Lead Opinion
In the Energy Policy Act of 1992, Congress imposed liability upon nuclear electric power companies that had purchased
In Commonwealth Edison Co. v. United States, No. 00-5069, also decided today, this court en banc has upheld the constitutionality of that statutory assessment against similar challenges, namely that it takes the property of another utility and denies that utility due process. That decision binds this panel, and requires us to reject the utilities’ taking and due process arguments in the instant case.
Two of the utilities in this case, Maine Yankee Atomic Power Company and Sacramento Municipal Utility District, also argue that the statute denies them equal protection — a contention not made in Commonwealth Edison. As the Court of Federal Claims stated, the utilities argued that “the fact that foreign utilities were exempted from the assessment impermissibly differentiates between similarly — situated entities — i.e., all those that had consumed government-enriched uranium. In addition, plaintiffs contend, the Act draws an illegitimate distinction between purchasers who resold the uranium, and those who kept it for their own purposes, as well as between pre 1992 consumers (who are subject to the fee) and post 1992 consumers (who are exempt).” Maine Yankee Atomic Power Co. v. United States,
The Court of Federal Claims correctly rejected those contentions. We rely upon and accept that court’s reasoning:
With regard to Congress’s decision to exempt foreign utilities from liability, we refer to the Supreme Court’s observation in Barclay & Co. v. Edwards,267 U.S. 442 , 451,45 S.Ct. 348 ,69 L.Ed. 703 (1924) that “[c]onsiderations of policy toward foreign countries may very well justify an exemption of the foreign corporations from taxes that might legitimately be imposed on them, but which Congress does not think it wise to exact.” In addition, we think it significant that, as defendant points out in its motion to dismiss, the exclusion of foreign utilities from the liability equation in no way increases or otherwise affects plaintiffs’ portion of domestic utility usage.
Similarly, legislatures need not burden the most responsible party to survive rational basis review. Association of Bituminous Contractors, Inc. v. Apfel,156 F.3d 1246 , 1255-56 (D.C.Cir.1998). While the original purchasers of uranium (those who resold it and were therefore exempt from assessment) may seem, to plaintiffs, equally to have benefited from the enrichment services, we cannot conclude that Congress’s decision to target end-users was without rational basis. And although plaintiffs may have preferred a system under which USEC’s post 1992 customers likewise picked up the tab, Congress’s assignment of liabili*1360 ty for a past problem to past consumers does not stretch the limits of the reasonable.
Id.
The judgments of the Court of Federal Claims dismissing the complaints are
AFFIRMED.
Concurrence Opinion
Concurring opinion of
in which MAYER, Chief Judge, joins.
Since I agree that we are bound by Commonwealth Edison and also agree with the court’s rejection of the equal protection contention, I join in the opinion and judgment of the court. If I were not bound by Commonwealth Edison, however, I would hold that the retroactive assessment denies the appellants due process. My reasons for that conclusion follow.
I
A. During World War II, the United States began enriching uranium, first for military purposes and, starting in the mid 1960s, as nuclear fuel for commercial generation of electricity, which it sold to domestic and foreign utilities. Maine Yankee Atomic Power Co. v. United States,
Congress dealt with this problem in the Energy Policy Act of 1992 (“the. Act” or “the Energy Act”). See generally id. That was comprehensive legislation designed to implement a “national energy policy,” a reaction, at least in part, to the adverse economic effects of an oil embargo associated with the military conflict in the Persian Gulf. H.R.Rep. No. 102-474(1), at 132 (1992), reprinted in 1992 U.S.C.C.A.N. 1953,1955.
