responsible, on an administrative basis, for paying Maroun use and occupancy based on the presence of personal property in the Building after the 1999 Lease was deemed rejected, the bankruptcy court stated simply that it would be “unfair” for the Debtor to shift the cost for cleanup and removal to Maroun. Transcript at 19. However, both the record below and the bankruptcy court’s decision were devoid of evidence or analysis of the requirements of § 503(b)(1)(A) and whether the estate received a benefit from leaving personal property and debris in the Building after rejection of the lease. In the absence of any postpetition business activities by the Debtor in the Building or any exigent circumstance such as an imminent threat to public health or safety, it is difficult to find a basis for any allowed claim for post-rejection damages to be entitled to administrative priority. Accordingly, that portion of the bankruptcy court’s order awarding a priority administrative claim to Maroun for any post-rejection damages shall be vacated and remanded to the bankruptcy court for further proceedings consistent with this opinion.
E. Debtor’s Claim of Easement for Steam Pipes
“An easement is an interest in land which grants one person the right to use or enjoy land owned by another.”
Cheever v. Graves,
“The decision to allow or foreclose rebuttal evidence rests squarely within the informed discretion of the district court.”
Faigin v. Kelly,
The bankruptcy court’s factual findings underlying its decision that the Debtor did not possess an express easement are reviewed for clear error while its legal conclusion as to the nonexistence of the express easement is entitled to plenary review.
See Gallo-Mure v. Tomchik,
V. CONCLUSION
For the reasons discussed above, the Panel’s conclusions regarding the issues raised on appeal are as follows:
1. That portion of the bankruptcy court’s order determining that Mar-oun had a claim for deterioration to the Building is vacated and remanded to the bankruptcy court for proceedings consistent with this opinion.
2. That portion of the bankruptcy court’s order determining Maroun’s claim for deterioration to the Building at $2,513,784.00 is vacated and remanded to the bankruptcy courtfor proceedings consistent with this opinion.
3. That portion of the bankruptcy court’s order determining the amount and priority of Maroun’s claim arising from the abandonment of property located in the Building is vacated and remanded to the bankruptcy court for proceedings consistent with this opinion.
4. The bankruptcy court’s determination that the Debtor did not possess an easement to maintain a steam line in the Building is affirmed.
5. The bankruptcy court’s determination of Maroun’s claim for damages arising from the rejection of the 1999 Lease at $413,176.08 is affirmed.
6. The bankruptcy court’s determination of Maroun’s damages arising from the continued use and occupancy by the Debtor’s steam pipes at $1.00 is affirmed.
7. The bankruptcy court’s determination that Maroun’s damage claim based upon use and occupancy charges for storage of abandoned personal property to only the portion of the building in which such property is actually stored, rather than the entire building, is affirmed.
8. The bankruptcy court’s decision to permit the Debtor to present the testimony of an expert as a rebuttal witness on the steam pipe easement issue is affirmed.
Notes
. This amount consisted of an award of $125,000.00 based on storage of the Debtor's personal property and debris in the Building, $75,000.00 based on the presence of the tank farm, $1.00 based on the presence of steam pipes, and $1.00 to reimburse Maroun the cost of removing some of the personal property from the premises. As explained in section IV.D of this opinion at footnote 6, the bankruptcy court’s award contained a mathematical error.
. In this opinion the term "Bankruptcy Code” shall mean Title 11 of United States Code.
. Where restoration is not reasonably necessary in light of the damage inflicted or the cost of restoration is unreasonable (i.e. due to obsolescence of the property), no restoration costs may be awarded.
Trinity Church,
. It is not clear from the record on appeal whether “pre-Malden occupancy” refers to the time immediately before the beginning of the 1990 Lease or to immediately before the Debtor’s occupancy of the entire Building in 1996.
. In this case, the record is devoid of evidence of the Building being used for a specialized purpose.
. The bankruptcy court stated that it was awarding an administrative claim for use and occupancy "based upon the approximate rental rate for the space actually used." Transcript at 14. The bankruptcy court considered the testimony of each side’s experts and determined that on an annual basis $2.50 per square foot was reasonable. The bankruptcy court then determined that the Debtor continued to use 50,000 square feet in the Building for storage of debris and 25,000 square feet based on the presence of the tank farm for a total of 75,000 square feet. The bankruptcy court then arrived at a claim of
. As the party asserting the existence of the easement, the Debtor had the burden of proof on the issue. See
Swensen v. Marino,