Malcuit v. Equity Oil & Gas Funds, Inc.Malcuit v. Equity Oil & Gas Funds, Inc.
Honest Malcuit, plaintiff-appellee, granted Buckhorn Oil Company (“Buck-horn”), predecessor in interest of Equity Oil & Gas Funds, Inc. (“Equity”), defendant-appellаnt, an easement across his farm for a pipeline right-of-way. The easement was properly recorded. In consideration for this eаsement, Buckhorn agreed to provide free gas to Malcuit’s farm. Equity obtained Buckhorn’s interest in the pipeline agreement at a foreclosure sale. The agreement is silent as to its duration.
Malcuit filed a declaratory judgment action and requested injunctive relief to stop Equity from removing the pipeline. The trial court held that Equity could not remove the pipeline under these circumstances and that Equity must continue to рrovide free gas to Malcuit. Equity appeals, raising five assignments of error.
Before addressing the assignments of error, we must note that no transcriрt of proceedings was.filed with this court. A review of the record reveals that appellant Equity failed to file a praecipe with the court reporter or file a copy of the transcript with the clerk of courts.
Assignment of Error I
“The trial court should have applied the law of negotiation of written contracts. As a matter of law, there should be no significance between printed and typed contractual provisions when thе same are negotiated. The plaintiff-appellee specifically agreed that the grantor’s rights could not interfere or be incоnsistent with the grantee’s rights. This plain and unambiguous
Equity argues that the court erred by giving preference to typеd provisions over printed provisions. We do not agree. The typed provision in question states in part:
“2. Buckhorn Oil will put in a gas tap (for free gаs for Malcuit Farm, no cubic feet limit). Gas will not be shut off if wells are shut down.”
This provision was typed at the end of a form contract. The printed provision provides that Malcuit grants “ * * * the right of way to lay, maintain, operate, inspect, replace, and remove a pipe line for the transportation of natural gas and other gaseous products * * 1
It is well settled in Ohio that the typed portion of a contract will prevail over the printed portion, if the two are inconsistent.
O’Neill v. German
(1951),
The first assignment of error is overruled.
Assignment of Error II
“The typewritten phrases should have been strictly construed against the plaintiff-appеllee. The trial court was in error by not construing the typewritten phrases against the plaintiff-appellee. After doing so, the printed and typewritten terms of the contract are reconcilable. The trial court was in error by finding these phrases to be irreconcilable.”
Equity asserts in its second assignment of error that the trial court erred by not construing the typed provision against Malcuit. We do not agree.
This court addressed a similar question in
Raphael v. Flage
(Sept. 20, 1989), Lorain. App. No. 89CA004539, unreported,
The primary rule of construction applied in
Raphael
was consideration of circumstances under which the writing was made. Where application of this rule makes the meaning of the languаge clear, the secondary rule of construction of strict construction against the drafter is not applicable.
Id.,
citing Williston,
supra,
at 760, Section 621. Many other decisions have reached the same result. See,
e.g., Alexander v. Buckeye Pipe Line Co.
(1978),
In the case at bar, the meaning of the disputed provisions was clear following thе application of the primary rule of construction. Therefore, the secondary rule was inapplicable, and the court cоrrectly did not construe the language against Malcuit.
The second assignment of error is overruled.
Assignment of Error III
“The trial court was in error in ruling that the intentions of the parties did not include a limited duration to thе agreement. This is because the right of removal does directly affect the duration of the contract.”
Equity argues in its third assignment of error that the рarties intended a limited duration by including a removal right in the easement. We do not agree.
When the duration of an easement is not expressly stated, as in the case at bar, the duration depends upon a reasonable construction of the language to effect the reasonable intention of the parties deducible from the words employed, as applied to the surrounding circumstances.
Hieatt v. Morris
(1860),
The third assignment of error is overruled.
“IV. The trial court was in error in ruling that thе parties’ contractual agreement implied an unlimited duration. As a matter of law, abandonment of a contract is sufficient to conclude its duration. Equity’s unconditional, intentional and voluntary notice of relinquishment was sufficient to conclude the parties’ agreement. In addition, cirсumstances surrounding the creation of the agreement show that abandonment and the right of removal were essentially the same.
“V. The trial court’s decision was in error by the manifest weight of evidence. The negotiations of the parties as well as the plaintiff’s agent’s understanding of the agrеement demonstrated that the right to remove the pipeline was applicable regardless of any other negotiations or parоle [sic] evidence.”
Assignments of error four and five both require reference to the transcript of proceedings, and therefore will be addressed together.
In its fourth assignment of error, Equity alleges that it proved it abandoned the easement and that Malcuit presented insufficient evidеnce to prove that the parties intended to delete the removal right from the contract. In its fifth assignment of error, Equity asserts that the trial cоurt’s judgment was against the manifest weight of the evidence. As already indicated, no transcript of proceedings was filed with this court.
Without an adequаte record, this court is unable to determine whether Equity proved abandonment, whether Malcuit presented insufficient evidence in support of his claim, or whether the trial court’s judgment was against the manifest weight of the evidence.
Volodkevich v. Volodkevich
(1989),
Accordingly, the fourth and fifth assignments of error are overruled.
The judgment of the trial court is affirmed.
Judgment affirmed.
Notes
. The words "change the size of, relocate” have been crossed out following the word "replace” in this provision.