In this legislation, Congress sought to “reform the current uranium enrichment program of the [government] so that it will be operated in a more business-like fashion.” H.R.Rep. No. 102-474(I), at 142 (1992), reprinted in 1992 U.S.C.C.A.N. 1953, 1965. The Act established the United States Enrichment Corporation (“Enrichment Corporation”) as a government corporation to assume the operation of the government’s uranium enrichment services, 42 U.S.C. § 2297, and “which eventually could be sold to the private sector.” H.R.Rep. No. 102-474(I), at 142-43 (1992), reprinted in 1992 U.S.C.C.A.N. 1953, 1965-66. The Act required that the Enrichment Corporation “[w]ithin 2 years prepare a strategic plan for transferring ownership of the Corporation to private investors.” 42 U.S.C. § 2297d(a). The “key purposes of the Corporation inelud[ed] providing enrichment services in a business-like fashion, maximizing the economic return to the [government].” H.R.Rep. No. 102-474(I), at 198 (1992), reprinted in 1992 U.S.C.C.A.N. 1953, 2021.
The Act provided that the Enrichment Corporation would not be hable for the costs of cleaning up and closing the government’s uranium enrichment facilities. 42 U.S.C. § 2297c-2(d). Instead, the Act established the Uranium Enrichment Decontamination and Decommissioning Fund (“Fund”) for that purpose. § 2297g. The Fund is financed through both Congres
The Fund is instructed to obtain up to $480 million per year (to be adjusted annually for inflation), with at most $150 million from a special assessment on the domestic utilities. § 2297g-1(a), (c). That assessment is based on each utility’s share of the government’s enriched uranium sales (whether purchased directly from the government or from another source), which were made prior to October 24, 1992 and that it did not resell. § 2297g 1(c). The special assessment terminates after 15 years or after $2.25 billion has been collected. § 2297g-1(e).
The Act also provided that the special assessments “shall be deemed a necessary and reasonable current cost of fuel and shall be fully recoverable in rates in all jurisdictions in the same manner as the utility’s other fuel cost.” 42 U.S.C. § 2297g-1(g).
B. The three appellants filed separate complaints in the Court of Federal Claims, as did a number of other similarly-situated electric utilities. They contend that the special assessment constituted a breach of the fixed-price contract under which they had purchased enriched uranium from the government. The complaints included the following factual allegations, which we accept for purposes of the government’s motions to dismiss. Highland Falls-Fort Montgomery Cent. Sch. Dist. v. United States,
The appellants — Maine Yankee Atomic Power Company (“Maine Yankee”), Sacramento Municipal Utility District (“Sacramento District”), and Omaha Public Power District (“Omaha District”) (collectively “the Utilities”) — all operated nuclear power plants and purchased government-produced enriched uranium before 1992. Thus, as domestic utilities that purchased and used government provided enriched uranium, each is liable for a portion of the Act’s special assessment, and each has paid millions of dollars.
The Utilities also allege that the government completely contaminated its enrichment facilities (buildings, equipment, property, and surrounding property) prior to 1969, at a time when they were used almost exclusively for defense purposes. Little, if any, additional contamination occurred after 1969, when these facilities were used to enrich uranium for sale to commercial utilities.
Maine Yankee is a domestic utility that operated a single nuclear power plant, which was permanently closed in 1996. It purchased enriched uranium from the government from 1970 to 1986 under two contracts, one executed on October 2, 1970 and the other on November 4, 1982. On its purchases of government enriched uranium, Maine Yankee is subject to a $25 million special assessment, of which it has paid more than $9.8 million.
Sacramento District is a municipal utility district in California that generates electricity and operated a nuclear generating facility, which it closed in 1989. During the operation of that facility, the Sacramento District purchased enriched uranium from the government, beginning in 1969 and ending in 1981. In 1990, the Sacramento District terminated its contract for purchasing enriched uranium. Because of those purchases, Sacramento District has paid $5.8 million in special
Omaha District is a domestic utility that generates and supplies electricity in Nebraska. It purchased enriched uranium from the government between 1969 and 1992 under two contracts. Omaha District has paid special assessments of more than $7.4 million, and estimates its total liability to be nearly $20 million.
