Mainstreet Makeover 2, Inc. v. Meenakshi SrinivasanMainstreet Makeover 2, Inc. v. Meenakshi Srinivasan
Ordered that the judgment is modified, on the law, (1) by deleting the provision thereof granting that branch of the petition which was to annul so much of the determination of the Board of Standards and Appeals of the City of New York dated December 13, 2005, as denied the appeal from so much of the determination of the Staten Island Borough Commissioner of the Department of Buildings dated April 22, 2005, interpreting the applicable zoning regulations to include a certain retaining wall within the definition of “structure,” and thus to include the construction of the retаining wall within the definition of a “development” pursuant to
In November 2002 the petitioner sought and received approval from the Department of Buildings of the City of New York (hereinafter the DOB) of its pre-consideration request to “enlarge the existing house [on the subject premises] and tо replace and relocate the existing square footage so as to be in compliance with existing zoning and to upgrade the structural integrity of the structure.” Upon receiving such approval, the petitioner filed a site alteration permit application describing the project as a “[h]orizontal and vertical enlargement as well as a relocation of existing square footage.” The petitioner submitted plans along with the application which proposed a complete demolition of the existing building and construction of a new building on a different portion of thе lot. The DOB approved
On May 18, 2004, following an inspection of the premises, the DOB issued a “notice of violation and hearing” (hereinafter the notice) to the petitioner, in which it asserted that the work was being performed without a demolition permit in violation of
On June 9, 2004, the DOB placed a “hold” on the original building permit, apрarently determining that the petitioner should have sought a new building permit for the work being performed. On October 13, 2004, the City of New York Environmental Control Board dismissed the notice upon a finding by an administrative law judge that the DOB‘s approval of the pre-consideration application in 2002 obviated the need for a demolition permit.
By letter to the New York City Department of City Planning (hereafter the DCP) dated November 16, 2004, the petitioner requested confirmation that the erection of a retaining wall is neither a “site alteration” nor a “development” as defined by
The petitioner subsequently requested that the DOB remove the “hold” status so that the building permit could be renewed and reinstated. On April 22, 2005, the Staten Island Borough Cоmmissioner of the DOB denied the petitioner‘s request on the ground, in effect, that the DCP determined that the petitioner must obtain CPC approval pursuant to
The petitioner appealed the April 22, 2005, determination to the Board of Standards and Appeals of the City of New York (hereinafter the BSA), again seeking to have the “hold” status removed so that the building permit could be renewed and reinstated.
On October 7, 2005, during the pendency of the BSA appeal, the DOB sent the petitioner a “notice of intent to revoke approval and permit” pursuant to
On December 13, 2005, after a hearing and upon accepting submissions by the parties, by a vote of zero in favor and three in opposition to the appeal, the BSA adopted a resolution which, in pertinent part, found that (1) the DOB‘s application of the relevant definitions to the construction of the dwelling and wall at the premises was correct, and (2) the DOB‘s refusal to lift the “hold” and reinstate the permit and application approval for failure to submit the proposal to the CPC was an appropriate exercise of its jurisdiction. Specifically, the BSA found that the construction of the new residence and the retaining wall each indeрendently satisfied the definition of “development” under
The petitioner commenced the instant proceeding against the BSA and the DOB pursuant to
We note that the petitioner seeks review not of the DOB‘s initial placement of the “hold,” but rather of the BSA‘s affirmance оf the DOB‘s denial of the request to lift the “hold.” Since the DOB‘s denial of the petitioner‘s request to lift the “hold” was based upon the DCP‘s determination that the erection of the retaining wall required CPC approval, the subject of the retaining wall was very much at issue at the hearing before the BSA, and, contrary to the finding оf the Supreme Court, was properly raised before the BSA and the Supreme Court. Thus, the Supreme Court erred in failing to consider any arguments relating to the retaining wall or to consider that portion of the BSA‘s determination which was based upon its findings as to the retaining wall.
The BSA, consisting of experts in zoning and planning, is the ultimate administrative authority charged with enforcing the ZR (see
Turning to the determination with respect to the demolition of the existing premises and the construction of a new residence on another portion of the subject lot, the parties do not disputе that this portion of the construction project would typically fall under the definition of a “development” within the meaning of
In making its determination on the appeal from the DOB‘s denial of the petitioner‘s request to lift the “hold” on the building permit application, the BSA, like the DOB, determined that the new construction constituted a “development” requiring CPC approval pursuant to
Mastro, J.P., Florio, Miller and Dickerson, JJ., concur.