90 N.Y.S. 598 | N.Y. App. Div. | 1904
The second defense contained in defendant’s answer sets up a former judgment between the same parties, which it was claimed was a bar. There being a dispute as to what was admitted and what was denied with respect to the former judgment, it becomes necessary to refer to so much of the pleadings as solves this dispute.
In the 8th paragraph of the second defense it was alleged “ That pn or before the 1st day of November, 1901, plaintiff duly tiled a notice of his alleged claim and lien for the said work and materials set forth in paragraph 61 ’ of the complaint, and claimed a lien therefor on the real estate set forth in paragraph £I’ of the complaint in the office of the Clerk of the County of New York, and on or about the 14th day of January, 1902, began an action to foreclose said lien and for a personal judgment against the defendant Wexler in the Supreme Court of the State of New York, held in and for the County of New York, entitled Frederick J. Ylaeder, plaintiff, against Adolph Wexler and others, defendants.” The reply of the plaintiff to this second defense is as follows : “He denies the allegations of the 8th paragraph of said answer, and alleges that he did file a notice of claim on or about the 1st day of November, 1901, based upon materials furnished and work done under the written contract and the written specifications annexed to the answer and for extra work, and did commence an action to foreclose said lien, alleging full and complete and specific performance of said written contract and written specifications, and not otherwise.”
Standing alone there might be force in the suggestion of the plaintiff that this form of denial was sufficient to raise the issue as to whether the labor and materials embraced in this action were the
We do not think that the plaintiff can seriously contend that the labor and materials embraced in this were not involved in the former action, but what is contended for is that, having alleged and failed to prove the full performance of the written contract, the question of the value of the work, labor and materials furnished was not presented, nor passed upon or decided in the former action.
We agree, therefore, with the learned Apj>ellate Term' that the question of law presented is whether the former action which was brought to foreclose a mechanic’s lien and wherein a personal judgment was demanded, is a bar to this action to recover the value of the same labor and materials upon the theory of a quantum meruit. (See Maeder v. Wexler, 43 Misc. Rep. 16.) It would be impossible in the limits of an opinion to refer to all the cases or to reconcile them because on the subject of res adjudAeata the facts are necessarily decisive of each particular case. So here resort must be had to the nature of the two actions in order to determine whether the plea of res adjudieata or the plea in bar which the defendant urges, and the facts concerning which are in effect admitted by the plaintiff’s reply, is a good defense.
The facts are as follows: A written contract was entered into between the plaintiff and the defendant dated April 11, 1901, for painting, papering, etc., certain houses for the price of $3,300. The contract provided that the work should be done according to certain specifications, and provided further that defendant Wexler should be at liberty to request extra work and that the same should 'be added to the contract by “ a fair and reasonable valuation.” In the former action the plaintiff alleged that he had performed this con
The plaintiff in the present action alleges that at the special instance and request of the defendant he performed work and labor and furnished material in painting, papering, etc., the same houses against which he sought to foreclose a lien in the former action.
We can see no escape from the conclusion that the judgment in the former action is a plea in bar. It is undoubtedly the rule, as said in Kinney v. Kiernan (49 N. Y. 164), that “ the institution by a party of a fruitless action, which he has not the right to maintain, will not preclude him from asserting the rights he really possesses.” We think, however, that where the plaintiff has an election either to sue upon an express contract or to treat that contract as rescinded and to sue upon an implied contract, then, when the election has once been made, and the suit proceeds to judgment and there is an adjudication “upon the merits,” such judgment is a bar thereafter to bringing an action upon another theory. If upon a trial because of insufficiency in the proof there is a dismissal of the complaint, such a dismissal does not prevent the bringing of another action even for the same cause or upon the same or a different theory. Where, however, an action is tried and there is a dismissal upon the merits, the judgment entered upon such dismissal upon the merits is
We do not think that where an action has been brought upon the theory of an express contract and such action tried and judgment entered dismissing the complaint xupon the merits, that a subsequent action can be brought upon the theory of an implied contract. In determining the force and effect which is to be accorded to a judgment dismissing a complaint upon the merits, we must view it in connection with the character of the action and its bearing upon the rights of the parties.
In the case at bar the former action was one not only for the foreclosure of a mechanic’s lien, but one in which a personal judgment was sought, and, upon proper proof, could have been obtained against the defendant. In Booth v. Barron (29 App. Div. 66) it was said: “ This action, though in form one for the foreclosure of a mechanic’s lien, in so far as it is for the recovery of a personal judgment, is governed by the rules applicable to actions for the recovery of money only.” Whether upon the thqory of an express or an implied contract it is apparent that for the work done and materials furnished the plaintiff had a single, indivisible cause of action, and we can find no authority that will permit the plaintiff after having reduced part of the claim to judgment to bring another action to recover the balance of the claim. The first action was upon a written contract and the provision for extra work was part of such contract, and for this the plaintiff has succeeded in obtaining judgment. If the present action upon an implied contract to recover the balance of the claim can be separately brought, then the rule is violated that where all the items spring from a single transaction or are connected by one contract, one action only can be maintained. As said in Secor v. Sturgis (16 N. Y. 554), “ the rule is fully established that an entire claim arising either upon a contract or from a wrong, cannot be divided and made the subject of several suits; and if several suits be brought for different parts of such a claim the pendency of the first may be pleaded in abatement of the others and a judgment upon the merits in either will be available as a bar in the other suits.” And it was held in O'Beirne v. Lloyd (43 N. Y. 248), as correctly stated in the head note, that “ Where an
We think, therefore, that the plaintiff having elected to sue upon the written contract which it was decided was the contract between the parties, and having secured by judgment a part of his claim, he cannot bring another suit for the balance ; and, further, that the part of such judgment which adjudged that he was not upon the merits entitled to foreclose his lien or to have a personal judgment against the defendant for the balance which he alleged was due him, is a bar to the present action to recover for the same work, labor and materials, though brought upon the theory of an implied contract.
It accordingly follows that the determination of the Appellate Term should be reversed, with costs, and the demurrer to the reply sustained, with costs.
Van Brunt, P. J., Patterson, Hatch and Laughlin, JJ., concurred.
Determination reversed, with costs, and demurrer sustained, with costs.