One of the other utilities that filed such a suit in the Court of Federal Claims was Yankee Atomic Electric Company. That court granted Yankee Atomic summary judgment, holding that “the assessment imposed upon Yankee Atomic to fund clean-up costs constitutes an unlawful exaction because it violates the Government’s earlier contractual agreements to supply enriched uranium at fixed prices.” Yankee Atomic Elec. Co. v. United States,
After our decision in Yankee Atomic, the Utilities amended their complaints to assert claims not addressed in Yankee Atomic; namely, that the assessment was a taking of their property and denied them due process in violation of the Fifth Amendment. Maine Yankee and the Sacramento District also asserted that the assessment denied them equal protection.
On the government’s motion, the Court of Federal Claims granted summary judgment dismissing the complaints for failure to state a claim upon which relief could be granted. Maine Yankee Atomic Power Co. v. United States,
In an opinion dealing with the three cases (but issued separately for each case), the court first held that Yankee Atomic was not stare decisis on the constitutional issues the Utilities raised. Maine Yankee,
Whether we analyze the assessment under the Due Process Clause, under the Takings Clause, or under some amalgam of the two, we are, in the end, faced with a single, basic question: Is it inherently unfair, unjust, or irrational for Congress, when faced with costs resulting from the enrichment of uranium, to ask those parties who received the uranium to contribute to the solution? The answer, quite clearly, is no. Plaintiffs’ assessments are directly proportional to their usage of uranium enrichment services the very services which created the contamination. Congress itself took responsibility for more than two thirds of the clean-up costs and assigned the rest, as a general tax, to the rate-payers in*1363 districts which had previously benefited from nuclear power. Such a scheme can hardly be construed as beyond the reach of fairness or rationality.
Id. at 382-83.
Finally, the court rejected the claim that the special assessment denied Maine Yankee and the Omaha District equal protection because it did not cover (1) foreign utilities or (2) utilities that purchased but resold government-enriched uranium. The court denied this claim since “legislatures need not burden the most responsible party to survive rational basis review.” Id. at 383 (citing Ass’n of Bituminous Contractors, Inc. v. Apfel,
II
A. The Supreme Court has noted that “the presumption against retroactive legislation is deeply rooted in our jurisprudence, and embodies a legal doctrine centuries older than our Republic. Elementary considerations of fairness dictate that individuals should have an opportunity to know what the law is and to conform their conduct accordingly; settled expectations should not be lightly disrupted.” Landgraf v. USI Film Prods.,
Another pertinent principle is that economic legislation has a presumption of constitutionality, which may be overcome by demonstrating that the legislation is arbitrary or irrational. Turner Elkhorn,
The special assessment was wholly retroactive: it covered only purchases of enriched uranium before the effective date of the Act. The retroactivity was severe. It reached back to the Utilities’ enriched uranium purchases that occurred up to twenty-two years (or twenty-three years, in the case of Omaha District) before the Act was passed, six years after Maine Yankee had stopped purchasing government enriched uranium, and three years after Sacramento District closed its plant. It also was
The Utilities did not cause or contribute to the contamination of the government’s plants, which the special assessment was designed to cure, and did not benefit from it. The Utilities allege that the contamination occurred prior to the beginning of their purchases, when the plants were producing enriched uranium “almost exclusively” for the military, and that “[ljittle, if any additional contamination” occurred thereafter. Moreover, when the Utilities entered into the purchase contracts at a fixed price, they had no reason to believe, or even suspect, that years later the government would seek to make them pay for a substantial portion of its cleanup costs. They may well have understood and expected that the government would incur substantial expenses in making that cleanup, but they reasonably would have believed that the charges the government made for the enriched uranium included the cleanup cost. They certainly had no basis to expect that they would be subject to the additional large amounts of the assessments.
To be sure, the Utilities benefited from their participation in the government’s uranium enrichment program, but the plant contamination and the cost of cleaning it up arose from an earlier stage of that program (when the Utilities were not participants). For the reasons just given, however, the Utilities’ participation is not a sufficient basis under the Due Process Clause to subject the Utilities to such a substantial portion of the costs of cleaning up the contamination, which they did not cause and from which they did not benefit.
