37 Ind. App. 469 | Ind. Ct. App. | 1906
Campbell, a subcontractor, sued the contractor and also the lot owners to recover an amount due him from the contractor and to foreclose a mechanic’s lien. The contractor, Reed, filed a cross-complaint against the lot owners — appellants—to foreclose a mechanic’s lien. The lot owners filed a cross-complaint against the contractor for damages for failure to comply with the contract.
So far as necessary to determine the questions presented, the facts found by the court are substantially as follows: On June 10, 1903, appellants contracted in writing with appellee Reed to construct a building, on lots owned by them, according to plans and specifications prepared by an
As conclusions of law the court found: ’ (a) That as between Campbell and appellants the law is with appellants ; (b) that Campbell should recover from Reed $121.12; (c) that Reed should recover from appellants $736.38 and $80 attorney’s fees, and have his lien foreclosed. Decree accordingly, and that each party to the •suit should pay the costs which each has occasioned.
The answer alleged that the expense incurred by appellants on account of the failure of Eeed to comply with the contract had been audited by the architect and was in a sum named, that Eeed had been notified thereof, and that he had not appealed from the architect’s decision and had not resorted to arbitration as the contract provided.
The parties might properly agree that any controversy or dispute arising under the contract should be submitted for determination to the architect, and it must be shown that such a condition precedent was performed before bringing suit, or a valid reason shown for its nonperformance. But that provision of the contract which assumes to make the decision of the architect, or of an arbitrator, final, is void. It is not competent for parties to a contract, in advance of any dispute, to oust the jurisdiction of the courts by providing that the decision of a party therein named upon a dispute which might thereafter arise shall be final and conclusive. Supreme Council, etc., v. Forsinger (1890), 125 Ind. 52, 9 L. R. A. 501, 21 Am. St. 196; Louisville, etc., R. Co. v. Donnegan (1887), 111 Ind. 179; McCoy v. Able (1892), 131 Ind. 417; Supreme Council, etc., v. Garrigus (1885), 104 Ind. 133, 54 Am. Rep. 298;
In the ease at bar there is a sharp conflict in the evidence upon the material facts at issue between the owners of the building and the contractor. In a case involving many items, extra work and material, and changes in the original contract, it would be expected, as was the case here, that there would be some conflict of opinion among candid witnesses well informed as to the matters about which they testified. Upon a careful consideration of the evidence we can not say that there is not sufficient evidence fairly to support the conclusion reached by the trial court. There is evidence in the record to support the findings of fact, and, while the findings are not as full in some respects as they might have been, yet they are sufficiently full to authorize the conclusions of law as announced by the court. We can not say that we would, from the evidence, have found the facts in all respects as the trial court did; but whether we would or would not have done so is not material, where it must be said that there is evidence in the record supporting the findings as announced by the court. The question is not what conclusion we would have reached from the testimony introduced at the trial, but whether there was evidence authorizing the trial court to reach the conclusion it did.
Judgment affirmed.