B. The government contends that Usery v. Turner Elkhorn Mining Co.,
The Supreme Court upheld the Act against this challenge. The Court recognized that the legislation imposed new liability for disabilities developed prior to enactment, but concluded that such retro-activity was “justified as a rational measure to spread the costs of the employees’ disabilities to those who have profited from the fruits of their labor.” Id. at 18,
The Court, however, in sustaining the presumptions of the Coal Act relating to
There is a critical difference between Turner Elkhom and the present case that precludes the application of Turner Elkhorn here. In Turner Elkhorn the miners’ illness was caused by conditions that existed when they were working for the company, for which it was responsible and which “profited from the fruits of their labor.” The company, therefore, could fairly be charged with responsibility for its former employees’ condition.
In the present case, however, the contamination occurred before the government sold enriched uranium to the Utilities, which neither were responsible for nor benefited from the contamination. In these circumstances, as shown, it would be unfair and unreasonable to subject the Utilities to a substantial additional charge to cure the contamination they neither caused nor benefited from.
In many (if not most) of the cases in which the Supreme Court rejected Due Process challenges to retroactive legislation, the statute dealt with the relationships, financial and otherwise, among private parties; the government’s role was only the regulation of those relationships. In the present case, however, the statute deals with the relationship between the government and private parties; it seeks to transfer to those parties a substantial portion of the government’s costs of rectifying the contamination of its plants used to produce the product it sold to those parties. It is by no means clear that those Supreme Court cases may be automatically and uncritically applied to the significantly different situation here involved.
C. The government contends that the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (“Environmental Response Act”), 42 U.S.C. § 9601 et seq. (1994), supports the validity under the Due Process Clause of the retroactive assessment of clean-up costs on the Utilities. Among other things, that Act provides for the clean-up of inactive hazardous waste disposal sites and established a Hazardous Substances Response Trust Fund (“Superfund”) to pay for it. The Superfund was funded initially, and in large part, by special taxes on certain petroleum products and chemicals and was to be replenished by assessments on persons responsible for the waste. Hazardous Substance Response Revenue Act of 1980, Title II, Subtitle A
The Environmental Response Act thus retroactively imposes liability on numerous persons for cleanup of pre-enactment contamination.
The government cites two Court of Appeals cases that upheld the retroactive application of the Environmental Response Act against Due Process challenges to its constitutionality, as support for the constitutionality of the retroactive assessment against the Utilities. United States v. Northeastern Pharm. & Chem. Co.,
In the present case, however, the Utilities did not participate in any way, directly or indirectly, or play any role in, the creation of the hazardous conditions at the government’s uranium facilities. The Utilities merely purchased enriched uranium after the contamination had occurred, long before the passage of the Energy Act. The Utilities’ tangential connection with the contamination of the government’s uranium enrichment facilities is quite different from the relationships to the hazardous waste disposal of the persons held constitutionally liable under the Environmental Response Act.
D. The government also contends that because 42 U.S.C. § 2297g-1(g) provides that the assessments “shall be deemed a necessary and reasonable current cost of fuel and shall be fully recoverable in rates in all jurisdictions in the same manner as the utility’s other fuel cost,” the Utilities
It is impossible to predict, however, to what extent (if any) state and local regulatory agencies and courts would permit the Utilities to treat the assessments as a “current cost of fuel” in determining their rates. The question whether § 2297g-l(g) preempts state regulatory authority in this area appears difficult. The power of Congress to require that particular items be included in the Utilities’ costs for rate making purposes is uncertain. Regulation of retail electric power rates is a traditional function of state government. The likelihood of the state action that the government envisions is far too speculative and conjectural to constitute a valid basis for upholding the assessments.
In any event, the question whether, and to what extent, the state regulatory agencies and courts will recognize the assessment as part of the Utilities’ costs for rate making purposes appears more appropriately an issue for the damages phase of these cases than for the liability phase.
E. In sum, I conclude that the Utilities’ complaints have stated a valid claim under the Due Process Clause, and that the Court of Federal Claims erred in dismissing the complaints for failure to state a claim upon which relief could be granted.
